980 CMR 16.02
Definitions
The definitions in 980 CMR 1.01(4): Definitions shall apply to 980 CMR 16.00. For the
purposes of 980 CMR 16.00, the additional definitions set forth in 980 CMR 16.02 shall apply,
unless the context otherwise requires.
Agency Consultation means written, oral, and other communications with Local Government and
state agencies with an interest in the permitting of a proposed LCEIF, SCEIF, or other Facility.
Community means at a minimum members of the public residing or working within a distance
set forth in 980 CMR 15.05(1)(b) from the Facility Boundary of a proposed facility.
(Mass. Register #1568, 02/27/2026)
Division of Public Participation (DPP) means the Division of Public Participation at the
Department established under M.G.L. c. 25, § 12T to assist stakeholders with navigating the
Department and the Board pre-filing requirements, clarifying filing requirements, and identifying
opportunities to intervene.
DPP Opinion means a written communication from the Director of DPP to the Board assessing
whether the Applicant has completed the pre-filing consultation and engagement requirements
in 980 CMR 16.00
Key Stakeholders means, at a minimum, public interest groups, organizations serving the local
community in the vicinity of a proposed Project that could be affected by a proposed Project;
abutters of the Project, including residents (both owners and renters) and businesses;
community-based organizations, elected or appointed municipal officials (e.g., mayor or
town/city manager, relevant Council/Select Board members, Chair(s) of the Conservation
Commission, Planning Board, Zoning Board, and Head of the Department of Public
Works),regional planning officials; representatives of labor groups (e.g., union locals, building
trades councils, central labor councils, and the Massachusetts AFL-CIO)and apprenticeship
programs; and federally recognized, state-acknowledged, or state-recognized Tribes.
MEPA Office means the Massachusetts Environmental Policy Act Office within the Executive
Office of Energy and Environmental Affairs that administers MEPA and 301 CMR 11.00:
MEPA Regulations.
OEJE means the Office of Environmental Justice and Equity within the Executive Office of
Energy and Environmental Affairs, as established in M.G.L. c. 21A, § 29.
Pre-filing Engagement Status Checklist means a document to be filed by an Applicant with DPP
approximately midway through the Pre-filing Outreach Period that catalogs the status of
pre-filing consultation and engagement requirements and includes supporting documentation
identified in 980 CMR 16.00. The checklist shall include an attestation by the Applicant that all
statements contained therein are true.
Pre-filing Engagement Completion Checklist means a document that reflects completed
pre-filing consultation and engagement requirements to be filed by an Applicant with DPP, the
Board, and Local Government and state permitting agencies at the completion of the Pre-filing
Outreach Period and together with the Pre-filing Notice. The Applicant shall submit supporting
documentation identified in 980 CMR 16.00 to DPP at the completion of the Pre-filing Outreach
Period. If certain outreach or agency consultation requirements cannot be completed, the
Applicant shall attach a statement clarifying the reason for a waiver or partial waiver that was
requested from and approved by DPP pursuant to 980 CMR 16.03(1). The checklist shall
include an attestation by the Applicant that all statements contained therein are true.
Pre-filing Notice means the Notification of Intent to File Application filed by an Applicant with
DPP, the Board and Local Government and state permitting agencies no less than 60 days and
no more than 90 days prior to filing an Application or a petition to construct with the Board.
Pre-filing Outreach Period means the period of time between the start of pre-filing consultation
and engagement activities specified in 980 CMR 16.04 and the submission of the Pre-filing
Notice to the Board and DPP. For purposes of 980 CMR 16.00, the Pre-filing Outreach Period
begins when the Applicant meets with DPP and OEJE. The Applicant may meet with the
stakeholders prior to the beginning of the Pre-filing Outreach Period.