7 CSR 10-24.130
Modified Design-Build Procedures
PURPOSE: This rule describes the modified
design-build selection procedures.
(1) Modified design-build selection procedures, the lowest price technically acceptable
source selection process, may be used for any
project.
(2) The Request for Proposal (RFP) will
clearly state the following:
(A) The identification of evaluation factors
and significant subfactors that establish the
requirements of acceptability; and
(B) That award will be made on the basis
of the lowest evaluated price of proposals
meeting or exceeding the acceptability standards for noncost factors.
(3) Tradeoffs will not be permitted, unless the
tradeoff is in accordance with 7 CSR 1024.110. However, the commission may incorporate cost-plus-time (A+B) bidding procedures, lane rental, or other cost-based
provisions in such contracts.
(4) Proposals will be evaluated for acceptability but not ranked using the noncost/price
factors.
(5) Exchanges may occur in accordance with
7 CSR 10-24.300 through 7 CSR 10-24.330.
AUTHORITY: sections 226.020, RSMo 2000
and 226.030 and 227.107, RSMo Supp.
2004.* Original rule filed Aug. 15, 2005,
effective Feb. 28, 2006.
*Original authority: 226.020, RSMo 1939; 226.030,
RSMo 1939, amended 1965, 2003, 2004; and 227.107,
RSMo 2002.