980 CMR 16.04
Overview of Requirements for the Pre-filing Outreach Period
(1) During the Pre-filing Outreach Period, the Applicant shall employ substantial, good faith
efforts and endeavor to balance the goal of providing available information on Project design
criteria to Key Stakeholders at an early point during Project development with the need to pursue
due diligence on potential site options to develop the optimal Project design.
(a) During the Pre-filing Outreach Period, the Applicant shall:
1. Review and implement applicable site suitability criteria, cumulative impact analysis
requirements, and the cumulative impact analysis tool as described in 980 CMR 15.00:
Cumulative Impact Analysis and Standards for Applying Site Suitability Criteria, as
applicable. The Applicant shall consider input from Key Stakeholders, Agency
Consultations, and public meetings with the Community to inform the selection of the
preferred site/route;
2. Communicate during Agency Consultations, meetings with Key Stakeholders, and
public meetings with the Community, how site and design options were or are being
considered based on the applicable site suitability criteria, cumulative impact analysis
requirements, and the cumulative impact analysis tool. Outreach shall include a
discussion of how the preferred site/route option avoids, minimizes, or mitigates the
potential for disproportionate adverse impacts. See 980 CMR 13.03(1)(d); 980 CMR
15.03(6), 15.10(2);
3. Document efforts to inform, involve, and partner with Key Stakeholders and the
Community;
4. Maintain notes from meetings with Key Stakeholders, Agency Consultation, and
Community meetings that included the date of the meeting, names of participants, key
discussion points, and take aways;
5. Summarize comments received and how they influenced Project design;
6. Publicize Project information using multiple outreach channels that have wide reach
within the Community, including multi-lingual and multi cultural media options; and
7. Create a Project web page at the start of the Pre-filing Outreach Period and maintain
up-to-date information as it becomes available on Project web page(s).
(b) The Applicant shall meet with DPP and OEJE individually or jointly at the start of the
Pre-filing Outreach Period, in accordance with 980 CMR 16.05 (1), to discuss its proposed
outreach plan and clarify pre-filing consultation and engagement requirements. The
Applicant may contact DPP for guidance on who constitutes Key Stakeholders prior to or
during the Pre-filing Outreach Period.
(c) The Applicant shall meet with relevant Key Stakeholders early during the Pre-filing
Outreach Period to inform, seek input, and be responsive to questions and feedback received
on the proposed Project. The Applicant shall create and maintain a Project email distribution
list and add Key Stakeholders they meet and those who opt-into the Project email distribution
list. The Applicant shall send quarterly updates to the Project email distribution list that
include but are not limited to new Project developments; any changes to site or Project
design; Project contact person(s), including email, phone number, and mailing address;
details of public meetings; and the estimated date Applicant plans to submit the Pre-filing
Notice to the Board. Emails sent to the Project email distribution list shall be by blind copy
and shall include a link or process for recipients to opt-out.
(d) The Applicant shall submit to DPP a Pre-filing Engagement Status Checklist and the
following supporting documentation related to its pre-filing consultation and engagement
efforts approximately midway through the Pre-filing Outreach Period:
1. A list of Key Stakeholders, Agency Consultation, and public meetings with the
Community held to date, including date/time and
location;
2. A summary of how the site suitability criteria, cumulative impact analysis
requirements, and cumulative impact analysis tool, as applicable, are informing Project
design and planning;
3. A summary of any related improvements proposed by Local Government or state
agencies during Agency Consultation; and
4. A table summarizing oral and written comments received that includes all issues
raised at meetings with Key Stakeholders, Agency Consultation, and public meetings
with the Community held to date, and any modifications in Project design made in
response to the comments.
(e) The Applicant shall consult with the MEPA Office at least once during the Pre-filing
Outreach Period.
1. The consultation with the MEPA Office shall be held early during the Pre-filing
Outreach Period to receive feedback on the Applicant’s compliance with regulatory
requirements and other best practices to avoid or minimize impacts, as well as to receive
recommendations on project specific studies or analyses that may be needed to inform
the agencies’ review of the Application or a petition to construct once it is filed with the
Board.
2. The Applicant may hold subsequent consultation(s) with the MEPA Office as
appropriate.
(f) The Applicant shall complete Agency Consultation, as appropriate, to receive feedback
on compliance with regulatory requirements, including necessary pre-filing studies and
analyses (such as wetlands delineation, or endangered species surveys).
(g) The Applicant shall publicize and conduct at least two public meetings for Key
Stakeholders and the Community.
1. The Applicant shall endeavor to hold the first mandatory public meeting after
meeting with Key Stakeholders and addressing feedback received, as appropriate.
2. The Applicant shall hold the second mandatory public meeting prior to submitting
the Pre-filing Notice with the Board. The Applicant shall present any changes to the
Project design and how input received during the first public meeting was considered.
3. In addition to the two mandatory public meetings, as appropriate, Applicants shall
endeavor to use other engagement channels such as open houses, workshops, or meetings
that are tailored to discuss specific topics of interest to Key Stakeholders and the
Community. See 980 CMR 16.07.
4. The pre-filing comment period shall remain open from when the first public meeting
is announced until the deadline to submit public comments after the second mandatory
public meeting. The Applicant shall provide at least three weeks after the second
mandatory public meeting for Key Stakeholders and Community to submit written
comments and for comments to be considered prior to filing the Pre-filing Notice.
5. For public meetings, the Applicant shall have a sign-in sheet that lists the name of
participants and any organizational affiliation. The Applicant shall upon request submit
the sign-in sheets to DPP during the Pre-filing Outreach Period or to the Siting Board
during the adjudication process.
(h) No less than 60 days and no more than 90 days prior to filing an Application or a
petition to construct with the Board, the Applicant shall submit a Pre-filing Notice
(Notification of Intent to File Application) to the Board. If the Applicant does not file its
Application or a petition to construct with the Board within 90 days after filing the Pre-filing
Notice, the Applicant shall resubmit a Pre-filing Notice. If more than 90 days pass after the
second Pre-Filing Notice has been filed without the filing of an Application or a petition to
construct, the Applicant shall submit to DPP written communication with the reason for the
delay and an estimated timeline or date to resubmit the Pre-filing Notice. The Applicant may
also meet with DPP staff to provide an update and discuss any additional outreach planned.
DPP staff shall review documentation submitted by the Applicant with the Pre-filing
Engagement Status Checklist and the Pre-filing Engagement Completion Checklist and
provide a written assessment if additional outreach is necessary before a Pre-filing Notice can
be resubmitted to the Board.
(i) At the conclusion of the Pre-filing Outreach Period, the Applicant shall file the Pre-filing
Notice and the Pre-filing Engagement Completion Check list with DPP, the Board, and
relevant Local Government and state permitting agencies. The Applicant shall also submit
the following supporting documentation related to its pre-filing consultation and engagement
efforts with DPP:
1. An overview of all pre-filing consultation and engagement efforts that have occurred
to date including:
a. List of Key Stakeholder, Agency Consultation, and Community meetings held,
including date/time and location;
b. Description of the outreach materials created and outreach recipients, including
date and method(s) of contact; and
c. Notes from meetings with Key Stakeholders, Agency Consultation, and public
meetings with the Community;
2. A table summarizing oral and written comments received throughout the Pre-filing
Outreach Period that includes all issues raised, how the comments were considered, and
any modifications in Project design made in response to the comments;
3. A description of how the site suitability criteria, cumulative impact analysis
requirements, and cumulative impact analysis tool as described in 980 CMR 15.00:
Cumulative Impact Analysis and Standards for Applying Site Suitability Criteria, as
applicable, were incorporated into the selection of the Applicant’s preferred Project site;
4. A description of any partnerships developed with Key Stakeholders and/or
Community, including any advisory bodies formed to provide ongoing input;
5. Any waiver or partial waiver request demonstrating good cause that was requested
and approved or requested and not approved by DPP;
6. A copy of the Pre-filing Engagement Status Checklist; and
7. An update on any ongoing discussions regarding community benefits plans and
community benefits agreements. See Standards and Guidelines for Community Benefits
Plans and Agreements, Executive Office of Energy and Environment.