10 CSR 40-3.120
Revegetation Requirements
PURPOSE: This rule sets forth revegetation
requirements pursuant to sections 444.810
and 444.855.2(19) and (20), RSMo.
Editor’s Note: The secretary of state has
determined that the publication of this rule in
its entirety would be unduly cumbersome or
expensive. The entire text of the material referenced has been filed with the secretary of
state. This material may be found at the
Office of the Secretary of State or at the headquarters of the agency and is available to any
interested person at a cost established by
state law.
(1) General Requirements.
(A) The permittee shall establish on
regraded areas and on all other disturbed
areas, except water areas and surface areas of
roads that are approved as part of the postmining land use, a vegetative cover that is in
accordance with the approved permit and
reclamation plan and that is to be—
1. Diverse, effective and permanent;
2. Comprised of species native to the
area, or of introduced species where allowable under section (2) of this rule, and necessary to achieve the approved postmining land
use and approved by the regulatory authority;
3. At least equal in extent of cover to the
natural vegetation of the area; and
4. Capable of stabilizing the soil surface
from erosion.
(B) The reestablished plant species shall—
1. Be compatible with the approved
postmining land use;
2. Have the same seasonal characteristics of growth as the original vegetation;
3. Be capable of self-regeneration and
plant succession;
4. Be compatible with the plant and animal species of the area; and
5. Meet the requirements of applicable
state and federal seed, poisonous and noxious
plant and introduced species laws or regulations.
(C) For areas designated as prime farmland, the requirements of 10 CSR 40-4.030
shall apply.
(D) The regulatory authority may grant
exception to the requirements of paragraphs
(1)(B)2. and 3. of this rule when the species
are necessary to achieve a quick-growing,
temporary, stabilizing cover and measures to
establish permanent vegetation are included
in the approved permit and reclamation plan.
(E) When the regulatory authority
approves a cropland or prime farmland postmining land use, the regulatory authority may
grant exception to the requirements of paragraphs (1)(A)1. and 3., and (1)(B)2. and 3.
of this rule.
(2) Use of Introduced Species. Introduced
species may be substituted for native species
only if approved in the permit and plan under
the following conditions:
(A) After appropriate field trials have
demonstrated that the introduced species are
desirable and necessary to achieve the
approved postmining land use;
(B) The species are necessary to achieve a
quick, temporary and stabilizing cover that
aids in controlling erosion; and measures to
establish permanent vegetation are included
in the approved plan submitted under 10 CSR
40-6.050(8)(B)3. and 10 CSR 40-6.050(10);
(C) The species are compatible with the
plant and animal species of the region; and
(D) The species meet the requirements of
applicable state and federal seed or introduced species statutes and are not poisonous
or noxious.
(3) Timing. Seeding and planting of disturbed
areas shall be conducted during the first normal period for favorable planting conditions
after final preparation. The normal period for
favorable planting shall be that planting time
generally accepted locally for the type of
plant materials selected. When necessary to
effectively control erosion, any disturbed
area shall be seeded and planted, as contemporaneously as practicable with the completion of backfilling and grading, with a temporary cover of small grains, grasses or legumes
until a permanent cover is established.
(4) Mulching and Other Soil Stabilizing
Practices.
(A) Suitable mulch and other soil stabilizing practices shall be used on all regraded
and topsoiled areas to control erosion, promote germination of seeds or increase the
moisture-retention capacity of the soil. The
commission or director, on a case-by-case
basis, may suspend the requirement for
mulch, if the permittee can demonstrate that
alternative procedures will achieve the
requirements of section (6) of this rule and do
not cause or contribute to air or water pollution.
(B) When required in the permit and plan,
mulches shall be mechanically or chemically
anchored to the soil surface to assure effective protection of the soil and vegetation.
(C) Annual grasses and grains may be used
alone as in situ mulch, or in conjunction with
another mulch, when the commission or
Surface Coal Mining and Related Activities
director determines that they will provide
adequate soil erosion control and will later be
replaced by perennial species approved for
the postmining land use.
(D) Chemical soil stabilizers alone, or in
combination with appropriate mulches, may
be used in conjunction with vegetative covers
approved for the postmining land use.
(5) Grazing. When the approved postmining
land use is pasture, the reclaimed land may
be used for livestock grazing at a grazing
capacity approved in the permit and plan
approximately equal to that for similar nonmined lands, for at least the last two (2) full
years of liability required under subsection
(6)(B) of this rule or may be used in another
manner, as approved, which will determine
the productive capacity approved in the permit and plan approximately equal to that for
similar nonmined lands.
(6) Standards for Success.
(A) Success of revegetation shall be measured by statistically valid techniques and in
accordance with guidelines established by the
director and referenced under paragraph
(6)(B)2. of this rule. Comparison of ground
cover and productivity may be made on the
basis of reference areas or criteria representative of unmined lands in the area being
reclaimed or through the use of technical
guidance procedures published by the United
States Department of Agriculture (USDA) or
United States Department of Interior (USDI)
for assessing ground cover and productivity.
Management of the reference area, if applicable, shall be comparable to that which is
required for the approved postmining land
use of the permit area.
(B) General Requirements.
1. Ground cover and productivity of living plants on the revegetated area within the
permit area shall be equal to the ground cover
and productivity of living plants on the
approved reference area or to the standards in
other technical guides approved by the commission for use in the regulatory program.
The period of extended responsibility initiates
after the last year of augmented seeding, fertilizing, irrigation or other work which
ensures success and continues for not fewer
than five (5) years.
2. Specific standards for postmining
land uses—
A. For areas to be used as woodland,
success in revegetation shall be determined
on the basis of ground cover and tree and
shrub count. Ground cover and tree and
shrub stocking shall be considered acceptable
if they are equal to ninety percent (90%) of
the approved success standard at a ninety percent (90%) statistical confidence level for the
last year of the five (5)-year responsibility
period. The success standard for ground
cover is a ground cover density of seventy
percent (70%). The success standard for tree
and shrub stocking rate shall be determined
on a specific permit basis with consultation
and approval of the Missouri Department of
Conservation. Measurements for ground
cover and productivity of living plants shall
be performed in accordance with the criteria
contained in the current guidelines of the
Land Reclamation Commission entitled
“Phase III Revegetation Success Standards
for Woodland”;
B. In areas to be developed for industrial/commercial land use fewer than two (2)
years after regrading is completed, the vegetative ground cover shall not be less than
required to control erosion. If the area is not
developed for industrial/commercial use
within two (2) years of regrading, ground
cover must have a density of seventy percent
(70%), at a ninety percent (90%) statistical
confidence level and not be less than that
required to control erosion. Measurements
for ground cover shall be performed in accordance with the criteria contained in the current guidelines of the Land Reclamation
Commission entitled “Phase III Success
Standards
for
Industrial/Commercial
Revegetation”;
C. For areas to be used for cropland
unless otherwise approved in the permit and
plan, success in revegetation of cropland shall
be determined on the basis of crop production
from the mined area as compared to approved
reference areas or other technical guidance
procedures. Crop production from the mined
area shall be equal to or greater than that of
the approved standard for any two (2) years,
except the first year, of the five (5)-year liability period established in paragraph
(6)(B)1. of this rule. Production shall not be
considered equal if it is less than ninety percent (90%) of the production of the approved
standard with ninety percent (90%) statistical
confidence. Measurements for crop productivity shall be performed in accordance with
the criteria contained in the current guidelines of the Land Reclamation Commission
entitled “Phase III Revegetation Success
Standards for Cropland”;
D. On areas to be developed for
wildlife habitat, success of vegetation shall be
determined on the basis of tree, shrub or halfshrub stocking and ground cover. The tree,
shrub or half-shrub stocking shall meet the
standards described in section (7) of this rule.
Ground cover shall be considered acceptable
if it has at least seventy percent (70%) density
with ninety percent (90%) statistical confidence. The success standard for tree and
shrub stocking rate shall be determined on a
specific permit basis with consultation and
approval of the Missouri Department of
Conservation. Measurements for ground
cover and stocking shall be performed in
accordance with the criteria contained in the
current guidelines of the Land Reclamation
Commission entitled “Phase III Revegetation
Success Standards for Wildlife Habitat”;
E. For areas to be developed for pasture use, success of revegetation shall be
determined on the basis of ground cover and
the production of living plants. Ground cover
and production shall be considered acceptable if they are at least ninety percent (90%)
of the approved success standard at a ninety
percent (90%) statistical confidence level for
any two (2) years of the five (5)-year responsibility period, except the first year. The success standard for ground cover shall be ninety
percent (90%) density. The success standard
for hay production shall be the yield from the
reference area. Measurements for ground
cover and productivity of living plants shall
be performed in accordance with the criteria
contained in the current guidelines of the
Land Reclamation Commission entitled
“Phase III Revegetation Success Standards
for Pasture and Previously Mined Areas”;
F. For areas to be developed for prime
farmland use, success of revegetation shall be
determined on the basis of crop production.
Crop production shall be considered acceptable if it is one hundred percent (100%) of
the approved success standard at a ninety percent (90%) statistical confidence level for any
three (3) years of the five (5)-year responsibility period, except the first year. The success standard for crop production shall be the
yield from the reference area or other technical guidance procedures. Measurement of
soil productivity shall be initiated within ten
(10) years after completion of soil replacement. Measurements for crop productivity
shall be performed in accordance with the
criteria contained in 10 CSR 40-4.030 and in
the
current
guidelines
of
the
Land
Reclamation Commission entitled “Phases
II/III Revegetation Success Standards For
Prime Farmland”;
G. For areas to be developed for a
recreation land use, success of revegetation
shall be determined on the basis of ground
cover and tree and shrub stocking. Ground
cover shall be considered acceptable if it is
equal to a density of seventy percent (70%),
at a ninety percent (90%) statistical confidence level. The success standard for tree and
shrub stocking rate shall be determined on a
specific permit basis with consultation and
approval of the Missouri Department of
Conservation. Measurements for ground
cover and productivity of living plants shall
be performed in accordance with the criteria
contained in the current guidelines of the
Land Reclamation Commission entitled
“Phase III Revegetation Success Standards
For a Recreation Land Use”;
H. For areas to be developed for residential use fewer than two (2) years after
regrading is completed, the vegetative ground
cover density shall not be less than required
to control erosion. If the area is not developed for residential use within two (2) years
of regrading, ground cover must be equal to
a density of seventy percent (70%), at a ninety percent (90%) statistical confidence level.
Measurements for ground cover density shall
be performed in accordance with the criteria
contained in the current guidelines of the
Land Reclamation Commission entitled
“Program Phase III Revegetation Standards
For Residential Land Use”; and
I. For areas previously disturbed by
mining that were not reclaimed to the requirements of subsection (6)(B) and that are remined or otherwise redisturbed by surface
coal mining operations, as a minimum, the
vegetative ground cover shall be not less than
the ground cover existing before redisturbance and shall be adequate to control erosion.
3. Vegetative ground cover shall not be
less than that required to achieve the
approved postmining land use.
(C) The person who conducts surface mining activities shall—
1. Maintain any necessary fences and
proper management practices; and
2. Conduct periodic measurements of
vegetation, soils and water prescribed or
approved in the permit and plan to identify
conditions during the applicable period of liability specified in subsection (6)(B) of this
rule.
(D) For permit areas forty (40) acres or
less in size in locations with an average annual precipitation of more than twenty-six inches (26"), the following performance standards, if approved in the permit and plan,
may be used instead of reference areas to
measure success of revegetation on sites that
are disturbed. These standards shall be met
for a minimum of five (5) consecutive years:
1. Areas planted only in herbaceous
species shall sustain a vegetative ground
cover of seventy percent (70%) for five (5)
full consecutive years;
2. Areas planted with a mixture of
herbaceous and woody species shall sustain a
herbaceous vegetative ground cover of seventy percent (70%) for five (5) full consecutive
years and four hundred (400) woody plants
per acre after five (5) years. On steep slopes,
the minimum number of woody plants shall
be six hundred (600) per acre; and
3. For purposes of this section, herbaceous species means grasses, legumes and
nonleguminous forbs; woody plants means
woody shrubs, trees and vines; and ground
cover means the area of ground covered by
the combined aerial parts of vegetation and
the litter that is produced naturally on-site,
expressed as a percentage of the total area of
measurement.
(7) Tree and Shrub Stocking for Woodland,
Wildlife Habitat and Recreation Land Uses.
This section sets forth forest resource conservation standards for reforestation operations
to ensure that a cover of commercial tree
species, noncommercial tree species, shrubs
or half-shrubs, sufficient for adequate use of
the available growing space, is established
after surface mining activities.
(A) Stocking, that is, the number of stems
per unit area, will be used to determine the
degree to which space is occupied by welldistributed, countable trees, shrubs or halfshrubs.
1. Root crown or root sprouts over one
foot (1') in height shall count as one (1)
toward meeting the stocking requirements.
Where multiple stems occur, only the tallest
stem will be counted.
2. A countable tree or shrub means a
tree that can be used in calculating the degree
of stocking under the following criteria:
A. The tree or shrub shall be in place
at least two (2) growing seasons;
B. The tree or shrub shall be alive and
healthy; and
C. The tree or shrub shall have at
least one-third (1/3) of its length in live
crown.
3. Rock areas, permanent road and surface water drainage ways on the revegetated
area shall not require stocking.
(B) The following are the minimum performance standards for areas where woodland is
the approved postmining land use:
1. The area shall have a minimum stocking of four hundred fifty (450) trees or shrubs
per acre;
2. A minimum of seventy-five percent
(75%) of countable trees or shrubs shall be
commercial tree species;
3. The number of trees or shrubs and the
ground cover shall be determined using
procedures
described
in
subparagraph
(6)(B)2.D. and subsection (7)(A) of this rule
and the sampling method approved in the permit and plan; when the stocking is equal to or
greater than four hundred fifty (>450) trees
or shrubs per acre and there is acceptable
ground cover, the five (5)-year responsibility
period required in subparagraph (6)(B)2.D.
and paragraph (7)(C)2. of this rule shall
begin; and
4. Upon expiration of the five (5)-year
responsibility period and at the time of
request for bond release, each permittee shall
provide documentation showing that the
stocking of trees and shrubs and the ground
cover on the revegetated area is satisfied by
the provisions set out in subparagraph
(6)(B)2.D. and paragraph (7)(B)1. of this
rule.
(C) The following are the minimum performance standards for areas where woody
plants are used for wildlife management,
recreation, shelter belts or forest uses other
than commercial forest land:
1. An inventory of trees, half-shrubs and
shrubs shall be conducted on established reference areas according to methods approved
in the permit and plan. This inventory shall
contain, but not be limited to—
A. Site quality;
B. Stand size;
C. Stand condition;
D. Site and species relations; and
E. Appropriate forest land utilization
considerations;
2. The stocking of trees, shrubs, halfshrubs and the ground cover established on
the revegetated area shall approximate the
stocking and ground cover approved in the
permit. Minimum stocking and planting
arrangements shall be based on local and
regional conditions after consultation with
and approval from the Missouri Department
of Conservation. The stocking of live woody
plants shall be equal to or greater than ninety
percent (90%) of the stocking of woody
plants of the same life form approved in the
permit. When this requirement is met and
acceptable ground cover is achieved, the five
(5)-year responsibility period required in subsection (6)(B) of this rule shall begin; and
3. Upon expiration of the five (5)-year
responsibility period, each permittee shall
provide documentation showing that—
A. The woody plants established on
the revegetated site are equal to or greater
than ninety percent (90%) of the stocking rate
approved in the permit with ninety percent
(90%) statistical confidence and, at the time
of final bond release, at least eighty percent
(80%) of the trees and shrubs used to determine success shall have been in place for
sixty percent (60%) of the applicable minimum period of responsibility;
B. The ground cover on the revegetated area satisfies subparagraph (6)(B)2.D. of
this rule. Species diversity, seasonal variety
and regenerative capacity of the vegetation of
Surface Coal Mining and Related Activities
the revegetated area shall be evaluated on the
basis of the results which could reasonably be
expected using the revegetation methods
described in the mining and reclamation plan;
and
C. Vegetative ground cover shall not
be less than that required to achieve the
approved postmining land use.
(8) Reclamation Schedule.
(A) In addition to the temporal and spatial
requirements for completion of grading specified in 10 CSR 40-3.110(1)(A), other
aspects of reclamation shall be completed in
a timely manner as follows:
1. Replacement of topsoil shall be completed within two hundred seventy (270) days
of the completion of backfilling and rough
grading or as contemporaneously as possible
as defined in the approved permit;
2. A permanent cover sufficient to control erosion, or an equivalent erosion control
practice, as approved by the director, shall be
in place within two (2) years of the completion of initial seeding;
3. Within four (4) years of the completion of initial seeding—
A. Reclaimed land shall qualify for a
Phase II liability release; and
B. The permittee shall submit a
request for release of Phase II liability;
4. Siltation structures and diversions
that are no longer needed for control of sediment shall be graded, topsoiled and seeded
within eighteen (18) months after approval of
a Phase II liability release of all disturbed
areas within the watershed they serve. These
Siltation structures and diversions shall be
clearly indicated by the director in the Phase
II liability release inspection report;
5. Revegetation success on indus -
trial/commercial areas, public service areas,
recreation areas and residential areas shall be
demonstrated in the last year of the five (5)-
year responsibility period;
6. Revegetation success on woodland
areas and wildlife areas shall be demonstrated in the last year of the five (5)-year responsibility period;
7. Revegetation success on cropland and
pasture shall be demonstrated in any two (2)
years of the last four (4) years of the five (5)-
year responsibility period;
8. Revegetation success on prime farmland shall be demonstrated in any three (3)
years of the last four (4) years of the five (5)-
year responsibility period;
9. Measurements of ground cover, productivity and tree and shrub density shall be
submitted to the commission within thirty
(30) days of data collection for the years the
permittee uses to prove revegetation success.
If a permittee is unable to demonstrate revegetation success at the end of the five (5)-year
responsibility period, the responsibility period and the requirement to measure productivity shall be extended year-by-year until the
revegetation success standards are met; and
10. Within six (6) months after revegetation success is demonstrated for a given
area—
A. All requirements of 10 CSR 407.021(2)(D) shall be met; and
B. The permittee shall submit a
request for release of Phase III liability to the
commission.
(B) The requirements of subsection (8)(A)
shall not apply to areas that are used and
needed specifically for the support of ongoing
reclamation or mining activities and on which
grading, topsoiling, or both cannot be completed until the areas are no longer needed for
the support of ongoing reclamation or mining
activities. The areas shall include, but shall
not be limited to, haul roads, siltation structures, diversions and stockpiles. The requirements of subsection (8)(A) shall apply to
these areas when they are no longer needed
for support activities.
(C) The director may approve variances
from the requirements of paragraphs
(8)(A)1.—8. if—
1. The permittee can demonstrate that
unusual circumstances which are beyond
his/her control have made him/her temporarily unable to conform to the requirements;
2. The variance is requested for the purpose of improving the efficiency of the management of the reclaimed land, and the director determines that the variance will not
unreasonably delay reclamation and the
release of Phase III liability; or
3. The variance is requested for the purpose of allowing the permittee to perform
reclamation that significantly exceeds the
requirements of the law.
(D) The permittee shall report to the director the status of reclamation on all of his/her
operations as of January 1 of each year. The
report shall contain a narrative and map outlining the following as a minimum:
1. Total acres disturbed by mining (that
is, spoil banks, open pit, bench);
2. Total acres disturbed to assist mining
(that is, siltation structures, diversions, haul
roads, topsoil stockpiles);
3. Acres finished graded (that is, all
grading complete);
4. Acres not yet finished graded (that is,
pit, bench, adjacent four (4) or fewer spoils);
5. Acres finished topsoiled (that is, topsoil completed and most likely seeded);
6. Acres not yet topsoiled;
7. Acres seeded (that is, permanent
seeding of grass-legume and cover crop) and
a description of the species planted and the
methods used;
8. Acres permanent impoundments (that
is, siltation structures and final pits);
9. Acres permanent roads;
10. Acres fully reclaimed (that is, reclamation completed; however, future touchup
and overseeding may be necessary to ensure
bond release status); and
11. Additional acres disturbed to support mining (that is, preparation plants, office
and shop areas, slurry ponds, coal storage
piles).
AUTHORITY: sections 444.530 and 444.810,
RSMo Supp. 1999.* Original rule filed Oct.
12, 1979, effective Feb. 11, 1980. Amended:
Filed April 14, 1980, effective Aug. 11, 1980.
Amended: Filed Dec. 10, 1980, effective
April 11, 1981. Amended: Filed Dec. 9, 1982,
effective April 11, 1983. Amended: Filed June
27, 1986, effective Oct. 27, 1986. Amended:
Filed Aug. 14, 1986, effective Feb. 28, 1987.
Amended: Filed Dec. 15, 1987, effective
April 1, 1988. Amended: Filed Sept. 15,
1988, effective Jan. 15, 1989. Amended:
Filed Jan. 4, 1989, effective April 1, 1989.
Amended: Filed July 3, 1990, effective Nov.
30, 1990. Amended: Filed May 15, 1992,
effective Jan. 15, 1993. Amended: Filed Sept.
29, 1995, effective March 30, 1996.
Amended: Filed March 21, 2000, effective
Oct. 30, 2000.
*Original authority: 444.530, RSMo 1971, amended 1983,
1990, 1993, 1995 and 444.810, RSMo 1979, amended
1983, 1993, 1995.