Rule 205. (1) The department shall not approve a permit to install for a stationary source,
process, or process equipment that meets the definition of a major stationary source or
major modification under any part of these rules unless the requirements specified in
subdivisions (a) and (b) of this subrule have been met. In addition, except as provided in
subrule (3) of this rule, the department shall not approve a permit to install that includes
limitations which restrict the potential to emit from a stationary source, process, or process
equipment to a quantity below that which would constitute a major source or major
modification under any part of these rules unless both of the following requirements have
been met:
(a) The permit to install contains emission limits that are enforceable as a practical matter.
An emission limit restricts the amount of an air contaminant that may be emitted over some
time period. The time period shall be set in accordance with the applicable requirements
and, unless a different time period is provided by the applicable requirement, should
generally not be more than 1 month, unless a longer time period is approved by the
department. A longer time period may be used if it is a rolling time period, but shall not be
more than an annual time period rolled on a monthly basis. If the emission limit does not
reflect the maximum emissions of the process or process equipment operating at full design
capacity without air pollution control equipment, then the permit shall contain 1of the
following:
(i) A production limit that restricts the amount of final product that may be produced over
the same time period used in the emission limit and that comports with the true design and
intended operation of the process or process equipment.
(ii) An operational limit that restricts the way the process or process equipment is operated
and that comports with the true design and intended operation of the process or process
equipment. An operational limit may include conditions specifying any of the following:
(A) The installation, operation, and maintenance of air pollution control equipment.
(B) The hours of operation of the stationary source, process, or process equipment, if the
hours are less than continuous.
(C) The amount or type of raw materials used by the stationary source, process, or process
equipment.
(D) The amount or type of fuel combusted by the stationary source, process, or process
equipment.
(E) The installation, operation, and maintenance of a continuous gas flow meter and a
continuous emission monitor for the air contaminant for which an enforceable emission
limit is required.
(iii) For volatile organic compound surface coating operations where an add-on control is
not employed, an emission or usage limit coupled with a requirement to calculate or
demonstrate daily compliance.
(b) A draft permit has been subjected to the public participation process specified in
section 5511(3) of the act. The department shall provide a copy of the draft permit to the
United States environmental protection agency for review and comment at or before the
start of the public comment period. The department shall also provide a copy of each final
permit to install issued pursuant to this rule to the United States environmental protection
agency.
(2) The department shall not approve a permit to install to construct a major source or
reconstruct a major source under any applicable requirement of section 112 of the clean air
act unless the requirements of subrule (1)(a) and (b) of this rule have been met. In addition,
except as provided in subrule (3) of this rule, the department shall not approve a permit to
install that includes limitations which restrict the potential to emit of a stationary source,
process, or process equipment to a quantity below that which would constitute a major
source or modification under any applicable requirement of section 112 of the clean air act
unless the requirements of subrule (1)(a) and (b) of this rule have been met.
(3) The department may approve a permit to install that includes limitations that restrict
the potential to emit of a stationary source, process, or process equipment to a quantity
below that which would constitute a major source or major modification under any part of
these rules without meeting the requirement of subrule (1)(b) of this rule if the emission
limitations restrict the potential to emit of the stationary source, process, or process
equipment to less than 90% of the quantity referenced in the applicable requirement.