R 324.1130
R 324.1130 Requirements for certain gathering lines, flow lines, and facility piping.
Cite as Mich. Admin. Code R 324.1130
Rule 1130. (1) A gathering line, installed after the effective date of these amendatory rules
carrying gas with more than 300 ppm hydrogen sulfide shall be subject to the provisions
for design, construction, testing, maintenance, and operation as specified in administrative
rules promulgated under Act No. 165 of the Public Acts of 1969, as amended, being
§483.151 et seq. of the Michigan Compiled Laws.
(2) A flow line or facility piping, carrying gas from a class I H2S well and which is subject
to a maximum working pressure in excess of 125 psig shall be subject to the provisions for
design, construction, testing, maintenance, and operation as specified in administrative
rules promulgated under Act No. 165 of the Public Acts of 1969, as amended, being
§483.151 et seq. of the Michigan Compiled Laws.
(3) A person or a permittee shall not install a flow line or gathering line, carrying gas from
a class I H2S or class II H2S well, or modify an existing flow line or gathering line to serve
additional class I H2S or class II H2S wells, unless all of the following provisions are met:
(a) The person or permittee shall calculate the 100 ppm radius of exposure, using either
the equation set forth in R 324.1102(c) or another dispersion model accepted by the
supervisor. The calculation shall be based upon the reasonably expected concentration of
hydrogen sulfide to be transported in the flow line or gathering line, the maximum actual
operating pressure, and the volume of gas that could be released from the flow line or
gathering line, accounting for any automatic shut-in systems and blocking valves that will
be utilized.
(b) If an existing structure used for public or private occupancy, an existing area
maintained for public recreation or the edge of the traveled portion of an existing interstate,
united states, or state highway falls within the 100 ppm radius of exposure, the person or
permittee shall prepare a construction and operation plan that incorporates reasonable
measures to reduce the potential for public exposure to hydrogen sulfide from a release that
might occur. The construction and operation plan shall consider appropriate construction
standards, routing alternatives, monitoring equipment, automatic controls for source shut-
in, or other available engineering methods. The person or permittee shall submit the
construction and operation plan to, and receive the approval of the supervisor or authorized
representative of the supervisor. The supervisor or authorized representative of the
supervisor shall have 30 days to approve the plan or to require modifications or additional
information.
(c) Repair and maintenance of an existing flow line or gathering line are exempt from the
provisions of this subrule.
(4) Gathering lines, flow lines, or facility piping are not subject to this rule if they are
subject to the issuance of a certificate of public convenience and necessity by the Michigan
public service commission under the provisions of Act 9 of the Public Acts of 1929, as
amended, being §483.101 et seq. of the Michigan Compiled Laws or are subject to
regulation by the Michigan public service commission under the provisions of Act No. 165
of the Public Acts of 1969, as amended, being §483.151 et seq. of the Michigan Compiled
Laws.