8 CSR 30-3.020
Definitions
PURPOSE: This rule sets forth the definition
of certain terms for purposes of issuance and
use of annual and general wage orders under
the Prevailing Wage Law, sections 290.210–
290.580, RSMo and the rules in this chapter.
(1) The term construction of public works
generally includes construction activity as
distinguished from manufacturing, furnishing
of materials or servicing and maintenance
work. The term includes, without limitation,
the construction of buildings, structures and
improvements of all types, such as bridges,
dams, plants, highways, parkways, streets,
subways, tunnels, sewers, mains, power lines,
pumping stations, heavy generators, railways,
airports, terminals, docks, piers, wharves,
ways, lighthouses, buoys, jetties, breakwaters,
levees, canals, dredging, shoring, rehabilitation and reactivation of plants, scaffolding,
drilling, blasting, excavating, clearing and
landscaping. The manufacture or furnishing
of materials, articles, supplies or equipment
is not construction of public works within the
meaning of the Prevailing Wage Law unless
conducted in connection with and at the site
of construction. The term construction of
public works also means all work done in the
construction or development of a public
works project, including without limitation,
altering, remodeling, demolishing existing
structures, installation on the site of the construction of items fabricated off-site, painting
and decorating, the transporting of materials
and supplies to or from the site of the construction by the employees of the construction
contractor or construction subcontractor, and
the manufacturing or furnishing of materials,
articles, supplies or equipment on the site of
the construction by persons employed by the
contractor or subcontractor.
(2) The term site of the building or construction job means the physical place(s) where
the public works are to be constructed, and
also means other adjacent or nearby property
used by the contractor or subcontractor in
that construction which can reasonably be
said to be included in the site. Except as otherwise provided in this section, fabrication
plants, mobile factories, batch plants, borrow
pits, job headquarters, tool yards and the like,
are part of the site of the building or construction job provided they are dedicated in a
substantial degree to the performance of the
public works project, and are so located in
proximity to the actual construction location
that it would be reasonable to include them.
The dedication of seventy-five percent (75%)
or more of the output of a fabrication plant,
batch plant and the like, to the public works
project raises a rebuttable presumption that
the facility is part of the site of the building
or construction job. The presumption may be
rebutted by evidence showing that the facility
was established for other legitimate commercial purposes that make the facility useful
well after the public works project has been
completed. Not included in the site of the
building or construction job are permanent
home offices, branch plant establishments,
fabrication plants and tool yards of a contractor or subcontractor whose location and continuance in operation are determined wholly
without regard to a particular public works
project. In addition, fabrication plants, batch
plants, borrow pits, job headquarters, tool
yards and the like, of a commercial supplier
or materialman which are established by a
supplier of materials for the project before
opening of bids and not on the project site are
not included in the site of the building or construction job. The permanent, previously
established facilities are not a part of the site
of the building or construction job, even
where the operations for a period of time may
be dedicated exclusively, or nearly so, to the
performance of a public works project.
AUTHORITY: section 290.240, RSMo 1994.*
Original rule filed Aug. 24, 1990, effective
April 29, 1991. Amended: Filed July 17,
1995, effective Jan. 30, 1996.
*Original authority: 290.240, RSMo 1957, amended
1959.