R 281.922a
R 281.922a Permit application review criteria.
Cite as Mich. Admin. Code R 281.922a
Rule 2a. (1) The department shall review a permit application to undertake an activity
listed in section 30304 of the act according to the criteria in section 30311 of the act.
(2) As required by subsection 30311(4) of the act, a permit applicant shall bear the burden
of demonstrating that an unacceptable disruption to aquatic resources will not occur as a
result of the proposed activity and demonstrating either of the following:
(a) The proposed activity is primarily dependent upon being located in the wetland.
(b) There are no feasible and prudent alternatives to the proposed activity.
(3) A permit applicant shall provide adequate information, including documentation as
required by the department, to support the demonstrations required by section 30311 of the
act. The department shall independently evaluate the information provided by the applicant
to determine if the applicant has made the required demonstrations.
(4) A permit applicant shall completely define the purpose for which the permit is sought,
including all associated activities. An applicant shall not so narrowly define the purpose as
to limit a complete analysis of whether an activity is primarily dependent upon being
located in the wetland and of feasible and prudent alternatives. The department shall
independently evaluate and determine if the project purpose has been appropriately and
adequately defined by the applicant, and shall process the application based on that
determination.
(5) The department shall consider a proposed activity as primarily dependent upon being
located in the wetland only if the activity is the type that requires a location within the
wetland and wetland conditions to fulfill its basic purpose; that is, it is wetland-dependent.
Any activity that can be undertaken in a non-wetland location is not primarily dependent
upon being located in the wetland.
(6) An alternative is feasible and prudent if both of the following provisions apply:
(a) The alternative is available and capable of being done after taking into consideration
cost, existing technology, and logistics.
(b) The alternative would have less adverse impact on aquatic resources. A feasible and
prudent alternative may include any or all of the following:
(i) Use of a location other than the proposed location.
(ii) A different configuration.
(iii) Size.
(iv) Method that will accomplish the basic project purpose.
The applicant shall demonstrate that, given all pertinent information, there are no feasible
and prudent alternatives that have less impact on aquatic resources. In making this
demonstration, the applicant may provide information regarding factors such as alternative
construction technologies; alternative project layout and design; local land use regulations
and infrastructure; and pertinent environmental and resource issues. This list of factors is
not exhaustive and no particular factor will necessarily be dispositive in any given case.
(7) If an activity is not primarily dependent upon being located in the wetland, it is
presumed that a feasible and prudent alternative exists unless an applicant clearly
demonstrates that a feasible and prudent alternative does not exist.
(8) Unless an applicant clearly demonstrates otherwise, it is presumed that a feasible and
prudent alternative involving a non-wetland location will have less adverse impact on
aquatic resources than an alternative involving a wetland location.
(9) An area not presently owned by the permit applicant that could reasonably be obtained,
utilized, expanded, or managed in order to fulfill the basic purpose of the proposed activity
is a feasible and prudent alternative location.
(10) An alternative may be considered feasible and prudent even if it does not
accommodate components of a proposed activity that are incidental to or severable from
the basic purpose of the proposed activity.
(11) An alternative may be considered feasible and prudent even if it entails higher costs
or reduced profit. However, the department shall consider the reasonableness of the higher
costs or reduced profit in making its determination.
(12) The department may offer a permit for a modification of an activity proposed in an
application if the proposed activity cannot be permitted under the criteria listed in section
30311 of the act and if the modification makes that activity consistent with the criteria
listed in section 30311 of the act.
(a) The applicant may accept the permit for the modification of the proposed activity by
signing it and returning it to the department within 30 days of the date of the offer. The
permit shall be considered issued upon countersignature by the department.
(b) The permit application is considered denied if the applicant does not sign and return
the permit for the modification of the proposed activity to the department within thirty days
of the date of the offer. The permit applicant may then appeal the denial pursuant to sections
30307(2) and 30319(2) of the act.
(c) The date on which the modification is offered shall be considered the date of the
department's approval or disapproval of the application pursuant to section 30307(2) of the
act.