R 299.2442
R 299.2442 Surface facilities; request for approval; other permits required.
Cite as Mich. Admin. Code R 299.2442
Rule 2442. (1) A permittee shall submit to the supervisor of mineral wells a written
request for approval to construct or substantially modify and operate a surface facility or
flow line. The request may be filed with the application for a permit to drill and operate a
well.
(2) A request for a surface facility shall include all of the following information, or in the
case of a substantial modification, updates of the following information:
(a) An environmental impact assessment.
(b) A scale map showing the location of the proposed surface facility.
(c) Identification of the well or wells to be connected to the surface facility.
(d) Reasonable and necessary measures to protect environmental values associated with
existing adjacent land uses, including berming, screening, and access road location.
(e) Information relative to the approximate distances and directions from the surface
facility or flow line to items identified in R 299.2311(2)(e)(iv).
(f) Identification of the fluid streams to be handled at the surface facility.
(g) A schematic of the flow schemes, including the location and storage capacities of all
on-site surface equipment.
(h) A copy of the spill response plan.
(i) Secondary containment plans showing construction details of dikes and floors of all
secondary containment areas.
(j) Details of tank overfill prevention systems.
(3) A request to construct or substantially modify a flow line shall include all the
following information:
(a) Material specifications for the proposed flow line material, including composition,
burst strength, corrosion resistance and other engineering data to characterize the suitability
of the pipe for transporting the liquid proposed.
(b) Details of flow line construction procedure, including burial depth, method of forming
joins, quality control procedures for joins, procedures for pre-use leak testing and other
information to characterize the installation from the standpoint of minimizing leaks.
(c) Details of flow line operation, including placement of emergency shutoff valves,
maximum anticipated operating pressure, and plans for leak detection by means of any of
the following:
(i) Regular inspections or corridor patrols.
(ii) Installation of monitoring systems for leak detection.
(iii) Flow line pressure testing.
(iv) Any other method and placement of emergency shutoff valves and maximum
anticipated operating pressure.
(d) A scale map showing the proposed route of the flow line.
(e) A copy of the spill response plan. A spill response plan prepared under another part of
the act is acceptable.
(4) Upon receipt of a written request for approval to construct and operate or to
substantially modify and operate a surface facility or flow line, other than a request made
as part of an application for permit to drill and operate a well, the supervisor of mineral
wells or authorized representative of the supervisor of mineral wells shall have up to 30
days to review the request to determine if the request is accurate and administratively
complete.
(5) If the request is determined to be inaccurate or incomplete, then the supervisor of
mineral wells or authorized representative of the supervisor of mineral wells shall, within
the 30-day period, provide the person making the request with a notice that the request is
inaccurate or incomplete and what changes or additional information shall be submitted.
Upon receipt of the requested information, the supervisor of mineral wells or authorized
representative of the supervisor of mineral wells shall have up to an additional 15 days to
review the information to determine if the request is accurate and administratively
complete.
(6) If a request to construct and operate a surface facility or flow line is submitted with an
application to drill and operate a storage or disposal well, and if the supervisor of mineral
wells holds a hearing, as allowed in R 299.2312(m) or R 299.2320, the review process will
continue until the hearing has been conducted and all evidence presented at the hearing has
been reviewed.
(7) Upon completion of the review process, the supervisor of mineral wells or authorized
representative of the supervisor of mineral wells shall approve or deny the request within
11 business days. A request shall be approved if the supervisor of mineral wells determines
that construction and operation of the proposed surface facility or flow line will prevent
waste, protect environmental values, and not compromise public safety. Upon approval by
the supervisor of mineral wells or authorized representative of the supervisor of mineral
wells, a request made under this rule shall become part of the permit to drill and operate
the well or wells served by the surface facility.
(8) A determination of administrative completeness does not mean that additional
information may not be required from the applicant as a result of new circumstances that
come to the attention of the supervisor of mineral wells.
(9) The supervisor of mineral wells shall not approve construction of a surface facility or
flow line by a person or an authorized representative of a person if the person is not eligible
for a permit.
(10) If discharges to the air, surface waters, or groundwater of the state are likely to occur
at a surface facility, then a permittee shall apply for and obtain all necessary state and
federal discharge permits
before operating the surface facility.