78OAG174
78OAG174
Cite as 78 Md. Op. Att'y Gen. 174
174
ENVIRONMENT ) ADMINISTRATIVE LAW — CONTESTED CASES —
LANDFILL PERMITTING PROCEDURES — CONSENT ORDER
AUTHORITY OF THE DEPARTMENT OF THE ENVIRONMENT
November 8, 1993
The Honorable Joan B. Pitkin
House of Delegates
You have requested our opinion on the following issues related
to public participation in the permitting process for the expansion of
the Sandy Hill landfill:
1.
Did members of the public have a right to a contested
case hearing under the Sugarloaf decision as part of the process for
considering an application for a permit to expand the Sandy Hill
landfill?
2.
What are the public participation rights under current
statutory procedures of opponents of the Sandy Hill landfill
expansion?
3.
Did the Department of the Environment have the legal
authority to enter into a consent agreement that allowed for a vertical
expansion of the Sandy Hill landfill in advance of providing an
opportunity for a contested case hearing?
For the reasons stated below, we conclude as follows:
1.
Members of the public were entitled to an opportunity for
a contested case hearing under the Sugarloaf decision as part of the
process under which the Department of the Environment (“MDE”)
considered an application for a permit to expand the Sandy Hill
landfill.
2.
If opponents of the Sandy Hill landfill expansion appeal
a final determination by MDE to permit the expansion of the landfill,
they will be entitled to an opportunity for a contested case hearing.
175
3.
MDE had the legal authority to enter into a consent
agreement that allowed for a vertical expansion of the Sandy Hill
Landfill in advance of providing an opportunity for a contested case
hearing.
I
Background
Sandy Hill landfill, located near Bowie, is operated by Prince
George’s County. The county desires to expand the landfill both
horizontally and vertically - that is, the landfill would cover more
ground, and the solid waste dumped there would be piled higher.
Not surprisingly, expansion of the landfill is controversial.
Under §9-204(d) of the Environment Article, Maryland Code
(“EN” Article), “a person shall have permit issued by the Secretary
[of the Environment] under this section before the person installs,
materially alters, or materially extends a ... refuse disposal system.”
The term “refuse disposal system” includes a landfill. EN §9-
201(e)(4). No one disputes that the horizontal and vertical
expansions sought for the Sandy Hill landfill constitute a material
alteration or material extension subject to the permit requirement in
EN §9-204.
EN §9-209(a) requires that, after publication of a suitable
notice, a “public hearing” precede any issuance of a permit for a
landfill expansion: “Before the Secretary issues a permit to an
applicant under §9-204 of this subtitle to install, materially alter, or
materially extend a landfill system, ... the Department shall hold a
public hearing on the application.”
II
Sugarloaf
In Sugarloaf Citizens Ass’n v. Northeast Maryland Waste
Disposal Auth., 323 Md. 641, 594 A.2d 1115 (1991), the Court of
Appeals expanded the availability of contested case procedures when
certain environmental permits were sought. To be sure, the Court’s
176
In light of this rationale, certain textual differences between EN
1
§2-404, the provision specifically at issue in Sugarloaf, and EN §9-209,
the provision at issue in this opinion, would be irrelevant to the ultimate
conclusion.
holding was a limited one: that the contested case hearing
procedures in the Administrative Procedure Act did not apply to the
first of a three-stage air quality permitting process. 323 Md. at 659.
In the course of its opinion, however, the Court concluded that at a
later stage of the process, prior to the issuance of a permit to
construct a source of air pollution, contested case procedures would
apply.
The particular statute on which this conclusion was based, EN
§2-404, required that “an opportunity for a public hearing” be
provided prior to the issuance of the permit. Rejecting the State’s
argument that this “public hearing” requirement was satisfied by the
provision of a legislative-type hearing, rather than an adversarial,
evidentiary hearing, the Court (in its opinion on reconsideration)
identified a general rule “that where a hearing was provided for in
connection with a permit or license, the proceeding was a ‘contested
case.’” 323 Md. at 666-67 (citation omitted). If this general rule
were taken to be the basic teaching of Sugarloaf, then contested case
procedures would attach to the public hearing requirement of EN §
9-209.1
Any doubt about the applicability of the Sugarloaf decision to
landfill permits was removed by the subsequent decision in Medical
Waste Assoc., Inc. v. Maryland Waste Coalition, Inc., 327 Md. 596,
612 A.2d 241 (1992). That decision, while largely addressing itself
to the standing of a citizens group to challenge a permit for an
incinerator, dealt directly with the nature of the hearing required
under EN §9-209:
Nothing in [this section], either expressly or
by clear implication, indicates that the hearing
is not to be a contested case hearing.... Since
the administrative proceeding involves the
grant of a permit, and since for the opportunity
for an agency hearing is required by law, the
application of the “contested case” definition
in the APA leads to the conclusion that the
177
We express no view whether any particular citizen opponent of the
2
expansion would have standing to appeal the issuance of a permit.
administrative proceeding prior to the issuance
of a refuse disposal permit is also a contested
case for purposes of judicial review under the
APA.
327 Md. at 610 (citing Sugarloaf). Hence, we conclude that, under
the applicable law prior to June 1, 1993, opponents of the Sandy Hill
landfill would have been entitled to an opportunity for a contested
case hearing prior to issuance of a permit to expand the landfill.
2
III
Post-Sugarloaf Public Participation Rights
Chapter 59 (House Bill 877) of the Laws of Maryland 1993
contained an extensive revision of the contested case procedures in
the Administrative Procedure Act and amended the public
participation requirements in the Environment Article for certain
environmental permits. This legislation, which became effective
June 1, 1993, was the product of the Commission to Revise the
Administrative Procedure Act.
One of the main tasks of the Commission was to assess and
respond to complaints that the Sugarloaf decision had resulted in an
unexpected and unwarranted expansion of the situations to which
contested case hearings were applicable. The General Assembly
responded to the recommendations of the Commission in a number
of ways, including enactment of the following provision to limit
dramatically the impact of Sugarloaf:
(c) A public hearing required or provided
for by statute or regulation before an agency
takes a particular action is not an agency
hearing under §10-202(d) of the subtitle [that
is, the definition of “contested case”] unless
the statute or regulation:
178
Conversely, where MDE receives no comments adverse to
3
issuance of the permit and there is no substantive change in the draft
permit, the tentative determination becomes a final decision of the
Department, and there is no opportunity for a contested case hearing.
We express no view whether any particular citizen opponent of the
4
Sandy Hill Landfill extension would be “aggrieved” within the meaning
of EN §1-605.
(1) Expressly requires that the public
hearing be held in accordance with this
subtitle; or
(2) Expressly requires that any judicial
review of the agency determination following
the public hearing be conducted in accordance
with this subtitle.
§10-203(c) of the State Government Article.
At the same time, the General Assembly sought to preserve the
essence of Sugarloaf for a number of environmental permit statutes
by enacting EN Title 1, Subtitle 6, “Public Participation in the
Permitting Process.” This new subtitle applies to a variety of
permits issued by MDE, including “permits to install, materially alter
or materially extend landfill systems ... subject to §9-209 of this
article.” EN §1-601(a)(2).
For such a permit, as for the others listed in EN §1-601(a),
MDE is required to publish notice of applications for permits and,
upon timely written request or in its own discretion, “provide an
opportunity for an informational meeting with respect to the
application.” EN §1-603(c)(1). If MDE then determines tentatively
to issue a permit, MDE “shall schedule a public hearing on the
tentative determination when a written request for a public hearing”
is timely made. EN §1-604(a)(4)(i). Where MDE receives
comments adverse to the issuance of the permit, or where MDE has
made a substantive change in the draft permit as it existed at the time
of the tentative determination, MDE is then required to prepare a
“final determination.” EN §1-604(b). Ultimately, a person who is
3
aggrieved by the final determination may request a contested case
hearing to appeal it. EN §1-605.4
179
In our view, these procedural changes are applicable to any
administrative proceeding involving the applications for expansion
of the Sandy Hill landfill. In other words, if MDE reaches the point
of preparing a final determination to grant a permit for vertical or
horizontal expansion of the landfill, then opponents of the expansion
would be entitled to an opportunity for a contested case hearing on
their appeal of the final determination.
IV
Consent Order
As we understand the situation, in January 1993, MDE and
Prince George’s County entered into a consent order under which the
Sandy Hill landfill was allowed to expand vertically, despite the fact
that the county’s application for a permit for vertical expansion is
still pending. You question MDE’s authority to have entered into
this order.
EN §9-222 provides as follows:
(a) The Secretary may issue an order
under subsection (b) of this section, if, after
investigation, the Secretary determines that the
absence or incompleteness of a public water
supply system, public sewerage system, or
public refuse disposal system in a county,
municipal
corporation,
sanitary
district,
subdivision, or locality:
(1) Is sufficiently prejudicial to the
health or comfort of that or any other county,
municipal
corporation,
sanitary
district,
subdivision, or locality, or
(2) Causes a condition by which any of
the waters of this State are being polluted or
could become polluted in a way that is
dangerous to health or is a nuisance.
180
(b) An order under this section may
require:
(1) The installation and operation or the
completion of a public water supply system,
public sewerage system, or public refuse
disposal system in a county, municipal
corporation, sanitary district, subdivision, or
locality within a time that the Secretary sets;
or
(2) The installation of any device, the
establishment
of
any
method,
or
the
enforcement of any measure or regulation that
the Secretary considers proper under the
circumstances.
This grant of authority is independent of MDE’s authority to
issue permits and enables MDE to move immediately when
necessary to protect the public interest in a healthful environment.
The fact that a permit application to extend a refuse disposal system
may be pending does not diminish MDE’s authority to order an
extension in advance of its decision on the application if operation
without the extension “is sufficiently prejudicial to health or comfort
....”
We are told by MDE that the prerequisites set out in EN §9-
222(a) were met with respect to the Sandy Hill landfill. In MDE’s
view, as we understand the situation, there was no satisfactory
alternative for the disposal of refuse once Sandy Hill reached
capacity. Hence, in MDE’s view, unless Sandy Hill were extended
vertically to increase its capacity and permit its continued operation,
the health or comfort of the residents of the county would be
prejudiced.
Others may disagree with MDE’s factual determination in this
regard. But the Attorney General’s Office cannot second-guess
technical judgments made by MDE, which has the presumed
expertise to make the judgment called for by EN §9-222(a). See
generally 76 Opinions of the Attorney General 3 (1991). Because
181
MDE has similar authority under EN §9-221, where MDE
5
determines that a refuse disposal system is a menace to health or comfort
or is causing a nuisance.
MDE appears to have made that judgment, we conclude that it had
authority to enter the consent order with the county.
5
V
Conclusion
In summary, it is our opinion that:
1.
Members of the public were entitled to an opportunity for
a contested case hearing under the Sugarloaf decision as part of the
process under which the Department of the Environment considered
an application for a permit to expand the Sandy Hill landfill.
2.
If opponents of the Sandy Hill landfill expansion appeal
a final determination by MDE to permit the expansion of the landfill,
they will be entitled to an opportunity for a contested case hearing.
3.
MDE had the legal authority to enter into a consent
agreement that allowed for a vertical expansion of the Sandy Hill
Landfill in advance of providing an opportunity for a contested case
hearing.
J. Joseph Curran, Jr.
Attorney General
Jack Schwartz
Chief Counsel
Opinions & Advice