R 323.1709
R 323.1709 Earth change requirements: time; sediment removal; design, installation, and removal of temporary or permanent control measures.
Cite as Mich. Admin. Code R 323.1709
Rule 1709. (1) A person shall design, construct, and complete an earth change in
a manner that limits the exposed area of any disturbed land for the shortest possible
period of time as determined by the county or local enforcing agency.
(2) A person shall remove sediment caused by accelerated soil erosion from runoff
water before it leaves the site of the earth change.
(3) A person shall design a temporary or permanent control measure that is
designed and constructed for the conveyance of water around, through, or from the earth
change area to limit the water flow to a nonerosive velocity.
(4) A person shall install temporary soil erosion and sedimentation control
measures before or upon commencement of the earth change activity and shall maintain
the measures on a daily basis. A person shall remove temporary soil erosion and
sedimentation control measures after permanent soil erosion measures are in place and
the area is stabilized. A person shall stabilize the area with permanent soil erosion
control measures under approved standards and specifications as prescribed by R
323.1710.
(5) A person shall complete permanent soil erosion control measures for all
slopes, channels, ditches, or any disturbed land area within 5 calendar days after final
grading or the final earth change has been completed. If it is not possible to permanently
stabilize a disturbed area after an earth change has been completed or if significant
earth change activity ceases, then a person shall maintain temporary soil erosion and
sedimentation control measures until permanent soil erosion control measures are in
place and the area is stabilized.