810 CMR 9.04
Prequalification Committee
Establishment. When the prequalification process is utilized by an Awarding Authority,
whether mandated or elected by the Awarding Authority, the Awarding Authority shall establish
a Prequalification Committee prior to issuing the RFQ to General Contractors.
(2) Purpose. The Prequalification Committee established by the Awarding Authority shall be
responsible for the evaluation of each General Contractor seeking prequalification for a particular
Building Project. Such evaluation shall be conducted by review of the SOQs (and required
supporting documentation) submitted by General Contractors in response to an RFQ issued by
an Awarding Authority for the prequalification of General Contractors on said Building Project.
(3) Composition. The Prequalification Committee shall be comprised of three representatives
of the Awarding Authority and one representative from the Designer. Where the Building
Project requires an OPM pursuant to M.G.L. c 149, § 44A½, the OPM shall fill one of the three
Awarding Authority seats on the Prequalification Committee. Variance from the aforementioned
size and composition of the Prequalification Committee is prohibited, except as specifically
provided for in 810 CMR 9.00. Whenever the Awarding Authority is prequalifying both General
Contractors and Subcontractors for a particular Building Project, to the extent possible, the
Prequalification Committee members should be the same for the prequalification evaluation of
both.
(a) Awarding Authority Representatives.
1. The Awarding Authority shall appoint three representatives to the Prequalification
Committee who, in the sole discretion of the Awarding Authority, will best serve the
interests of the Building Project. Where a particular Building Project is being undertaken
by one Awarding Authority for the beneficial use of another Awarding Authority, one
representative of the Awarding Authority on the Prequalification Committee may be a
representative of the beneficiary Awarding Authority or user agency.
2. If the Building Project is one where an OPM is required pursuant to M.G.L. c. 149,
§ 44A½, then the OPM shall be one of the three Awarding Authority representatives on
the Prequalification Committee.
3. If the OPM is a third-party, not employed directly by the Awarding Authority, then
the Prequalification Committee services performed by the OPM shall be included in the
scope of work of the OPM’s contract with the Awarding Authority and the costs
associated with the same shall be included in the OPM contract price and specifically
approved by the Awarding Authority. The OPM shall not be entitled to additional
compensation for any work associated with prequalification services provided by the
OPM unless agreed to and approved in writing by the Awarding Authority.
4. If the OPM is not an employee of the Awarding Authority, but a third-party retained
by the Awarding Authority, then the OPM must be independent of the Designer in order
to avoid an appearance of or an actual conflict of interest.
(b) Designer Representative.
1. The Designer Representative shall be an individual person employed by the Designer
who either prepared the design documents for the Awarding Authority and is familiar
with the requirements of the Building Project or who will be the Designer’s designated
representative for said Building Project.
The selection of the Designer Representative must be approved by the Awarding
Authority. The Awarding Authority has the right to reject the Designer Representative
to the Prequalification Committee selected by the Designer where, in its sole discretion,
the Awarding Authority concludes that the inclusion of said Design Representative
would not be in the best interest of the Building Project.
3. The Prequalification Committee services performed by the Designer Representative
should be included in the scope of work of the Designer’s contract with the Awarding
Authority and the costs associated with the same should be included in the design
contract price and specifically approved by the Awarding Authority.
(4) Initial Meeting of the Prequalification Committee. Where the prequalification process is
to be utilized on a Building Project by an Awarding Authority, either by mandate or by the
election of the Awarding Authority, the Prequalification Committee shall convene as soon as
possible upon designation by the Awarding Authority to perform the following administrative
tasks required for the prequalification evaluation process:
(a) Appointment of Chairperson. The Prequalification Committee shall designate one of
the three Awarding Authority members of the Prequalification Committee to be the
chairperson for the committee. The chairperson shall be responsible for the coordination of
meetings and the management of the evaluation process as set forth in 810 CMR 9.09;
(b) Finalize RFQ Form. Upon designation of a chairperson, the Prequalification Committee
shall finalize the RFQ for the Building Project in accordance with the statutory requirements
and evaluation categories set forth in M.G. L. c. 149, § 44D½. The RFQ shall only include
the evaluation categories and criteria set forth in M.G.L. c. 149, § 44D½ and shall be in
compliance with the requirements set forth in 810 CMR 9.05;
(c)
Allocation of Points for Evaluation Subcategories. The Prequalification Committee
shall, prior to the issuance of the RFQ for the Building Project, allocate the points available
in each of the evaluation subcategories set forth in M.G.L. c. 149, § 44D½. The point
allocations for each of the evaluation subcategories are within the discretion of the
Prequalification Committee or as otherwise determined by the Awarding Authority.
(d)
Finalize Statement of Qualifications Form. Included in the RFQ prepared by the
Prequalification Committee, there shall be a SOQ form in a form consistent with the standard
SOQ form prescribed by DCAMM in the DCAMM Guidelines for Prequalification to be
completed by General Contractors interested in being prequalified to bid on the Building
Project. The SOQ form shall only solicit information from interested General Contractors
that is specifically designated in M.G.L. c. 149, § 44D½ and shall conform to the
requirements set forth in 810 CMR 9.06.