R 325.10720e
R 325.10720e Enhanced treatment for Cryptosporidium; reporting and recordkeeping requirements.
Cite as Mich. Admin. Code R 325.10720e
Rule 720e. (1) Subpart H supplies that are subject to R 325.10611d shall report sampling
schedules under 40 CFR §141.702 and source water monitoring results under 40 CFR
§141.706 unless they notify the department that they will not conduct source water
monitoring due to meeting the criteria of 40 CFR §141.701(d). These Subpart H supplies
are also considered "supplies" in this rule. The department adopts 40 CFR §141.701, 40
CFR §141.702, and 40 CFR §141.706 by reference in R 325.10720b.
(2) Supplies shall report their Cryptosporidium bin classification as described in R
325.10611e.
(3) Supplies shall report disinfection profiles and benchmarks to the department as
described in R 325.10720c to R 325.10720d before making a significant change in
disinfection practice.
(4) Supplies shall report to the department under the following table for the microbial
toolbox options used to comply with treatment requirements under R 325.10611f.
Alternatively, the department may approve a supply to certify operation within required
parameters for treatment credit rather than reporting monthly operational data for toolbox
options.
Microbial Toolbox Reporting Requirements
Toolbox option
Supplies shall submit all of
the following information:
On the following schedule:
(a) Watershed control
program (WCP)
(i) Notice of intention to
develop a new or continue
an existing watershed
control program.
Not later than 2 years
before the applicable
treatment compliance date
in R 325.10611g.
(ii) Watershed control plan
Not later than 1 year before
the applicable treatment
compliance date in R
325.10611g.
(iii) Annual watershed
control program status
report.
Every 12 months, beginning
1 year after the applicable
treatment compliance date
in R 325.10611g.
(iv) Watershed sanitary
survey report.
For community water
supplies, every 3 years
beginning 3 years after the
applicable treatment
compliance date in R
325.10611g. For
noncommunity water
supplies, every 5 years
beginning 5 years after the
applicable treatment
compliance date in R
325.10611g.
(b) Alternative
source/intake management
Verification that supply has
relocated the intake or
adopted the intake
withdrawal procedure
reflected in monitoring
results.
Not later than the applicable
treatment compliance date
in R 325.10611g.
(c) Presedimentation
Monthly verification of all
of the following:
(i) Continuous basin
operation.
(ii) Treatment of 100% of
the flow.
(iii) Continuous addition
of a coagulant.
(iv) Not less than 0.5-log
mean reduction of influent
turbidity or compliance
with alternative department
approved performance
criteria.
Monthly reporting within
10 days following the
month in which the
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
Toolbox option
Supplies shall submit all of
the following information:
On the following schedule:
(d) 2-stage lime softening
Monthly verification of
both of the following:
(i) Chemical addition and
hardness precipitation
occurred in 2 separate and
sequential softening stages
before filtration.
(ii) Both stages treated
100% of the plant flow.
Monthly reporting within
10 days following the
month in which the
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(e) Bank filtration
(i) Initial demonstration of
both of the following:
(A) Unconsolidated,
predominantly sandy
aquifer.
(B) Setback distance of
not less than 25 ft. (0.5-
log credit) or 50 ft. (1.0-
log credit).
Not later than the applicable
treatment compliance date
in R 325.10611g.
(ii) If monthly average of
daily max turbidity is
greater than 1 NTU then
supply shall report result
and submit an assessment
of the cause.
Report within 30 days
following the month in
which the monitoring was
conducted, beginning on the
applicable treatment
compliance date in R
325.10611g.
(f) Combined filter
performance
Monthly verification of
combined filter
effluent (CFE) turbidity
levels less than or equal to
0.15 NTU in not less than
95% of the 4-hour CFE
measurements taken each
month.
Monthly reporting within
10 days following the
month in which the
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
Toolbox option
Supplies shall submit all of
the following information:
On the following schedule:
(g) Individual filter
performance
Monthly verification of
both of the following:
(i) Individual filter
effluent (IFE ) turbidity
levels less than or equal to
0.15 NTU in not less than
95% of samples each
month in each filter.
(ii) No individual filter
greater than 0.3 NTU in 2
consecutive readings 15
minutes apart.
Monthly reporting within
10 days following the
month in which the
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(h) Demonstration of
performance
(i) Results from testing
following a department
approved protocol.
Not later than the applicable
treatment compliance date
in R 325.10611g.
(ii) As required by the
department, monthly
verification of operation
within conditions of
department approval for
demonstration of
performance credit.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(i) Bag filters and cartridge
filters
(i) Demonstration that
both of the following
criteria are met:
(A) Process meets the
definition of bag or
cartridge filtration.
(B) Removal efficiency
established through
challenge testing that meets
criteria in R 325.10611d to
R 325.10611n and R
325.10720b to R
325.10720e.
Not later than the applicable
treatment compliance date
in R 325.10611g.
(ii) Monthly verification
that 100% of plant flow
was filtered.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
Toolbox option
Supplies shall submit all of
the following information:
On the following schedule:
(j) Membrane filtration
(i) Results of verification
testing demonstrating both
of the following:
(A) Removal efficiency
established through
challenge testing that meets
criteria in R 325.10611d to
R 325.10611n and R
325.10720b to R
325.10720e.
(B) Integrity test method
and parameters, including
resolution, sensitivity, test
frequency, control limits,
and associated baseline.
Not later than the applicable
treatment compliance date
in R 325.10611g.
(ii) Monthly report
summarizing the following:
(A) All direct integrity
tests above the control
limit.
(B) If applicable, a
turbidity or alternative state
approved indirect integrity
monitoring results
triggering direct integrity
testing and the corrective
action that was taken.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(k) Second stage filtration
Monthly verification that
100% of flow was filtered
through both stages and
that first stage was
preceded by coagulation
step.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(l) Slow sand filtration as
secondary filter.
Monthly verification that
both a slow sand filter and
a preceding separate stage
of filtration treated 100% of
flow from surface water or
GWUDI sources.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
Toolbox option
Supplies shall submit all of
the following information:
On the following schedule:
(m) Chlorine dioxide
Summary of CT values for
each day as described in R
325.10611m.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(n) Ozone
Summary of CT values for
each day as described in R
325.10611m.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(o) UV
(i) Validation test results
demonstrating operating
conditions that achieve
required UV dose.
Not later than the applicable
treatment compliance date
in R 325.10611g.
(ii) Monthly report
summarizing the
percentage of water
entering the distribution
system that was not treated
by UV reactors operating
within validated conditions
for the required dose as
specified in R 325.10611m.
Within 10 days following
the month in which
monitoring was conducted,
beginning on the applicable
treatment compliance date
in R 325.10611g.
(5) Supplies shall retain records under R 325.11508.