R 408.42044
R 408.42044 Manual removal of ceiling and floor systems.
Cite as Mich. Admin. Code R 408.42044
Rule 2044. (1) A floor upon or above which an employee is working and which
will be weakened by manual demolition shall be shored to support the intended load.
(2) An opening that is cut into a floor for disposal of materials shall not be more
than 25% of the total floor area, unless the lateral supports of the removed flooring
remain in place.
(3) An opening that is cut into a floor shall extend the full span of the floor
between supports.
(4) Before a floor is demolished, debris and other material shall be removed
from the area and adjacent areas for a distance of not less than 20 feet.
(5) Before demolishing a floor arch, debris and other material shall be removed
from the arch and other adjacent floor area. Planks that are not less than 2 inches by
10 inches in cross section, full size undressed, shall be provided for, and used by, an
employee to stand on while breaking down a floor arch between beams. The planks
shall be located so as to provide a safe support for the workmen if the arch
between the beams collapses. The open space between planks shall not be more than
16 inches.
(6) A safe walkway, not less than 18 inches wide, formed of planks not less than
2 inches thick if wood, or of equivalent strength if metal, shall be provided for, and
used by, employees when necessary to enable them to reach any point without
walking upon exposed beams.
(7) Planks shall be laid together over solid bearings with the ends overlapping
at least 1 foot.
(8) A floor arch to an elevation of not more than 25 feet above grade may be
removed to provide storage area for debris, if the removal does not endanger the
stability of the structure.