810 CMR 8.09
Submission of Standard Contractor Evaluation Forms by Awarding Authorities
(1) Each Awarding Authority shall submit to DCAM a properly completed Standard Contractor
Evaluation Form for each of the Sub-bidder firms on each Building Project undertaken by such
Awarding Authority within90 calendar days fromCompletionof each Building Project or termination
of a Sub-bidder on a Building Project.
(2) The evaluation form must be completed and signed by one of the following:
(a) For Building Projects that require an Owner’s Project Manager, then said Project Manager
shall complete the Standard Contractor Evaluation Form; or
(b) For Building Projects that do not require an Owner’s Project Manager, thenan official from
theAwardingAuthority,architect/designer representing the Awarding Authority, or any other party
responsible for the oversight of the project shall complete the Standard Contractor Evaluation
Form. An Awarding Authority or Owner’s Project Manager may seek input from the general
contractor in evaluating a sub-bidder’s performance of a Building Project, however, the Awarding
Authority or their representativemust complete and sign the Standard Contractor Evaluation Form.
(3) An Awarding Authority must certify in the evaluation form as to the accuracy of its contents and
shall not negotiate the contents of the Standard Contractor Evaluation Form or the Project Rating with
the Sub-bidder or its representatives for any reason.