R 322.1016 Inspection and certification of completed projects.
Cite as Mich. Admin. Code R 322.1016
Rule 16. (1) The department may issue a certification for a project after final
inspection, if the project was satisfactorily performed according to state permit.
(2) Where notice of certification is required as a permit condition, the permittee shall
notify the department within 10 days of completion of the project to schedule a final
inspection for certification. The department shall schedule its field inspection of a
completed project when weather conditions will permit a thorough inspection.
(3) When any permit conditions are not complied with, enforcement action may be
brought against the permit holder.