R 299.4912
R 299.4912 Landfill construction; natural soil barrier verification.
Cite as Mich. Admin. Code R 299.4912
Rule 912. (1) A natural soil barrier at a landfill that is used to comply with these rules
shall be verified in accordance with this rule. Information collected under this rule shall be
submitted to the solid waste control agency with either the hydrogeological report or, for
existing disposal areas, the construction certification that is submitted under R 299.4921.
(2) An owner or operator shall verify that any natural soil barrier extends to the surface.
Natural soil sites where the soil barrier does not extend to the surface shall include
compacted side cutoff walls or an equivalent barrier to impede the lateral infiltration of
water into the fill and to impede lateral flow of leachate out of the fill interior. The wall or
other barrier shall be equivalent in width and permeability as that of the soil barrier required
by these rules. Hydraulic head buildup outside the wall shall be limited to the extent
necessary to prevent unstable conditions within the wall or liner. The hydraulic head shall
be controlled by gravity or, as an alternative, the hydraulic head of groundwater that does
not constitute an aquifer may be limited by pumping if the system is part of a sewerage
system permitted by the director, or his or her designee, under part 41 of the act.
(3) To use a natural soil barrier, the owner and operator shall demonstrate that the natural
soil barrier does both of the following:
(a) Is in compliance with the thickness and hydraulic conductivity requirements of these
rules. To demonstrate this, the owner and operator shall obtain soil borings on the grid
spacing specified in subrule (4) of this rule and determine all of the following at various
depths:
(i) The particle size distribution, by sieve and hydrometer.
(ii) The Atterberg limits, according to ASTM D4318-95a, which is adopted by reference
in R 299.4135.
(iii) The classification pursuant to the unified soil classification system, ASTM D2487-
93, which is adopted by reference in R 299.4135.
(iv) The hydraulic conductivity of an undisturbed sample by a method specified in R
299.4920.
(b) Provides an adequate subbase for the overlying leachate collection and removal
systems by evaluating the subgrade conditions for stability and correcting unstable areas.
(4) An owner and operator shall obtain soil borings on a grid spacing approved by the
director based on either of the following:
(a) The homogeneity of soils at the site, as determined by a hydrogeologic report.
(b) Geophysical methods that are proposed under subrule (5) of this rule.
(5) An applicant may utilize geophysical methods to replace or supplement borings
specified in subrule (4) of this rule if a plan for such a survey is approved by the director
or his or her designee.