225 CMR 14.06
Qualification Process for RPS Class I, Solar Carve-out Renewable Generation Units, and Solar
Carve-out II Renewable Generation Units
(1) Statement of Qualification Application. A Statement of Qualification Application shall be
submitted to the Department by the Owner or Operator of the Generation Unit or by the
Authorized Agent for an Aggregation, as provided in 225 CMR 14.05(6)(b). The applicant must
use the most current forms and associated instructions provided by the Department, and must
include all information, documentation, and assurances required by such forms and instructions.
(2) Review Procedures.
(a)
The Department will notify the applicant when the Statement of Qualification
Application is administratively complete or if additional information is required pursuant to
225 CMR 14.06(1).
(b) The Department may, in its sole discretion, provide an opportunity for public comment
on any Statement of Qualification Application.
(3) Issuance or Non-issuance of a Statement of Qualification.
(a)
If the Department finds that all or a portion of the electrical energy output of a
Generation Unit or of an Aggregation meets the requirements for eligibility as RPS Class I
Renewable Generation, Solar Carve-out Renewable Generation, or Solar Carve-out II
Renewable Generation pursuant to 225 CMR 14.05, the Department will provide the Owner
or Operator of such Generation Unit or the Authorized Agent for such Aggregation with a
Statement of Qualification.
225 CMR - 126.6
(b) The Statement of Qualification shall include any applicable restrictions and conditions
that the Department deems necessary to ensure compliance by a particular Generation Unit
or Aggregation with the provisions of 225 CMR 14.00. After June 28, 2013, a Statement of
Qualification shall be issued to a Solar Carve-out Renewable Generation Unit only if it meets
the conditions of 225 CMR 14.05(4)(k).
(c) If the Generation Unit or Aggregation does not meet the requirements for eligibility as
an RPS Class I Renewable Generation Unit, a Solar Carve-out Renewable Generation Unit,
or Solar Carve-out II Renewable Generation Unit, the Department shall provide written
notice to the Owner or Operator or to the Authorized Agent for an Aggregation, including
the Department's reasons for such finding.
(d) A Solar Carve-out Renewable Generation Unit shall receive a Statement of Qualification
that states that the Generation Unit is eligible for the Massachusetts Solar Carve-out and that
specifies a term of calendar quarters, referred to as the Opt-in Term, during which period the
Generation Unit is eligible to participate in the Solar Credit Clearinghouse Auction. The
Opt-in Term shall be set at the time that the Generation Unit receives its Statement of
Qualification, and the Opt-in Term shall commence with the earlier of either the first day of
the calendar quarter during which occurs the RPS Effective Date, as such date is provided
in 225 CMR 14.06(4), or, at the request of the applicant or in the case that the Generation
Unit has not yet been granted the approval to interconnect to the grid by the local
Distribution Company, the first day of the subsequent calendar quarter from the date of the
Statement of Qualification.
(e) The length of the Opt-in Term shall be 40 quarters for all Solar Carve-out Renewable
Generation Units that receive a Statement of Qualification.
(f) After January 1, 2022, starting in the calendar quarter after the end of a Solar Carve-out
Renewable Generation Unit's Opt-in Term, it shall no longer be eligible to generate Solar
Carve-out Renewable Generation Attributes, but will remain qualified to generate RPS Class
I Renewable Generation Attributes.
(g)
A Solar Carve-out II Renewable Generation Unit shall be issued a Statement of
Qualification provided that it meets the provisions of 225 CMR 14.05(9).
(4)
RPS Effective Date. The RPS Effective Date shall be the earliest date on or after the
Commercial Operation Date on which electrical energy output of an RPS Class I Renewable
Generation Unit, Solar Carve-out Renewable Generation Unit, or Solar Carve-out II Renewable
Generation Unit can result in the creation of RPS Class I Renewable Generation Attributes, Solar
Carve-out Renewable Generation Attributes, or Solar Carve-out II Renewable Generation
Attributes except that:
(a) in the case of a Generation Unit using Eligible Biomass Fuel, the RPS Effective Date
shall not be earlier than the date on which the Department determines that the Generation
Unit has commenced compliance with the low-emission conditions in its Statement of
Qualification;
(b) in the case of a Hydroelectric Energy Generation Unit, the RPS Effective Date shall not
be earlier than the date on which the Department determined that the Generation Unit has
commenced compliance with the environmental conditions in its Statement of Qualification;
and
(c)
in the case of Solar Carve-out II Renewable Generation Units, the Generation Unit
Owner may elect to have their RPS Effective Date established as the first day of the calendar
quarter following their Commercial Operation Date. In the case of a Solar Carve-out II
Renewable Generation Unit in the Managed Growth Sector, its RPS Effective Date will be
no earlier than the first day of the calendar year of the Annual Capacity Block under which
the Solar Carve-out II Renewable Generation Unit is qualified.
225 CMR - 126.7
(5) Notification Requirements for Change in Eligibility Status. The Owner or Operator of an
RPS Class I Renewable Generation Unit, Solar Carve-out Renewable Generation Unit, or Solar
Carve-out II Renewable Generation Unit shall notify the Department of any changes in the
technology, operation, emissions, fuel sources, energy resources, capacity commitment, or other
characteristics of the Generation Unit that may affect the eligibility of the Generation Unit as an
RPS Class I Renewable Generation Unit, Solar Carve-out Renewable Generation Unit, or Solar
Carve-out II Renewable Generation Unit. The Owner or Operator shall submit the notification
to the Department no later than five days following the end of the month during which such
changes were implemented. The notice shall state the date the changes were made to the RPS
Class I Renewable Generation Unit, Solar Carve-out Renewable Generation Unit, or Solar
Carve-out II Renewable Generation Unit and describe the changes in sufficient detail to enable
the Department to determine if a change in eligibility is warranted.
(6)
Notification Requirements for Change in Ownership, Generation Capacity, or Contact
Information. The Owner or Operator of an RPS Class I Renewable Generation Unit, Solar
Carve-out Generation Unit, or Solar Carve-out II Renewable Generation Unit shall notify the
Department of any changes in the ownership, operating entity, generation capacity, NEPOOL
GIS account, independent verification system for the Generation Unit's or Aggregation's
electrical energy output, or contact information for the Generation Unit or Aggregation. The
Owner or Operator shall submit the notification to the Department no later than five days
following the end of the month during which such changes were implemented.
(7) Time Limit for Project Implementation. Any Statement of Qualification issued on or after
March 31, 2009 shall expire 24 months after the issuance date of the Statement of Qualification
(the Expiration Date), unless the Commercial Operation Date of the Generation Unit or
Aggregation is on or before the Expiration Date, with the exception of any Statement of
Qualification issued to a Solar Carve-out Generation Unit, which shall expire per the terms
outlined in 225 CMR 14.05(4)(k). Any Statement of Qualification issued to a Solar Carve-out
II Renewable Generation Unit shall expire pursuant to the terms outlined in 225 CMR
14.05(9)(p). The Department may, at its discretion, grant an extension of the Expiration Date
of the Statement of Qualification upon petition by the Owner or Operator of the Generation Unit
or Aggregation. If the Owner or Operator of such Generation Unit or Aggregation desires an
extension, such Owner or Operator must submit a new Statement of Qualification Application,
and the decision of the Department on such new application may be made in accordance with the
regulations and criteria that are applicable on the date that the Department receives that
application.
(8)
Expiration of Advisory Rulings. An advisory ruling issued by the Department for any
proposed Generation Unit for which an administratively complete Statement of Qualification
Application has not been submitted as of January 7, 2011, shall be deemed to have expired on
January 7, 2011.
(9) Suspension or Revocation of Statement of Qualification. The Department may suspend or
revoke a Statement of Qualification if the Owner or Operator of an RPS Class I Renewable
Generation Unit, Solar Carve-out Renewable Generation Unit, or Solar Carve-out II Renewable
Generation Unit or Authorized Agent of an Aggregation fails to comply with 225 CMR 14.00
or if a Generation Unit does not operate during a consecutive 12-month period.