78OAG287
78OAG287
Cite as 78 Md. Op. Att'y Gen. 287
287
This opinion was originally issued in unpublished form on August
1
10, 1992 as Opinion No. 92-023. Subsequently, the Board approved the
contracts. Although our conclusion is unchanged and the Board has long
since acted, some passages in the initial opinion were susceptible of
misinterpretation. To avert unintended problems, we are withdrawing
Opinion No. 92-023 in favor of this published treatment of the issue.
PROCUREMENT
BOARD OF PUBLIC WORKS ) APPROVAL OF CONTRACTS DATED
“AS OF” AN EARLIER DATE
May 24, 1993
The Honorable William Donald Schaefer
Governor
The Honorable Louis L. Goldstein
Comptroller
The Honorable Lucille Maurer
Treasurer
Board of Public Works
You have requested our opinion as to the legality of two
contracts presented for approval to the Board of Public Works
(“Board”) at the Board’s July 22, 1992 meeting. For the reasons
stated below, we conclude that the Board could lawfully approve the
contracts as presented if it chooses to do so. 1
I
Background
The contracts in question are between the Department of
Health and Mental Hygiene (“DHMH”) and The Johns Hopkins
University School of Medicine (“Hopkins”). The contracts, which
are funded entirely with federal and private foundation grant monies,
288
are for the purpose of obtaining studies of the effectiveness of
certain programs in improving the birth outcomes of Medicaid
recipients.
Hopkins has already begun performance under both of these
contracts, and the contracts are dated “as of September 30, 1991”
and “as of March 1, 1992,” respectively. We are told that DHMH
has not executed the contracts by signing them. On the other hand,
DHMH did not promptly seek to obtain approvals for the contracts,
and the delay in seeking approval coupled with the start of
performance by the contractor gave rise to concern that the parties
might have been proceeding as if the contracts were already in
effect. The record is not entirely clear on this point, however.
The contract dated as of September is for $530,066. Authority
for the approval of this contract has not been delegated by the Board.
See COMAR 21.02.01.04A(a) (delegating approval authority for
service contracts “in the amount of $100,000 or less” to the
Department of Budget and Fiscal Planning (“DBFP”)). Therefore,
DHMH “may not enter into” this contract without Board approval.
COMAR 21.03.01.
The contract dated as of March is for $56,900. This contract
ordinarily would have been subject to DBFP’s delegated approval
authority; DBFP, however, submitted it to the Board on the view that
the contract was either void or, if the Board so determined, voidable,
because it violated COMAR 21.02.03.02C(5). This regulation
provides in pertinent part as follows: “Any contract required to be
submitted to [DBFP] in accordance with this regulation may not take
effect unless it has been approved by [DBFP].” Again, the record is
not entirely clear but it appears that pre-approval performance by
Hopkins may have been the sole basis on which DBFP judged that
a regulatory violation had occurred.
II
Analysis
We are aware of no provision in the Procurement Law that
prohibits approval and subsequent agency execution of a contract
dated “as of” an earlier date or where the contractor already has
289
Prior to approval, the contractor is at risk that it will not be
2
compensated for work performed. The contractor may not enforce an
unapproved contract.
begun to perform. Under common law principles, moreover, there
2
is no bar to a contract’s taking effect prior to the date of execution.
Canaras v. Lift Truck Services, Inc., 272 Md. 337, 349, 322 A.2d
866, 872 (1974); Brewer v. National Surety Corporation, 169 F.2d
926, 928 (10th Cir. 1948). As the Court of Appeals wrote, “The
parties [to a contract] may ... provide at the time of its execution that
the contract is entered ‘as of’ an earlier date than that on which it
was in fact executed; such agreements are then effective
retroactively as of the earlier date and the parties are bound
accordingly.” 272 Md. at 349. As noted in Part I above, the
contracts at issue are dated “as of” the dates when the work began.
This phrasing is sufficient to obligate the State during the retroactive
periods, but only if the contracts are approved.
Thus, a regulatory violation does not occur solely because a
contemplated effective date for a contract is earlier than the expected
date of approval or execution by the State or because a contractor
already has embarked on performance. In the absence of other facts,
a proposed contract with an “as of” effective date or involving
performance underway may be acted upon under the procedures
normally applicable to contract approval. COMAR 21.02.
However, to the extent that Hopkins and DHMH had been
proceeding as if the contracts already were effective without
approval, DHMH’s handling of these contracts was inconsistent with
the intent of the procurement regulations. We recognize, in the
words of the regulation, that legally DHMH has not “enter[ed] into”
the contracts and that the contracts have not “take[n] effect,” given
that DHMH has not executed them. See generally Riegel v. Holmes,
171 N.E.2d 553, 563 (Ohio Ct. Com. Pleas 1960) (“enter into”
means to become legally bound). Nonetheless, the regulatory
scheme is intended to give DBFP and the Board the opportunity to
consider a services contract before the contracting agency treats the
contract as if it already is in force. Acquiescence in the contractor’s
undertaking performance while at the same time failing to seek the
requisite approval in a timely way may indicate to the approval
authority that the agency was not complying with the requirement for
approval.
290
COMAR 21.03.01.04 requires the appropriate department head to
3
make an initial determination regarding voidness and voidability, available
for review by the Board. Such a determination, which COMAR
21.01.02.01(34) requires be in writing, would presumably set forth the
facts relating to the procurement in sufficient detail to allow an informed
judgment by the Board.
A purported contract that does not comply with the
Procurement Law or its implementing regulations is void. §11-
204(b)(1) of the State Finance and Procurement Article (“SF”
Article); COMAR 21.03.01.02A. Procedures normally used for
contract approval may not be used when the lack of compliance is
known to the approval authority. Instead, under SF §11-204(c)(1)
and COMAR 21.03.01.03A, the Board may, in its discretion, treat a
contract as merely voidable if (i) the parties acted in good faith, (ii)
ratification would not undermine the purposes of the Procurement
Law, and (iii) the violation was insignificant or did not prevent
substantial compliance with the Procurement Law. While judgments
about what is void or voidable are for the Board and not the Attorney
General, certain facts of which we have been made aware ) for
example, the desirability of using the federal grant funds promptly
for these public health research projects and the unique expertise of
Hopkins ) coupled with the apparent good faith of DHMH and
Hopkins, suggest that a determination of mere voidability would be
well within the Board’s discretion.
3
III
Conclusion
In summary, it is our opinion that the Board may, in its
discretion, approve the contracts with Hopkins as of the dates when
Hopkins’ performance commenced.
J. Joseph Curran, Jr.
Attorney General
Jack Schwartz
Chief Counsel
Opinions & Advice