958 CMR 10.08
Extension to File a Performance Improvement Plan
(1) Requests for an extension to file a Performance Improvement Plan shall be filed in a manner
and form prescribed by the Commission.
When filing a request for an extension, the PIP Entity shall indicate the requested
submission deadline for the proposed Performance Improvement Plan.
(3) The PIP Entity may submit any documentation or supporting evidence to the Commission
to support the PIP Entity's request for extension.
(4) The Commission may require the PIP Entity to submit any other relevant information it
deems necessary in considering the extension request.
(5) The Executive Director may grant an extension of time, up to 45 days, to file a Performance
Improvement Plan to provide sufficient time for the creation and submission of a plan that will
be reasonably likely to successfully address the underlying cause(s) of the PIP Entity's cost
growth.
(6) Any extension of more than 45 days shall be granted by vote of the Board.
(7) The Executive Director or Board may deny any extension request or grant an extension, as
applicable, for a period of time less than the period requested.
(8) If the Executive Director or Board declines to extend the timeline for the PIP Entity to file
a Performance Improvement Plan, the Commission shall provide written notice to the PIP Entity
stating that its request for extension was denied, the reason for the denial, and that the PIP Entity
shall file a proposed Performance Improvement Plan within 45 days of receipt of the notice of
denial.