11 CSR 90-2.040
Project Administration
PURPOSE: This rule establishes the process the board will use to
administer approved 911 communications service projects.
(1) Project Agreements. Approved applicants and their 911
services authorities must enter into project agreements with
the board. The project agreements will contain the terms and
conditions of the board’s award of financial assistance. For
projects involving a loan, the project agreements will contain
the interest rate, repayment amount, number of payments,
and a repayment schedule determined by the board based
on the total project costs, amount of the loan, amount of
match in local funds, award priority areas addressed by the
project, and purposes listed in section 650.330.4.(16), RSMo to
be accomplished. The project agreements will require each
eligible applicant’s 911 services authority to agree to repay
on behalf of the eligible applicant, any portion of the loan
transmitted directly to them or used to pay costs incurred on
their behalf.
(2) Fund Disbursement. The board will not disburse any financial
assistance for any project until a project agreement has been
fully executed, and it has received a written certification of
approval, such as a resolution, of the project agreement from
the applicants’ respective governing bodies or the applicants
have demonstrated to the board’s satisfaction that no such
approval is required.
(3) Project Agreement Change Requests. 911 services authorities
must obtain written approval of the board or its designee
before making any material changes to an approved project.
(A) 911 services authorities may request approval of the board
or its designee for a material change to an approved project
by submitting a written request by electronic mail to the
electronic mail address in the project agreement or by certified
or registered mail addressed to “Missouri 911 Service Board” at
PO Box 2126, Jefferson City, MO 65102.
(B) Requests must include a detailed explanation of the
circumstances warranting the requested change.
(C) The board or its designee, in its sole discretion, will
determine all change requests on a case-by-case basis and
advise the requestor in writing of the board’s decision. If a
change request is denied, the writing will advise of the protest
procedure in 11 CSR 90-1.050.
(4) Extensions of Time. 911 services authorities may request
extensions of the project completion deadline in their project
agreement by submitting a written request by electronic mail
to the electronic mail address in the project agreement or by
certified or registered mail addressed to “Missouri 911 Service
Board” at PO Box 2126, Jefferson City, MO 65102.
(A) Requests must include a detailed explanation of the
circumstances warranting extension of the project completion
deadline.
(B) Requests for extension must be received by the board at
least forty-five (45) calendar days before the expiration of the
current project completion deadline.
(C) The board will not consider any request for extension of a
project completion deadline that exceeds six (6) months.
(D) The board or its designee, in its sole discretion, will
determine all requests for extensions on a case-by-case basis
and will grant a timely submitted first request for extension
when the requestor demonstrates an inability to meet its
project completion deadline despite a good faith effort to
do so. Second and subsequent requests for extension will
be viewed unfavorably and will only be granted when the
board determines that substantial justification or extreme
circumstances exist.
(E) The board or its designee will notify the requestor of its
decision in writing. If a request for extension is denied, the
writing will advise of the protest procedure in 11 CSR 90-1.050.
(5) Audits. The board will conduct audits as it deems
appropriate. Applicants and 911 services authorities shall
provide any information requested by the board and access to
the project site.
(6) Funding Change or Termination. The board reserves the
right to reduce, suspend, or terminate the provision of financial
assistance before or after execution of the project agreement
due to a lack of funds, misrepresentations on the application,
a failure to comply with the project agreement or applicable
laws, or other conduct deemed inappropriate by the board.
AUTHORITY: sections 650.330 and 650.335, RSMo Supp. 2020.*
Emergency rule filed May 6, 2020, effective May 21, 2020, expired
Feb. 25, 2021. Original rule filed May 7, 2020, effective Dec. 30,
2020.
*Original authority: 650.330, RSMo 1997, amended 2017, 2018, 2019 and 650.335,
RSMo 2018.