1 CSR 30-3.040
Project Contracts and Work Completion
PURPOSE: This rule establishes the procedures for accomplishing the work on projects
under the supervision of the director of the
Division of Facilities Management, Design
and Construction.
(1) Project Supervision. The director is
responsible for supervision of work on all
projects with the exception of projects for
agencies that are exempt from this rule as set
forth below.
(A) Department/Agency/Site. The department/agency and personnel at the project site
are responsible for providing the contractor
with reasonable access to the project site,
available utility connections, and authorized
storage areas. These will be arranged to minimize interference between necessary operations at the facility and the project work.
Department/agency/site personnel shall:
1. Cooperate by exchanging information
and coordinating with the contractor, but
shall not assist the contractor with, or issue
instructions on, project work;
2. Cooperate with and assist, to the
extent possible, the director’s on-site representative and the designer in observing the
work, equipment, and materials on the site;
and
3. Report unusual occurrences or apparent problems to the director’s on-site representative at the earliest opportunity.
(B) Division of Facilities Management,
Design and Construction. For each project,
the director shall designate an on-site representative. The director’s on-site representative may be a division employee, a consultant, or a department/agency employee, as the
director deems appropriate for that project.
The director’s on-site representative is
responsible for supervision and administration of the project, including the following:
1. Issuing, in coordination with the
designer, official instructions to the contractor;
2. Providing coordination as necessary
with site personnel and verifying work or
materials included in payment estimates;
3. Assisting with coordinating and
scheduling the work and providing coordination between contractors working at the project site;
4. Performing or arranging for testing
when indicated by conditions or special
requirements;
5. Providing periodic reports and/or recommendations to the director;
6. Notifying the department/agency of
scheduled visits, meetings, and inspections;
and
7. Maintaining records of payments,
proposals, request for information, contract
changes, etc. having to do with the progress
of the work.
(C) Designer. The designer shall provide
construction administration as set forth in the
terms of the designer’s contract or, if the
designer is a state employee, as follows:
1. Provide on-site observation to assure
that the work is performed in accordance
with the contract documents;
2. Issue, in coordination with the director’s on-site representative, official instructions to the contractor and verify work or
materials included in payment estimates;
3. Assist the contractor in establishing
the sequence and control for the several phases and trades involved in the project work;
4. Provide expeditious review and
response for all submissions from the contractor and/or along with clarifications or
interpretations of the intent of the contract
documents;
5. Provide reports for all meetings called
to review the work or progress or to resolve
problems. Reports for periodic progress
meetings should include a review of work to
date, progress for the period, scheduled versus actual progress, and efforts to resolve differences between the schedule and actual
progress;
6. Provide recommendations for resolving problems of unusual occurrences or unanticipated requirements; and
7. Provide a complete set of reproducible, as-built drawings for the project.
(D) Contractor. The contractor shall be
responsible for providing all services set forth
in the contractor’s contract.
(E) Preconstruction Conference. The
director’s on-site representative shall call
together the contractor, the designer, a
department/agency representative, and other
interested parties for a conference at the site
prior to the start of work on the project. The
administrative procedures, coordination of
access, security, storage, utility connections,
areas of responsibilities, and the authority for
interpretations and/or issuance of instructions
will be reviewed to assure understanding by
all parties. The director’s on-site representative will provide instructions for any requirements or conditions requiring special attention.
(F) Construction Progress Meetings. The
director’s on-site representative shall periodically call together the designer and the contractor to review progress of the work in addition to the review and verification of payment
requests. Schedule versus actual progress will
be examined. When actual progress has fallen behind scheduled progress, adjustments in
work force, materials, equipment, or other
factors, as appropriate, should be established
at the progress meeting to assure completion
within the time allowed.
(G) Contract Changes. Changes in the
work shall be approved only when the director determines that it would be detrimental to
bid the work separately. If possible, pricing
for contract changes will be determined from
unit prices stated in, or derived from, the
contractor’s original bid proposal. Contract
changes shall not be used to expand the scope
of work beyond the intent of the appropriation. Contract changes will be submitted in
such form as may be established by the director, and the proposed work shall not proceed
until approved by the director or his/her
designee. The designer will coordinate proposed changes with the director’s on-site representative and the department/agency and
then prepare the contract change, including
appropriate drawings and specifications.
After review and approval of the contractor’s
proposal, the designer shall furnish the contract change and proposal to the director’s onsite representative. Submission and approval
of an encumbrance in the amount of the contract change should proceed concurrently
with approval and signature for the contract
change. Notice to proceed with work under a
contract change will be issued only after confirmation of available funding.
1. Pre-final inspection. When the contractor notifies the director’s on-site representative that the contractor has substantially
completed the work, the on-site representative, with the designer and contractor, shall
review this list, examine the work, and note
any exceptions or additional items to be corrected or completed. After review of the
items to be corrected and completed and considering the time necessary to accomplish
these, a time and date will be set for final
inspection.
2. Final inspection. Final inspection is an
examination of the completed project, with
particular emphasis on the items for correction
and completion established in the pre-final
Design and Construction
inspection. Representatives of the department/agency will be invited to participate in
the final inspection along with the director’s
on-site representative, the designer, and contractor. Any items remaining for correction
and completion shall be noted and the contractor given a specific time to accomplish
these items. Items of testing and adjustment
that are incomplete due to seasonal requirements will be scheduled for completion in the
appropriate season. Final acceptance may be
made after completion of all items except for
testing or adjusting seasonal equipment.
3. Warranty period. All equipment,
materials, and work should be guaranteed or
warranted for at least one (1) year after final
acceptance, unless otherwise approved by the
director. During the warranty period the
facility operator shall inform the contractor of
all deficiencies encountered needing correction. If not corrected within a reasonable
period of time, the director’s on-site representative shall be notified.
4. Warranty inspection. During the tenth
or eleventh month following completion, the
designer shall schedule a meeting at the project site with the contractor, a representative
of the department/agency/site, and a representative of the director. Performance of
items under guaranty or warranty will be
examined to assure that the contractor is providing satisfactory service. Deficiencies shall
be noted and the contractor given a specific
time for correction. Payment/performance
bonds shall not be released until after the
warranty inspection and correction of noted
deficiencies. This warranty inspection shall
not be construed to limit or relieve any contractual responsibility of the contractor to
provide call-back or other service or correction of deficiencies during the warranty period for the equipment, materials, or work on
the project.
(2) Exemptions. There are specific exemptions from requirements of this rule provided
by the Missouri Constitution or by the
Revised Statutes of Missouri.
(A) Department of Transportation projects
and expenditures for highway construction
and highway mainte nance are exempted from
provisions of this rule by Article IV, Section
29, Missouri Constitution of 1945.
(B) Institutions of higher learning, community junior colleges, and the Department of
Conservation are exempted by section 8.310,
RSMo from provisions of this rule which
require coordination with or approval by the
commissioner of administration, Division of
Facilities
Management,
Design
and
Construction, or both, for soliciting and
receipt of proposals, award of and payments
for contracts and contract supervision.
AUTHORITY: sections 8.310 and 8.320,
RSMo 2016 and subsections 6 and 7 of section 15, 1974 Reorganization Act.* Original
rule filed July 9, 1981, effective Feb. 15,
1982. Emergency amendment filed June 14,
1985, effective July 1, 1985, expired Oct. 29,
1985. Amended: Filed June 14, 1985, effective Aug. 26, 1985. Amended: Filed Nov. 30,
1993, effective July 10, 1994. Rescinded and
readopted: Filed Nov. 5, 2007, effective June
30, 2008. Amended: Filed Oct. 11, 2018,
effective May 30, 2019.
*Original authority: 8.310, RSMo 1958, amended 1965,
1984, 1987, 1995 and 8.320, RSMo 1958, amended 1965.