11 CSR 45-53.060
Disclosure of Development Process
PURPOSE: This rule sets forth the required
disclosure of the development process for a
Class D license.
(1) An applicant for a Class D license must
disclose with regard to the development of its
racing facility—
(A) The total cost of facility construction
or any modifications of an existing facility,
distinguishing between fixed costs and projections;
(B) Separate identification of the following
costs, if applicable, distinguishing between
fixed costs and projections:
1. Facility design;
2. Land acquisition;
3. Site preparation;
4. Improvements and equipment separately identifying the costs of the items
required in 12 CSR 50-13.050(D)—(O) and
other categories of improvements and equipment;
5. Interim financing;
6. Permanent financing; and
7. Organization, administrative, accounting and legal;
(C) Documentation of fixed costs;
(D) The schedule for construction, if any,
of the facility or any modifications to an
existing facility including estimated completion date;
(E) Schematic drawings;
(F) Copies of any contracts with and performance bonds for each of the following:
1. Architect or other design professional;
2. Project engineer;
3. Construction engineer;
4. Contractors and subcontractors; and
5. The equipment procurement personnel; and
(G) Evidence of acquisition or lease of the
site by the applicant. If the site is not owned
or currently leased by the applicant, the
applicant must disclose the plans for the
acquisition or lease or other use of the site.
AUTHORITY:
sections
313.580.1
and
313.580.2, RSMo 1986.* This rule originally
filed as 12 CSR 50-13.060. Emergency rule
filed June 5, 1986, effective June 15, 1986,
expired Oct. 13, 1986. Original rule filed
June 12, 1986, effective Oct. 27, 1986.
Moved to 11 CSR 45-53.060, effective Aug.
28, 1995.
*Original authority: 313.580, RSMo 1986.