R 281.1311 Emergency action plans.
Cite as Mich. Admin. Code R 281.1311
Rule 11. (1) An emergency action plan for a high or significant hazard potential dam
shall be submitted to the county or local emergency management coordinator for
review for consistency with county or local emergency operations plans and the
Michigan emergency preparedness plan. An emergency action plan for an existing dam
shall be submitted to the department with documentation that the plan has been
submitted to the county or local emergency management coordinator not later than
the time that the first inspection report for the dam is due or at another time agreed
to by the department. An emergency action plan for a newly constructed dam
shall be submitted to the department with documentation that the plan has been
submitted to the county or local emergency management coordinator not later than
the date of expiration of the permit for construction of the dam, including any
extensions of time for completion.
(2) At the time subsequent inspection reports are due, the owner shall determine if
the plan is up to date. The owner shall advise the department of the findings of this
review and shall submit any revisions to the department and to the county or local
emergency management coordinator.
(3) The emergency action plan shall include a description of the circumstances under
which it shall be activated, what actions shall be taken, and who shall be responsible
to take those actions when the plan is activated.
(4) The emergency action plan shall include the name, address, and telephone number
of all of the following entities:
(a) The person who is responsible for the operation of the dam.
(b) The alternate person who is responsible for the operation of the dam.
(c) The local emergency management coordinator or coordinators.
(5) The emergency action plan shall include either of the following:
(a) A listing of occupied facilities, buildings, and residences that may be threatened with
flooding due to the failure of the dam.
(b) Mapping that is adequate to clearly delineate the areas of potential inundation
resulting from a failure of the dam. The degree of detail for mapping or listings shall be
determined through consultations between the dam owner and the appropriate
emergency services agencies that are responsible for implementing the emergency action
plan.