R 425.308
R 425.308 Financial assurance; update.
Cite as Mich. Admin. Code R 425.308
Rule 308. (1) A permittee shall update the calculation of the cost to administer, and to
hire a third party to implement, the reclamation, remediation, and postclosure monitoring
required under R 425.301(2) every 3 years or as the department determines to be necessary.
The update shall include the following:
(a) A description of the reclamation and postclosure monitoring completed since the last
update.
(b) An estimate of the cost to administer, and to hire a third party to implement,
reclamation under the mining, reclamation, and environmental protection plan that has not
been completed, as well as necessary environmental protection measures, including
remediation of any contamination of the air, surface water, or groundwater that is in
violation of the mining permit.
(c) The effects of inflation on the costs of reclamation and postclosure monitoring.
(2) A permittee shall update an assurance instrument required under R 425.301 in
accordance with 1 of the following schedules:
(a) If the amount of the assurance instrument equals or exceeds the cost to administer, and
to hire a third party to implement, the reclamation, remediation, and postclosure monitoring
as originally calculated, multiplied by the Detroit consumer price index as of January 1 of
each year, then the permittee shall update the assurance instrument every 3 years by April
1 of the succeeding year.
(b) If the amount of the assurance instrument does not equal or exceed the cost to
administer, and to hire a third party to implement, the reclamation, remediation, and
postclosure monitoring as originally calculated, multiplied by the Detroit consumer price
index as of January 1 of each year, then the permittee shall update the assurance instrument
by April 1 of the succeeding year.
(3) The department shall provide notice of an adjustment of the financial assurance to any
interested person who has requested notice.