10 CSR 100-5.010
Claims for Cleanup Costs
PURPOSE: This rule describes who can
make claims against the Petroleum Storage
Tank Insurance Fund, when and how such
claims must be made, requirements to seek
preapproval of costs, what costs the fund considers eligible, and how to request payment
from the fund.
(1) A notice of claim must be submitted in
writing to the board as soon as reasonably
possible after a fund participant or beneficiary described in section (4) of this rule:
(A) Knows or reasonably suspects that a
release from a tank has occurred;
(B) Receives notice of the assertion of an
obligation to pay cleanup costs or damages as
a result of a release from tanks on the property; or
(C) Learns that petroleum contamination
exists on or near a tank site at levels such that
a cleanup is required by the Department of
Natural Resources.
(2) Except as described below, prior to the
initiation of any work where cleanup costs
will be incurred, whether within the
deductible or in excess of the deductible, the
cleanup costs must first be approved by the
board. Failure to obtain approval of the
cleanup costs may subject the fund participant or fund beneficiary to reduction or
denial of benefits.
(A) Fund participants or beneficiaries are
not required to obtain prior approval of the
board for the costs of necessary first aid or
emergency response.
(B) In cases where first aid or emergency
response is provided, the fund participant or
beneficiary must notify the board of such
activities as soon as practical.
(3) The board retains final authority to make
a determination concerning all eligibility
issues, including but not limited to, whether
costs for products and services were reasonable, and whether the costs incurred were
necessary to achieve the cleanup required by
the Department of Natural Resources.
(4) Fund participants or beneficiaries may
request pre-approval and reimbursement of
costs from the fund—
(A) For a release that occurs or is discovered on a date that the participant is participating in the fund.
1. The fund participant must provide
notice of claim to the board while the participant is insured and before expiration or cancellation of the participant’s coverage, or during an extended reporting period granted by
the board under 10 CSR 100-4.010 or 10
CSR 100-4.020.
2. Fund participants must get cleanup
costs approved in advance, as described in
this rule.
3. A fund participant who has properly
made a claim may request that the board
assign his or her benefits for cleanup costs to
another party, and the board may, with the
consent of the other party and at the board’s
sole discretion, agree to such assignment;
(B) For a site where one (1) or more
petroleum storage tank(s) was/were in use on
December 31, 1997, the owner or operator
applied to participate in the fund by December 31, 1997, that application was ultimately
accepted by the board, there are ongoing
costs of cleanup associated with a release
from one (1) or more of those tanks which
occurred prior to the date the application was
accepted, and the cleanup began after August
28, 1989.
1. Fund participants must get cleanup
costs approved in advance, as described in
this rule.
2. In order to maintain its status as an
eligible site, the owner or operator of any
petroleum storage tanks at the site must maintain participation in the fund as long as such
tanks are in use. Failure to do so shall result
in the site becoming ineligible; costs incurred
after the date of cancellation or nonrenewal of
participation in the fund are not eligible.
Should the owner or operator elect to participate in the fund again, he or she may
become eligible under subsection (4)(A) for
any new release;
(C) For a site where a release occurred as
a result of the operation of one (1) or more
petroleum storage tanks, cleanup began or
will begin after August 28, 1989, and the
tank(s) from which the release occurred
was/were taken out of use prior to December
31, 1997, provided such site was documented
by or reported to the Department of Natural
Resources prior to December 31, 1997.
1. For the purposes of this subsection,
evidence of a site being documented by or
reported to the Department of Natural
Resources may include, but is not limited to:
A. Completion of a tank registration
form;
B. Completion of the notification
form circulated by the Department of Natural
Resources in 1995–1997;
C. A letter, sent via U.S. mail or
overnight delivery service, identifying the
location of the site and indicating the existence or prior existence of tanks on the site;
D. A written message transmitted via
facsimile, identifying the location of the site
and indicating the existence or prior existence
of tanks on the site;
E. A Site Assessment Report or similar report, submitted to the department, identifying the site as one where tanks were previously operated; or
F. Any other similar documentation
which is determined by the board to provide
reasonable evidence of such fact.
2. Fund beneficiaries may be required
by the board to provide evidence that the site
was documented by or reported to the
Department of Natural Resources prior to
December 31, 1997.
3. Fund beneficiaries must get cleanup
costs approved in advance, as described in
this rule;
(D) For a site described in subsection
(4)(B) or (4)(C), except the release occurred
and was being remediated prior to August 28,
1989.
1. Fund participants and beneficiaries
must get cleanup costs approved in advance,
as described in this rule; and
(E) For a site where underground storage
tanks which contained petroleum were taken
out of use prior to December 31, 1985, and
the current owner purchased such site before
December 31, 1985, provided such site was
reported to the board on or before June 30,
2000. For the purposes of this subsection,
current owner shall mean the person who
owns a site at the time it is reported to the
Petroleum Storage Tank Insurance Fund
Board of Trustees or its designated representative.
1. Fund beneficiaries must get cleanup
costs approved in advance, as described in
this rule.
(5) Fund participants or beneficiaries may not
receive monies from the fund for the following sites:
(A) Sites owned by a railroad corporation,
as defined in section 388.010, RSMo, or airline company as defined in section 155.010,
RSMo, at the time the release occurred;
(B) Sites contaminated by a release from a
tank that—
1. Is or was used to store hazardous substances when the release occurred;
2. Is a farm or residential tank of one
thousand one hundred (1,100) gallons or less,
which is used for storing motor fuel for noncommercial purposes;
3. Is or was used, at the time of the
release, for storing heating oil for consumptive
use on the premises;
4. Is a septic tank or part of a storm
water or waste water collection system;
5. Is a flow-through process tank;
6. Is situated in an underground area,
such as a basement, the tank is on or above
the floor; or
7. Is part of a transformer, circuit breaker, or similar electrical equipment; and
(C) Sites contaminated by a release of
petroleum from a tank which is or was located at a refinery, pipeline terminal, or marine
terminal.
(6) The following persons may request preapproval of costs and reimbursement from the
fund:
(A) A fund participant;
(B) A fund beneficiary; or
(C) A creditor, or the creditor’s subsidiary,
who is a successor in interest as defined in
section 319.131.3, RSMo.
(7) Persons who believe they have suffered
property damage, bodily injury, or other
damages, or have incurred costs to clean up
petroleum contamination on their property
resulting from the operation of tanks on an
adjacent or nearby site, may not request payment directly from the fund. Such claims
must be made directly to the fund participant.
(8) Fund participants and beneficiaries who
desire reimbursement from the fund are
required to seek preapproval of cleanup costs
by following the procedures outlined below:
(A) Tank Removal—Prior to removal of a
petroleum storage tank or other activity
involving excavation of contaminated soil, a
fund participant or beneficiary must—
1. Obtain an adequate number of bids or
proposals from qualified contractors or consultants to demonstrate that a fair and reasonable price will be paid. The bids or cost estimates must include all tasks and services
which may be necessary and an anticipated
schedule for the tasks; and
2. Submit the bid(s) or proposal(s) to the
board, including:
A. A cost estimate for excavation and
hauling of contaminated soil, expressed as a
unit cost (e.g., per ton or per cubic yard);
B. A cost estimate for disposal or
treatment of contaminated soil;
C. A cost estimate for backfill,
expressed as a unit cost;
D. A cost estimate for removal, treatment, and/or disposal of contaminated water
which may be encountered during the excavation;
E. A cost estimate for project management, supervision, and reporting;
F. A cost estimate for collection
and/or analysis of soil and water samples;
G. A contingency cost estimate,
expressed as unit costs, for any additional
costs which may be incurred if field conditions warrant or necessitate more work than
anticipated; and
H. A cost estimate for any other
anticipated cleanup costs;
(B) Site Characterization—Prior to conducting a site characterization which is
required in response to a release, a fund participant or beneficiary must—
1. Obtain an adequate number of bids or
proposals from qualified contractors or consultants to demonstrate that a fair and reasonable price will be paid and submit the bid(s)
or proposal(s) to the board. The bids or cost
estimates must include:
A. A description of all tasks and services which may be necessary;
B. A site conceptual model;
C. Clearly-presented conclusions
regarding the current and reasonably anticipated future uses of potentially-impacted
properties;
D. The anticipated schedule of
events;
E. Estimated costs for all field activities, with drilling quoted on a per lineal foot
basis;
F. A cost estimate for laboratory analysis of soil and/or water samples, as appropriate;
G. A cost estimate for project management, oversight, data analysis, reporting,
and similar activities, as appropriate;
H. A contingency cost estimate,
expressed in unit costs, for additional costs
which may be incurred if field data indicates
the need for expanded field investigation; and
I. A cost estimate for any other anticipated costs associated with the site characterization;
(C) Risk Assessment.
1. Prior to preparing a risk assessment,
a fund participant or beneficiary must submit
one (1) or more cost estimate(s) to the board.
A. The cost estimate(s) must include
the anticipated schedule of events and/or
tasks.
B. The cost estimate(s) may be combined with a cost estimate for site characterization.
C. The cost estimate(s) may include
costs for both a Tier 1 and a Tier 2 risk
assessment.
D. The cost estimate(s) may include
costs for preparation of a corrective action
plan.
2. The board may require a fund participant or beneficiary to submit a cost estimate
for a Tier 2 or Tier 3 risk assessment.
(D) Corrective Action.
1. Prior to conducting corrective action
in response to a release, a fund participant or
beneficiary must obtain an adequate number
of bids or proposals, each of which must
include a schedule, from qualified contractors
or consultants to adequately compare costs of
alternatives for achieving the applicable corrective action standards. These proposals may
include:
A. Treatment, reduction of concentrations, removal, or remediation of chemicals
of concern;
B. Mitigation or elimination of complete exposure pathways;
C. Preventing future receptors; or
D. Any combination thereof.
2. Prior to conducting corrective action,
a fund participant or beneficiary must submit
the bid(s) or proposal(s) to the board.
3. When corrective action includes the
lease or purchase and installation of equipment designed to clean up petroleum contamination, the fund participant or beneficiary is
required to solicit competitive bids for such
equipment and provide such bids to the
board. A fund participant or beneficiary who
is paid salvage value for remediation equipment after corrective action is completed
shall report such to the board, which will
reduce its reimbursement for decommissioning and removal of said remediation equipment by that amount.
(E) The board will respond in writing to
bid(s) or cost estimate(s) submitted by fund
participants or beneficiaries, and will state
whether the bid(s) or cost estimate(s) are eligible, reasonable, and necessary. This response
will be based on information submitted for
each project, as well as information available
to the board from its review of other cost estimates and its processing of similar claims. To
the extent possible, the board’s response will
note which specific tasks, rates, or items are
deemed to be ineligible, unreasonable or
unnecessary, and will explain the reason for its
decision.
(F) If the bid(s) or cost estimate(s) submitted to the board are incomplete, or contain
costs which are higher than the board determines to be reasonable, the board may—
1. Agree to pay a lesser cost;
2. Ask the fund participant or beneficiary to solicit additional cost estimates; or
3. Ask the fund participant or beneficiary to demonstrate how the estimate was prepared.
(G) The board reserves the right to reject
any proposed costs or estimates if, in the
opinion of the board and at its sole discretion,
such costs are ineligible, unreasonable, or
Board of Trustees
unnecessary.
(9) The board will recognize eligible, reasonable, and necessary costs incurred for the following activities:
(A) Costs incurred to characterize the
extent of and assess risks posed by a release
from a petroleum storage tank; and
(B) Costs incurred for corrective actions
taken in accordance with state or federal regulations in response to a release from a
petroleum storage tank.
(10) Costs not associated with cleanup of a
release from a petroleum storage tank are not
eligible. Such costs include, but are not limited to:
(A) Costs of excavation solely necessary to
remove a petroleum storage tank;
(B) Costs of removal of tanks or piping,
cleaning of the tank, transportation and disposal of the tank and piping;
(C) Costs of demolition and removal of
buildings, canopies, dispensers, etc.;
(D) Costs of excavation, transport, treatment or disposal of soil which is not contaminated with petroleum at levels such that the
Department of Natural Resources requires
corrective action, except that—
1. The cost of removal of concrete or
similar surface material, overburden, or fill
material which is necessary to access contaminated soil for removal is eligible; and
2. Costs for transport and treatment or
disposal of backfill which surrounds underground tanks or piping, which is removed
during tank closure activities, and which is
contaminated at a level such that the Department of Natural Resources prohibits placement of the material back into the excavated
area, are eligible;
(E) Costs for environmental site assessments, or similar work, the purpose of which
is to determine whether a release has
occurred;
(F) Markup of costs charged by a treatment
or disposal facility which is used for disposition of contaminated soil;
(G) Markup of costs charged by a laboratory for analysis of water, soil, or vapor samples;
(H) Markup by the environmental consultant or contractor of major subcontracted
work, such as drilling, well installation, or
pushprobe investigation;
(I) Repairs and maintenance of tanks and
lines;
(J) Tank and line tightness tests;
(K) Preparation of claim submittals;
(L) Paving or resurfacing, except as
required as a result of necessary cleanup
activities. Claims for resurfacing shall be
paid on a depreciated basis, or on the basis of
the actual cash value of the surface which
existed immediately prior to the cleanup;
(M) Installation of new tanks, lines,
spill/overfill prevention devices, etc.; or
(N) Other costs excluded by the document
issued by the board to fund participants (see
10 CSR 100-4.010(5) and 10 CSR 1004.020(5)).
(11) The board shall have the authority to
investigate as needed in response to the submission of a notice of claim or invoices.
(A) The board shall have the right, but not
the obligation, to—
1. Make inspections of sites for which
the fund participant or beneficiary has given
notice of claim;
2. Request and review records concerning the operation of tanks at the site, maintenance of the tank system, site characterization, or corrective actions; or
3. Take recorded statements from tank
owners, operators, their employees, contractors, consultants, local officials, or other persons with pertinent knowledge or information
about a claim.
(B) Fund participants and beneficiaries
must provide copies of records and reports
which the board requests as part of its claim
investigation.
(C) Neither the fund participant or beneficiary nor the board shall waive any rights
expressed in Missouri law or the coverage
document issued by the board by virtue of the
participant or beneficiary submitting notice
of claim or invoices, or the board investigating the claim.
(12) When a fund participant or beneficiary
incurs costs for cleanup of petroleum contamination, he or she shall comply with the procedures set forth below to request reimbursement from the fund:
(A) Persons requesting reimbursement
from the fund must send invoices for the
work done, along with a copy of any reports
generated by consultants, contractors, or laboratories as part of the work, to the address
specified by the board.
1. Such invoices must be submitted
within two (2) years of the date the costs were
incurred. Failure to submit invoices within
that time frame shall waive the fund participant’s or beneficiary’s rights, and those of
their successors and assigns, to any benefits
which would have otherwise been paid by the
Petroleum Storage Tank Insurance Fund
Board of Trustees for such costs.
2. Original invoices are requested; if
photocopies are submitted, they must be
accompanied by a signed statement certifying
that the copies are true and accurate.
3. Invoices must match the general format of the previously-submitted cost estimate;
(B) If the person requesting reimbursement
is not the owner of the land where the work
is being or has been done, he or she must
submit either proof of payment or lien
waivers with the invoices;
(C) To the extent possible, invoices should
be accumulated and submitted as a batch
when a project, or phase of a project, is complete. In cases where the size of a project
would present a financial hardship, the fund
will make periodic reimbursements as the
project progresses;
(D) The board may, for the purposes of
standardizing claim submittals and assisting
persons in preparing such submittals, require
submission of a form along with invoices,
summarizing the costs for which reimbursement is being sought, identifying the purposes of such costs, and providing such other
information as may be needed to more efficiently process claims;
(E) The board will respond in writing to
every request for reimbursement. If the
response indicates some or all costs are being
disallowed or denied, the response will identify those costs and the reason for such disallowance or denial; and
(F) For claims made under subsection
(4)(A), the first reimbursement for eligible
costs will be reduced by the applicable
deductible. For claims made under subsections (4)(B), (C), (D), or (E), the first reimbursement for eligible costs will be reduced
by ten thousand dollars ($10,000).
AUTHORITY: sections 319.129 and 319.131,
RSMo 2016.* Original rule filed April 1,
1999, effective Nov. 30, 1999. Amended:
Filed March 31, 2000, effective Sept. 30,
2000. Amended: Filed Nov. 15, 2001, effective May 30, 2002. Amended: Filed Aug. 1,
2014, effective March 30, 2015. Amended:
Filed Feb. 15, 2018, effective Sept. 30, 2018.
*Original authority: 319.129, RSMo 1989, amended 1991,
1996, 1998, 2001, 2008 and 319.131, RSMo 1989, amended 1991, 1994, 1995, 1996, 1998, 1999, 2001, 2008.