R 323.2233
R 323.2233 Land treatment of wastewater; requirements.
Cite as Mich. Admin. Code R 323.2233
Rule 2233. (1) For the purposes of this rule, the land treatment of wastewater shall be
categorized into 1 of 3 of the following general processes:
(a) Slow rate.
(b) Overland flow.
(c) Rapid infiltration.
(2) If land application is considered part of the overall treatment to meet the standards of
R 323.2222, then a discharger shall incorporate the use of slow rate or overland flow
processes in the design.
(3) A land treatment system shall comply with the general requirements for land treatment
systems as described in subrule (4) of this rule as well as the specific requirements
applicable to the type of land treatment system provided in R 323.2234 to R 323.2236. If
a land treatment system includes a combination of 1 or more of the processes, then the
overall system shall comply with the general requirements in subrule (4) of this rule and
its individual component processes shall comply with the applicable requirements provided
in R 323.2234 to R 323.2236. A discharger shall provide detailed design data, as described
in this rule, to the department upon request.
(4) A land treatment system shall meet all of the following requirements:
(a) The system shall be designed, constructed, and operated as follows:
(i) The system shall be designed and constructed to prevent surface runoff from either
entering or exiting the system.
(ii) The system shall be designed and constructed to provide even distribution of
wastewater during application. A header ditch, where used, shall be designed and
constructed to allow for complete drainage after each wastewater loading or shall be lined
to prevent seepage.
(iii) If vegetative cover is utilized and is considered part of the overall treatment system,
then the design and construction of the system shall allow for the mechanical harvesting of
vegetative cover.
(iv) The system shall be designed, constructed, and operated to allow an appropriate
loading cycle. An appropriate loading cycle allows time between loadings for all of the
following:
(A) Soil organisms to biologically decompose organic constituents in the wastewater.
(B) Organic solids on the soil surface to decompose.
(C) The soil to become aerated.
(D) Vegetative cover to utilize available nutrients provided through the application of the
wastewater.
(E) Soil conditions to become unsaturated and aerobic.
(F) Harvesting operations to occur at appropriate times.
(v) The design hydraulic loading or application rate, whether daily, monthly, or annual,
shall not be more than 7% of the permeability of the most restrictive soil layer within the
solum over the area of the discharge as determined by the saturated hydraulic conductivity
method or 12% of the permeability as determined by the basin infiltration method. The
design annual hydraulic loading rate shall not be more than 3% of the permeability of the
solum when determined by either the cylinder infiltration method or air entry permeameter
test method. The methods referenced in this paragraph for determining soil permeability
are adopted by reference in these rules and are contained in the publication entitled
"Methods of Soil Analysis, Part 1, Physical and Mineralogical Properties," Second Edition,
American Society of Agronomy, 1986. The publication may be purchased from the
American Society of Agronomy, 677 South Segoe Road, Madison, Wisconsin 53711-1086,
or the Michigan Department of Environmental Quality, Waste Management Division, P.O.
Box 30241, Lansing, Michigan 48909, at a cost at the time of adoption of these rules of
$65.00, plus shipping and handling. A discharger, if utilizing published information, shall
determine the methodology used to measure the reported hydraulic conductivity. If
published information is utilized and if it is given as a range of expected values, then a
discharger shall use the minimum value given the most restrictive soil layer within the
solum when calculating the hydraulic loading or application rate.
(vi) The system shall be designed, constructed, and operated so as to prevent the
development of sodic conditions within the solum of the discharge area. Sodic conditions
are considered to exist in the solum when the exchangeable sodium percentage, which is
the percentage of the cation exchange capacity of a soil occupied by sodium, is more than
15%. The exchangeable sodium percentage shall be calculated by dividing the quantity of
exchangeable sodium in the solum, in milliequivalents per 100 grams of soil, by the cation
exchange capacity, also in milliequivalents per 100 grams of soil, multiplied by 100.
(b) If phosphorus adsorption within the solum or unsaturated soil column is part of the
overall treatment process, then the system shall be designed as follows:
(i) The available phosphorus adsorptive capacity of the solum or unsaturated soil column
from within the discharge area shall be sufficient to provide the necessary treatment to
ensure that the applicable limit established in the permit is not exceeded for the duration of
the permit.
(ii) The loading cycle shall be designed so as to provide the necessary contact time within
the solum or unsaturated soil column required for phosphorus to be removed from the
applied wastewater through adsorption processes.
(iii) The available phosphorus adsorptive capacity of the discharge area shall be
determined through either of the following methods:
(A) By subtracting phosphorus levels of the unsaturated soil column, determined through
on-site Bray-P1 analysis, from published phosphorus adsorption capacity data for the
solum found within the discharge area. The method and procedure for the Bray-P1 analysis
referenced in this subparagraph are contained in the publication entitled "Methods of Soil
Analysis, Part 3 - Chemical Methods," American Society of Agronomy, 1996. The
publication is adopted by reference in these rules and may be purchased from the American
Society of Agronomy, 677 South Segoe Road, Madison, Wisconsin 53711-1086, or the
Michigan Department of Environmental Quality, Waste Management Division, P.O. Box
30241, Lansing, Michigan 48909, at a cost at the time of adoption of these rules of $65.00,
plus shipping and handling.
(B) By subtracting phosphorus levels of the unsaturated soil column, as determined
through on-site Bray-P1 analysis, from the phosphorus adsorption maximum as determined
through Langmuir isotherm analysis of on site soils, after adjustments for the concentration
of phosphorus in the effluent and fraction of utilization within the solum are made. The
method and procedure for determining phosphorus adsorption maximum through
Langmuir isotherm analysis referenced in this subparagraph are contained in the
publication entitled "Phosphate Sorption Isotherms for Evaluating Phosphorus
Requirements of Soils," Soil Science Society of America Journal, Volume 34, American
Society of Agronomy, 1970. The publication is adopted by reference in these rules and
may be purchased from the American Society of Agronomy, 677 South Segoe Road,
Madison, Wisconsin 53711- 1086, or the Michigan Department of Environmental Quality,
Waste Management Division, P.O. Box 30241, Lansing, Michigan 48909, at a cost at the
time of adoption of these rules of $65.00, plus shipping and handling.
(iv) Unless otherwise specified in a permit issued under R 323.2216 or R 323.2218, each
individual discharge area shall be annually sampled in accordance with the publication
entitled "Michigan State University Extension Bulletin E- 498" or other method approved
by the department, and the samples shall be analyzed for cation exchange capacity,
available Bray-P1 phosphorus, pH, and sodium. Bulletin E-498 is available from Michigan
State University Bulletin Office, 10-B Agriculture Hall, Michigan State University, East
Lansing, Michigan 48824, at a cost of 25 cents per copy at the time of adoption of these
rules. A single copy is free to Michigan residents. A copy of bulletin E-498 may also be
obtained from the Michigan Department of Environmental Quality, Waste Management
Division, P.O. Box 30241, Lansing, Michigan 48909, at a cost at the time of adoption of
these rules of 25 cents, plus shipping and handling.
(c) All of the following operation and maintenance requirements shall be met:
(i) Portions of the wastewater distribution system shall be capable of being taken out of
service for maintenance and other operational activities and to provide rest to portions of
the irrigation area without disrupting applications to other areas of the system.
(ii) All areas within a system shall be accessible for maintenance equipment.
(iii) For slow rate and overland flow treatment systems, the pH of the plow layer within
the discharge area shall be maintained between 6.0 and 7.5 standard units.
(iv) The discharge to a land treatment system shall be limited so that the discharge volume
combined with the precipitation from a 10-year frequency, 24- hour duration rainfall event
does not overflow the designed discharge area.
(d) For the purposes of the issuance of a permit under R 323.2218, in determining
discharge limitations, the department shall consider all of the following:
(i) Past operating performance.
(ii) The ability of the solum or the unsaturated soil column to treat the pollutants of
concern in the discharge.
(iii) Hydrogeologic characteristics of the site.
(iv) Other pertinent information.