811 CMR 3.04
Studies, Programs and Design and Administration of Construction Projects
(1) If the scope of work involves a study or program, a designer may be selected from the list
of consultants who have previously applied to the Board for projects of this nature.
(2)
If the scope of the work involves design and administration of a construction project,
finalists may be selected from the existing standing list of consultants who have previously
applied to the DSB for projects of this nature.
(3) The Chair of the DSB, or in his or her absence, the Vice Chair or senior DSB member, upon
receipt of the declaration by the Commissioner that an emergency exists, will select at least six
finalists as described in 811 CMR 3.04(1) and (2) in consultation with the project manager or
other representative of the planning office.
811 CMR: DESIGNER SELECTION BOARD
10/30/20
811 CMR - 8