R 281.1307
R 281.1307 Performance bonds.
Cite as Mich. Admin. Code R 281.1307
Rule 7. (1) As authorized by the provisions of section 31(5) of the act, a permit to
construct a new dam or reconstruct a failed dam may require a performance bond. A
performance bond may be in the form of any of the following:
(a) A surety bond.
(b) A secured trust fund.
(c) A letter of credit.
(d) Insurance.
(e) A financial test.
(f) A corporate guarantee.
(g) Another suitable instrument or mechanism.
(h) A combination of the items listed in subdivisions (a) to (g) of this subrule as
approved by the department. The department shall consider an applicant's past
performance in determining if a performance bond shall be required.
(2) The performance bond shall be secured and documentation shall be submitted to
the department before the commencement of construction. The bond, instrument,
mechanism, or fund or combination of these methods of assurance shall be in the
amount equal to a reasonable estimate of the cost, adjusted for inflation, that is
required to adequately complete a project or remove a completed or partially
completed dam and to provide for complete or partial restoration of a project site.
Performance bonds may be required in the following instances if there is a
reasonable possibility that the permittee may not complete the project:
(a) Where total project completion is essential for the protection of public health,
welfare, or safety or to protect natural resources and the public trust in those natural
resources.
(b) For temporary dams or dams that are constructed or reconstructed for a specific
purpose and period of time after which removal is planned.
(c) For phased construction projects where dam construction or reconstruction is
an integral and necessary part of the total project and is to be phased in over a number of
years.
(d) Projects to be constructed in the future to mitigate the loss of natural resources
or environmental degradation.