958 CMR 7.07
Responses to Information Requests; Timing
(1) Responses to Information Requests. Entities that received information requests pursuant
to 958 CMR 7.05 shall provide information in response to such information requests within 21
days of receipt. The response shall include any written response, information and/or documents
requested by the Commission pursuant to such information requests and may include additional
information.
(2)
Request for Additional Time. Entities that received information requests pursuant to
958 CMR 7.05 may request additional time to provide their written responses and requested
information and documents. Any additional time granted by the Commission to submit
information may be added to the time for completion of the Final Report, pursuant to M.G.L.
c. 6D, § 13 and 958 CMR 7.12.
(3)
Certification of Compliance. Entities that received information requests pursuant to
958 CMR 7.05 shall certify substantial compliance with the Commission's information requests
on the date determined by the Commission.