19 CSR 30-30.040
Preparation of Plans and Specifications for Ambulatory Surgical Centers
PURPOSE: The Division of Health Resources, Department of
Health has the authority to establish construction standards
for ambulatory surgical centers. This rule provides procedures
to follow in the submission of plans and specifications for new
construction.
(1) Preliminary Plans and Sketches.
(A) When construction is contemplated, either for new
buildings additions to existing buildings or material alterations
to existing buildings, the preliminary plans or sketches shall be
submitted in duplicate to the Department of Health for review
and approval before the preparation of working drawings is
undertaken. The preliminary plans may be reviewed by the
Department of Health in schematic form, but before they are
declared acceptable for procedure with working drawings
and specifications, they should also include the following
information, stated briefly and not in detailed form required in
working drawings and specifications:
1. Site plan showing scale, orientation, street names,
topography, walks, drives, fire lanes, parking areas and utilities
including fire hydrant location;
2. Plans and elevations of the buildings at a scale of not
less than one-eighth inch to one foot no inches (1/8":1' 0");
3. Rooms and corridors, designated by name and number;
4. Windows. Note, wired glass where it is required;
TABLE I
Pressure Relationships and Ventilation of Certain Areas
Pressure
Minimum Air
Minimum Total
All Air
Recirculated
Relationship to
Changes of Outdoor
Air Changes
Exhausted
Within
Area Designation
Adjacent Areas
Air Per Hour
Per Hour
Directly to Outdoors
Room
Operating Room
P
5
15
Optional
No
Recovery
P
2
26
Optional
No
Patient Area Corridor
E
2
24
Optional
No
Treatment Room
E
2
6
Optional
No
Laboratory
N
2
6
Optional
No
Soiled Workroom
N
2
4
Yes
No
Clean Workroom
P
2
4
Optional
Optional
Toilet Room
N
10
Yes
No
Janitor’s Closet
N
10
Yes
No
P=Positive
N=Negative
E=Equal
SENIOR SERVICES
5. Doors, including door swings. Identify fire doors by time
rating and Underwriters’ Laboratories label;
6. Plumbing fixtures. Show fixtures in proper shape and
scale for positive recognition. Identify special types such as
service sinks and clinic sinks;
7. Plans of rooms shall indicate principal items of furniture
accurately scaled;
8. All other principal items of equipment such as boilers,
chiller, cooling tower, electrical substations, tanks, air handlers,
fan-coil units, kitchen equipment, laundry equipment,
cabinets, counters and any other items which take up space
and affect the final layout;
9. Fire and smoke-barrier partition designations;
10. Floor lines, top ceiling line and grade lines, designated
and preferably dimensioned, and with basic elevations shown;
11. Ceiling heights of principal rooms and also of each
room for which the rules establish a minimum ceiling height.
Only one (1) typical room of a group need be so shown;
12. Area of each room for which the rules establish a
minimum area. Only one (1) typical room of a group need be
so noted; and
13. Brief noted descriptions of the general construction
and finish; the structural system; the heating, ventilating
and air-conditioning systems, including the fuel supply; the
plumbing system including the water supply and sewage
disposal; and the electrical system.
(B) In the case of a project which is an addition to an existing
building, it will be necessary to give the Department of Health
sufficient information about the existing building on which
to base a determination of acceptability of the plans for the
addition. This information shall cover all items required to be
provided in an ambulatory surgical center by the rules of the
Department of Health and shall be submitted in the form as
required for the particular project by the Department of Health.
(2) Working Drawings and Specifications.
(A) Working drawings and specifications, complete in all
respects, shall be submitted in duplicate, covering all phases
of the construction project, including site preparation; paving;
general construction; mechanical work, including plumbing,
heating, ventilating and air conditioning; electrical work and
all built-in equipment, including elevators, kitchen equipment,
cabinet work, etc.
1. Each sheet of the plans and each set of the specifications
shall identify the project by name and location and shall
bear the names and addresses of the architect or professional
engineer and the owner.
2. Each sheet of the plans and each set of specifications
shall bear the official seal and signature of the registered
architect or registered professional engineer who prepared it.
3. Each set of the plans and each set of specifications shall
bear the date of its completion or its latest revision.
4. The plans shall be on sheets of the same size, securely
bound into complete sets, with the sheets in the proper order.
The specifications shall be securely bound into complete sets.
(B) The working drawings and specifications shall include
the following: the material set out in paragraphs (1)(A)1.–12. of
this rule; courses and distances of property lines; dimensions
and locations of any building, structures, easements, rights-ofway or encroachments on the site; details of party walls, and
walls and foundation adjacent to lot line; detailed information
by the city engineer or other official report as to established
curbs, buildings lines, streets, alleys, sidewalks; all utilities
including size, characteristics and location of these services,
piping, mains, sewers, poles, wires, hydrants and manholes
upon, over or under the site and location of high pressure
gas lines within one thousand two hundred feet (1200') of the
building; complete information as to the disposal of sanitary,
storm water and subsoil drainage; official datum upon which
elevations are based and benchmark established on or adjacent
to the site; contours on elevations at two foot (2') intervals over
site and elevations at the bottom of excavation; and thickness,
consistency, character and estimated safe bearing value of
various strata encountered.
AUTHORITY: section 197.225, RSMo 1986. This rule was previously
filed 13 CSR 50-30.040. Original rule filed Dec. 2, 1975, effective
Feb. 1, 1976.