Minn. R. 4620.3420

EMERGENCY PROJECT NOTICE

Last amended: 1995Year: 2026Length: 249 wordsOfficial source
Subpart 1. Emergency project begun during work hours. For an emergency project which begins between 8:00 a.m. and 4:30 p.m. on the days the Minnesota Department of Health is open, the commissioner must receive from the licensed asbestos contractor: A. a completed notice on a form provided by the commissioner which seeks only information the commissioner considers reasonably necessary to inspect the project and issue the permit as soon as possible before the project begins; and B. within five calendar days after the emergency project begins, the items listed in part 4620.3410 , subpart 2, items B and C. Subp. 2. Emergency project begun after work hours. For an emergency project which begins at a time other than the times specified in subpart 1, the commissioner must receive from the licensed asbestos contractor: A. a completed notice on a form provided by the commissioner which seeks only information the commissioner considers reasonably necessary to inspect the project and issue the permit by 4:30 p.m. of the next day the department is open; and B. within five calendar days after the emergency project begins, the items listed in part 4620.3410 , subpart 2, items B and C. Subp. 3. Amendments to emergency project notice. Amendments to the emergency project notice form must be made according to part 4620.3415 , items A, C, and D. An amendment to an emergency project notice must not include additional asbestos-containing material to be abated unless that material is part of the same emergency situation.
Minn. R. 4620.3420: EMERGENCY PROJECT NOTICE | Justis AI