10 CSR 40-3.140
Road and Other Transportation Requirements
PURPOSE: This rule sets forth road and
other transportation requirements pursuant to
section 444.810, RSMo.
PUBLISHER’S NOTE: The publication of the
full text of the material that the adopting
agency has incorporated by reference in this
rule would be unduly cumbersome or expensive. Therefore, the full text of that material
will be made available to any interested person at both the Office of the Secretary of State
and the office of the adopting agency, pursuant to section 536.031.4, RSMo. Such
material will be provided at the cost established by state law.
(1) Roads—Class I—General.
(A) Each person who conducts surface
mining activities shall locate, design, construct or reconstruct, utilize and maintain
Class I roads and reclaim the area to meet the
requirements of sections (2)–(7) of this rule
and to control or prevent erosion; siltation;
the air pollution attendant to erosion, including road dust as well as dust occurring on
other exposed surfaces, by measures such as
vegetating, watering, using chemical or other
dust suppressants, or otherwise stabilizing all
exposed surfaces in accordance with current,
prudent engineering practices; and water pollution and damage to public or private property.
(B) To the extent possible using the best
technology currently available, Class I roads
shall not cause damage to fish, wildlife and
related environmental values and shall not
cause additional contributions of suspended
solids to streamflow or to runoff outside the
permit area. These contributions shall not be
in excess of limitations of state or federal law.
(C) All Class I roads shall be removed and
the land affected regraded and revegetated in
accordance with the requirements of section
(7) of this rule unless—
1. Retention of the road is approved as
part of the approved postmining land use or
as being necessary to adequately control erosion;
2. The necessary maintenance is
assured; and
3. All drainage is controlled according
to section (4) of this rule.
(D) Class I Roads General Design.
1. The design and construction or reconstruction of Class I and II roads shall be certified by a qualified registered professional
engineer in accordance with sections (2)–(7)
of this rule. Construction or reconstruction of
Class I roads must be certified in a report to
the director. The report shall indicate that the
Class I road has been constructed or reconstructed as designed and in accordance with
the approved plan.
2. The design shall incorporate the
demand for mobility and travel efficiency
based on geometric criteria both horizontal
and vertical, appropriate for the anticipated
volume of traffic and weight and speed of
vehicles to be used.
(2) Roads—Class I—Location.
(A) Class I roads shall be located, insofar
as possible, on ridges or on the most stable
available slopes to minimize erosion.
(B) No part of any Class I road shall be
located in the channel of an intermittent or
perennial stream unless specifically approved
in the permit and plan.
(C) Stream fords are prohibited unless they
are specifically approved in the permit and
plan as temporary routes during periods of
construction. The fords shall not adversely
affect stream sedimentation or fish, wildlife
and related environmental values. All other
stream crossings shall be made using bridges,
culverts or other structures designed, constructed and maintained to meet the requirements of section (4) of this rule.
(D) Class I roads shall be located to minimize downstream sedimentation and flooding.
(3) Roads—Class I—Design and Construc -
tion. Class I roads shall be designed and constructed or reconstructed in compliance with
the following standards in order to control
subsequent erosion and disturbance of the
hydrological balance:
(A) Vertical Alinement. Except where lesser grades are necessary to control site-specific conditions, maximum road grades shall be
as follows:
1. The overall grade shall not exceed
1v:10h (10%);
2. The maximum pitch grade shall not
exceed 1v:6.5h (15%); and
3. There shall be not more than three
hundred feet (300') of pitch grade exceeding
ten percent (10%) within any consecutive one
thousand feet (1000') of Class I roads, but in
no case shall there be any pitch grade over
fifteen percent (15%);
(B) Horizontal Alinement. Class I roads
shall have horizontal alinement as consistent
with the existing topography as possible and
shall provide the alinement required to meet
the performance standards of sections (1)–(7)
of this rule. The alinement shall be determined
in accordance with the anticipated volume of
traffic, and weight and speed of vehicles to be
used. Horizontal and vertical alinement shall
Surface Coal Mining and Related Activities
be coordinated to ensure that one will not
adversely affect the other and to ensure that
the road will not cause environmental damage;
(C) Road Cuts.
1. Cut slopes shall not be steeper than
specifically authorized in the permit and plan
which shall not authorize slopes steeper than
1v:1.5h in unconsolidated materials or
1v:0.25h in rock, except that steeper slopes
may be specifically authorized in the permit
and plan if geotechnical analysis demonstrates that a minimum safety factor of one
and five-tenths (1.5) can be maintained.
2. Topsoil or other materials suitable
under 10 CSR 40-3.030(2) shall be placed on
all cut slopes of 1v:1.5h or flatter to aid in
establishing vegetation and to minimize erosion. Topsoil depth shall be adequate to support vegetation necessary to control erosion.
3. Temporary erosion-control measures
shall be implemented during construction to
minimize sedimentation and erosion until
permanent control measures can be established;
(D) Road Embankments. Embankment
sections shall be constructed in accordance
with the following provisions:
1. All vegetative material and topsoil
shall be removed from the embankment foundation during construction to increase stability and no vegetative material or topsoil shall
be placed beneath or in any Class I road
embankment;
2. Where an embankment is to be placed
on side slopes exceeding 1v:5h (20%), the
existing ground shall be plowed, stepped or;
if in bedrock, keyed in a manner which
increases the stability of the fill. The keyway
shall be a minimum of ten feet (10') in width
and shall extend a minimum of two feet (2')
below the toe of the fill;
3. Material containing by volume less
than twenty-five percent (25%) of rock larger
than six inches (6") in greatest dimension
shall be spread in successive uniform layers
not exceeding twelve inches (12") in thickness before compaction;
4. Where the material for an embankment consists of large size rock, broken stone
or fragmented material that makes placing it
in twelve-inch (12") layers impossible under
paragraph (3)(D)3. of this rule, the embankment shall be constructed in uniform layers
not exceeding in thickness the approximate
average size of the rock used, but the layers
shall not exceed thirty-six inches (36") in
thickness. Rocks shall not be dumped in final
position but shall be distributed by blading or
dozing in a manner that will ensure proper
placement in the embankment, so that voids,
pockets and bridging will be reduced to a
minimum. The final layer of the embankment
shall meet the requirements of paragraph
(3)(D)3. of this rule;
5. Each layer of the embankment shall
be completed, leveled and compacted before
the succeeding layer is placed. Loads of
material shall be leveled as placed and kept
smooth. The successive layers shall be evenly
compacted by routing the hauling and leveling equipment over the entire width of the
embankment. This procedure shall be continued until no visible horizontal movement of
the embankment material is apparent;
6. Embankment layers shall be compacted as necessary to ensure that the embankment is adequate to support the anticipated
volume of traffic and weight and speed of
vehicles to be used. In selecting the method
to be used for placing embankment material,
consideration shall be given in the design to
factors such as the foundation, geological
structure, soils, type of construction and
equipment to be used. A structural and foundational analysis shall be performed to establish design standards for embankment stability appropriate to the site. Publications of the
American Association of State Highway and
Transportation Officers (AASHTO) including
AASHTO T-99, T-180, T-191 and the modified AASHTO test or other specifications
generally recognized by transportation engineers as adequate for design of highway
embankments, shall be used to determine the
degree of compaction required, on the basis
of soil type and the anticipated volume of
traffic and weight and speed of vehicles to be
used and are incorporated in this rule by reference. Compaction effort shall be adequate
to achieve the degree of compaction required.
No lift shall be placed on a layer until the
design density is achieved throughout the
layer. AASHTO specifications such as T-99,
T-180, the modified AASHTO test or other
comparable specifications approved in the
permit and plan shall be used as guidelines
for the determination of the maximum dry
density for granular materials;
7. Material shall be placed in an
embankment only when its moisture content
is within acceptable levels to achieve design
compaction;
8. Embankment slopes shall not be
steeper than 1v:2h, except that where the
embankment material is a minimum of
eighty-five percent (85%) rock, slopes shall
not be steeper than 1v:1.35h if it has been
demonstrated that embankment stability will
result. Where rock embankments are constructed, they shall meet the requirements of
paragraph (3)(D)4. of this rule;
9. The minimum safety factor for all
embankments shall be one and three-tenths
(1.3) or a higher factor as the permit and plan
may specify;
10. The road surface shall be sloped
toward the ditch line at a minimum rate of
one-quarter inch (1/4") per foot of surface
width or crowned at a minimum rate of width
as measured from the centerline of the road;
11. All material used in embankments
shall be suitable for use under paragraphs
(3)(D)1.–8. of this rule. The material shall be
reasonably free of organic material, coal or
coal blossom, frozen materials, wet or peat
material, natural soils containing organic
matter or any other material considered
unsuitable in the permit and plan for use in
embankment construction;
12. Excess or unsuitable material from
excavations, as defined in paragraph
(3)(D)11. of this rule, shall be disposed of in
accordance with 10 CSR 40-3.060(1). Acidand toxic-forming material shall be disposed
of in accordance with 10 CSR 40-3.040(8),
10 CSR 40-3.080(1) and 10 CSR 403.110(3);
13. Acid-producing materials shall be
permitted for constructing embankments for
only those Class I roads constructed or reconstructed on coal processing waste banks and
only if it has been demonstrated that no additional acid will leave the confines of the coal
processing waste bank. In no case shall acidbearing refuse material be used outside the
confines of the coal processing waste bank.
Restoration of the road shall be in accordance
with the requirements of 10 CSR 403.110(3)–(6) and 10 CSR 40-3.120(1)–(7);
14. Topsoil or other material suitable
under 10 CSR 40-3.030(2) shall be placed on
all embankment slopes of 1v:1.5h or flatter
to aid in establishing vegetation and to minimize erosion. Topsoil material depth shall be
adequate to support vegetation and to prevent
erosion; and
15. Temporary erosion-control measures
shall be incorporated during construction to
control sedimentation and minimize erosion
until permanent control measures can be
established; and
(E) Topsoil Removal. Before initiation of
construction or reconstruction of a Class I
road, topsoil and other materials, as determined under 10 CSR 40-3.030(2), shall be
removed from the design roadbed, shoulders
and surfaces where associated structures will
be placed and shall be stored in accordance
with 10 CSR 40-3.030(3).
(4) Roads—Class I—Drainage.
(A) General.
1. Each Class I road shall be designed,
constructed or reconstructed and maintained
to have adequate drainage, using structures
such as, but not limited to, ditches, cross
drains and ditch relief drains. The water control system shall be designed to safely pass
the peak runoff from a ten (10)-year, (24)-
hour precipitation event or a greater event if
required in the permit and plan.
2. Sediment control shall comply with
10 CSR 40-3.040(2) and (5).
3. Vegetation shall not be cleared for
more than the width necessary for road and
associated ditch construction, to serve traffic
needs and for utilities.
(B) Ditches.
1. A ditch shall be provided on both
sides of a through-cut and on the inside
shoulder of a cut-and-fill section, with ditch
relief cross drains spaced according to grade.
Water shall be intercepted before reaching a
switchback or large fill and drained safely
away in accordance with this section. Water
from a fill or switchback shall be released
below the fill, through conduits or in
riprapped channels and shall not be discharged onto the fill. Drainage ditches shall
be placed on the toe of all cut slopes formed
by the construction of roads.
2. On the flat sections of Class I roads
where rolling topography is insufficient to
provide natural ditch drainage, the road grade
shall be undulated to provide for free flow of
water in the ditch section. Road sections may
be constructed to elevate the road surface
above the original ground surface to facilitate
drainage.
(C) Culverts and Bridges.
1. Culvert design.
A. Culverts with an end area of thirty-five (35) square feet or less shall be
designed to safely pass the ten (10)-year,
twenty-four (24)-hour precipitation event
without a head of water at the entrance.
Culverts with an end area greater than thirtyfive (35) square feet and bridges with spans
of thirty feet (30') or less, shall be designed
to safely pass the twenty (20)-year, twentyfour (24)-hour precipitation event. Bridges
with spans of more than thirty feet (30') shall
be designed to safely pass the one hundred
(100)-year, twenty-four (24)-hour precipitation event or a larger event as specified by the
permit and plan.
B. Drainage pipes and culverts shall
be constructed to avoid plugging or collapse
and erosion at inlets and outlets.
C. Trash racks and debris basins shall
be installed in the drainage ditches wherever
debris from the drainage ditches could impair
the functions of drainage and sediment-control structures.
D. All culverts shall be covered by
compacted fill to a minimum depth of one
foot (1').
E. Culverts shall be designed, constructed and maintained to sustain the vertical
soil pressure the passive resistance of the
foundation and the weight of vehicles to be
used.
2. Culverts for road-surface drainage
only shall be constructed in accordance with
the following:
A. Unless otherwise authorized or
required under subparagraph (4)(C)2.B. or
C. of this rule, culverts shall be spaced as follows. Spacing shall not exceed:
(I) One thousand feet (1000') on
grades of zero percent to three percent (0%–
3%);
(II) Eight hundred feet (800') on
grades of three percent to six percent (3%–
6%);
(III) Five hundred feet (500') on
grades of six percent to ten percent (6%–
10%); and
(IV) Three hundred feet (300') on
grades of ten percent (10%) or greater;
B. Culverts at closer intervals than the
maximum in subparagraph (4)(C)2.A. of this
rule shall be installed if required in the permit and plan as appropriate for the erosive
properties of the soil or to accommodate flow
from small intersecting drainages;
C. Culverts may be constructed at
greater intervals than the maximum indicated
in subparagraph (4)(C)2.A. of this rule if
authorized in the permit and plan upon a
finding that greater spacing will not increase
erosion;
D. Culverts shall cross the road at not
less than a thirty degree (30°) angle downgrade;
E. Culverts may be designed to carry
less than the peak runoff from a ten (10)-year,
twenty-four (24)-hour precipitation event if
the ditch will not overtop and will remain stable; and
F. The inlet end shall be protected by
a rock headwall or other material approved in
the permit and plan as adequate protection
against erosion of the headwall. The water
shall be discharged below the toe of the fill
through conduits or in riprapped channels
and shall not be discharged onto the fill.
(D) Natural Drainage. Natural channel
drainageways shall not be altered or relocated
for road construction or reconstruction without prior approval in the permit and plan in
accordance with 10 CSR 40-3.040(3) and
(4). Alterations and relocations may be
approved in the permit and plan only if—
1. The natural channel drainage is not
blocked;
2. No significant damage occurs to the
hydrologic balance; and
3. There is no adverse impact on adjoining landowners.
(E) Stream Crossings. Drainage structures
are required for stream channel crossing.
Drainage structures shall not affect the normal flow or gradient of the stream, or
adversely affect fish migration and aquatic
habitat or related environmental values.
(5) Roads—Class I—Surfacing.
(A) Class I roads shall be surfaced with
rock, crushed gravel, asphalt or other material approved in the permit and plan as sufficiently durable for the anticipated volume of
traffic, and weight and speed of vehicles to be
used.
(B) Acid- or toxic-forming substances shall
not be used in road surfacing.
(6) Roads—Class I—Maintenance.
(A) Class I roads shall be maintained in a
manner that the required or approved design
standards are met throughout the life of the
entire transportation facility including surface, shoulders, parking and side areas,
approach structures, erosion control devices,
cut-and-fill sections and traffic-control
devices as are necessary for safe and efficient
utilization of the road.
(B) Class I road maintenance shall include
repairs to the road surface, blading, filling of
potholes and replacement of gravel or
asphalt. It shall include revegetating, brush
removal, watering for dust control and minor
reconstruction of road segments as necessary.
(C) Class I roads damaged by catastrophic
events, such as floods or earthquakes, shall
not be used until reconstruction of damaged
road elements. The reconstruction shall be
completed as soon as practicable after the
damage has occurred.
(D) A road shall be maintained to meet the
performance standards applicable in this rule
and any additional criteria specified by the
regulatory authority.
(7) Roads—Class I—Restoration.
(A) Unless the retention of a Class I road
is approved in the permit and plan, as suitable
for the approved postmining land use, immediately after the road is no longer needed for
operations, reclamation or monitoring—
1. The road shall be closed to vehicular
traffic;
2. The natural drainage patterns shall be
restored;
3. All bridges and culverts shall be
removed;
4. Roadbeds shall be ripped, plowed and
scarified;
5. Fill slopes shall be rounded or
reduced and shaped to conform the site to
adjacent terrain and to meet natural drainage
Surface Coal Mining and Related Activities
restoration standards;
6. Cut slopes shall be shaped to blend
with the natural contour;
7. Cross drains, dikes and water bars
shall be constructed to minimize erosion;
8. Terraces shall be constructed as necessary to prevent excessive erosion and to
provide long-term stability in cut-and-fill
slopes; and
9. Road surfaces shall be covered with
topsoil in accordance with 10 CSR 403.030(4)(B) and revegetated in accordance
with 10 CSR 40-3.120(1)–(6).
(B) Unless otherwise authorized in the permit and plan, all road surfacing materials
shall be removed, hauled or conveyed and
disposed of under 10 CSR 40-3.080(8).
(8) Roads—Class II—General.
(A) Each person who conducts surface
mining activities shall locate, design, construct or reconstruct, utilize and maintain
Class II roads and reclaim the area to meet
the requirements of sections (9)–(14) of this
rule and to control or prevent erosion; siltation; the air pollution attendant to erosion,
including road dust as well as dust occurring
on other exposed surfaces, by measures such
as vegetating, watering, using chemical or
other dust suppressants, or otherwise stabilizing all exposed surfaces in accordance with
current, prudent engineering practices; and
water pollution and damage to public or private property.
(B) To the extent possible using the best
technology currently available, Class II roads
shall not cause damage to fish, wildlife and
related environmental values and shall not
cause additional contributions to suspended
solids to streamflow or to runoff outside the
permit area. These contributions shall not be
in excess of limitations of state or federal law.
(C) All Class II roads shall be removed and
the affected land regraded and revegetated in
accordance with the requirements of section
(14) of this rule, unless—
1. Retention of the road is approved as
part of the approved postmining land use or
as being necessary to control erosion adequately;
2. The necessary maintenance is
assured; and
3. All drainage is controlled according
to section (11) of this rule.
(D) Class II Roads General Design.
1. The design and construction or reconstruction of Class II roads shall be certified
by a registered professional engineer in
accordance with sections (9)–(12) of this
rule. Construction or reconstruction of Class
II roads must be certified in a report to the
director. The report shall indicate that the
Class II road has been constructed or reconstructed as designed and in accordance with
the approved plan.
2. The design shall incorporate consideration of the needs of the specific uses of the
road in addition to travel efficiency. To the
extent that the anticipated volume of traffic or
weight or speed of vehicles to be used
requires higher standards than those set forth
in sections (9)–(14) of this rule, those higher
standards shall be incorporated in the design,
construction or reconstruction and maintenance of Class II roads.
(9) Roads—Class II—Location.
(A) Class II roads shall be located, as far
as possible, on ridges or on the most stable
available slopes to minimize erosion.
(B) No part of any Class II road shall be
located in the channel of an intermittent or
perennial stream unless specifically approved
in the permit and plan.
(C) Stream fords are prohibited unless they
are specifically approved in the permit and
plan as temporary routes during periods of
construction. The fords shall not adversely
affect stream sedimentation or fish, wildlife
and related environmental values. All other
stream crossings shall be made using bridges,
culverts or other structures, designed, constructed and maintained to meet the requirements of section (11) of this rule.
(D) Class II roads shall be located to minimize downstream sedimentation and flooding.
(10) Roads—Class II—Design and Construction. Class II roads shall be designed and
constructed or reconstructed in compliance
with the following standards in order to control subsequent erosion and disturbance of the
hydrologic balance:
(A) Vertical Alinement. A continuous
grade with excessive cuts or embankments
shall be avoided. Changes of grade shall be
made to conform as closely as possible to the
existing terrain and maximum road grades
shall be as follows:
1. The overall grade shall not exceed
1v:10h (10%);
2. The pitch grade shall not exceed
1v:6.5h (15%), for any consecutive one thousand feet (1000'); and
3. The pitch grade exceeding fifteen percent (15%) shall not be longer than three
hundred feet (300') within any consecutive
one thousand feet (1000') of Class II roads;
(B) Horizontal Alinement. Class II roads
shall have horizontal alinement as consistent
with the existing natural topography as possible and shall provide the alinement required
for the performance standards of sections
(8)–(14) of this rule. The alinement shall be
determined in accordance with the anticipated volume of traffic and weight and speed of
vehicles to be used. Horizontal and vertical
alinement shall be coordinated to ensure that
one will not adversely affect the other and to
ensure that the road will not cause environmental damage;
(C) Road Cuts. Cut slopes shall not be
steeper than specifically authorized in the
permit and plan, which shall not authorize
slopes steeper than 1v:1.5h in unconsolidated
materials or 1v:0.25h in rock, except that
steeper slopes may be specifically authorized
in the permit and plan if geotechnical analysis
demonstrates that a minimum safety factor of
one and five-tenths (1.5) can be maintained.
1. Topsoil or other materials suitable
under 10 CSR 40-3.030(2) shall be placed on
all cut slopes of 1v:1.5h or flatter to aid in
establishing vegetation and to minimize erosion. Topsoil depth shall be adequate to support vegetation necessary to minimize erosion.
2. Temporary erosion control measures
shall be implemented during construction to
minimize sedimentation and erosion until
permanent control measures can be established;
(D) Road Embankments. Embankment
sections shall be constructed in accordance
with the following provisions:
1. All vegetative material and topsoil
shall be removed from the embankment foundation to increase stability and no vegetative
material or topsoil shall be placed beneath or
in any Class II road embankment;
2. Where any embankment is to be
placed on side slopes exceeding 1v:3h (33%),
the existing ground shall be plowed, stepped
or if in rock, keyed in a manner which
increases the stability of the fill. The keyways
shall be a minimum of ten feet (10') in width
and shall begin at the toe of the fill. No material shall be placed below the toe or be
allowed to slide below the toe. For slopes of
less than 1v:3h (33%), the slopes shall be
scarified to ensure bonding of the embankment and natural material;
3. Material containing by volume less
than twenty-five percent (25%) of rock larger
than six inches (6") in greatest dimension
shall be spread in successive uniform layers
not exceeding twelve inches (12") in thickness before compaction;
4. Where the material for an embankment consists of large size rock, broken stone
or fragmented material that makes placing in
twelve-inch (12") layers impossible under
paragraph (10)(D)3. of this rule, the embankment shall be constructed in uniform layers
not exceeding in thickness the approximate
average size of the rock used but, the layers
shall not exceed thirty-six inches (36") in
thickness. Rock shall not be dumped in final
position, but shall be distributed by blading
or dozing in a manner that will ensure proper
placement in the embankment, so that voids,
pockets and bridging will be reduced to a
minimum. The final layer of the embankment
shall meet the requirements of paragraph
(10)(D)3. of this rule;
5. Each layer of the embankment shall
be completed, leveled and compacted before
the succeeding layer is placed. Embankment
material shall be leveled as placed and kept
smooth. The successive layers shall be compacted evenly by routing the hauling and leveling equipment over the entire width of the
embankment. This procedure shall be continued until no visible horizontal movement of
the embankment material is apparent;
6. Compaction greater than that specified in paragraph (10)(D)5. of this rule shall
be performed to the extent necessary to
ensure stability;
7. Material shall be placed in an
embankment under moisture content conditions which will permit compaction and
ensure proper soil cohesion;
8. Embankment slopes shall not be
steeper than 1v:1.5h, except that if the
embankment material is a minimum of
eighty-five percent (85%) rock, slopes shall
not be steeper than 1v:1.35h if it has been
demonstrated that embankment stability will
result. Where rock embankments are constructed, they shall meet the requirements of
paragraph (10)(D)4. of this rule;
9. The minimum safety factor for all
embankments shall be one and three-tenths
(1.3) or a higher factor as may be specified in
the permit or plan;
10. The road surface shall be sloped sufficiently to prevent ponding of water on the
surface;
11. All material used in embankments
shall be suitable for use under paragraphs
(10)(D)1.–8. of this rule. The material shall
be reasonably free of organic material, coal
or coal blossom, frozen materials, wet or
peat material or natural soils containing
organic matter or any other material considered unsuitable for use in embankment construction in the permit and plan;
12. Excess or unsuitable material from
excavations, as defined in paragraph
(10)(D)11. of this rule, shall be disposed of in
accordance with 10 CSR 40-3.040(8), 10
CSR 40-3.060(1), 10 CSR 40-3.080(1) and
10 CSR 40-3.110(3);
13. Topsoil or other material suitable
under 10 CSR 40-3.030(2) shall be placed on
all embankment slopes of 1v:1.5h or flatter
to aid in establishing vegetation to minimize
erosion. Topsoil material depth shall be adequate to support vegetation and to minimize
erosion; and
14. Temporary erosion control measures
shall be incorporated during construction to
control sedimentation and minimize erosion
until permanent control measures can be
established; and
(E) Topsoil Removal. Before initiation of
construction or reconstruction of a Class II
road, topsoil and other materials, as determined under 10 CSR 40-3.030(2), shall be
removed from the design roadbed, shoulders
and surfaces where associated structures will
be placed and shall be stored in accordance
with 10 CSR 40-3.030(3).
(11) Roads—Class II—Drainage.
(A) General.
1. Each Class II road shall be designed,
constructed or reconstructed and maintained
to have adequate drainage, using structures
such as ditches in wet areas, cross drains in
natural drainageways, surface dips and stream
crossings. The water control system shall be
designed to safely pass the peak runoff from
a ten (10)-year, twenty-four (24)-hour precipitation event or a greater event if required in
the permit and plan.
2. Sediment control shall comply with
10 CSR 40-3.040(2) and (5).
(B) Ditches and Alternative Measures for
Roadbed Erosion Control. Where required to
minimize erosion on the roadbed, ditches
shall be designed and constructed in accordance with subsection (4)(B) of this rule. In
wet areas or where there is free water, these
ditch sections shall be required. For every
segment of a Class II road without drainage
ditches which comply with subsection (4)(B)
of this rule, drainage shall be provided by
surface dips. These drainage dips shall be
constructed as undulations in the roadway of
sufficient height from the hydraulic bottom to
the top of the dip to prevent water from running down the surface of the road. Insloped
dips shall discharge into a culvert or drop
inlet. Outsloped dips shall discharge either
onto the natural ground or onto embankments
if a drain is provided. The bottom of the dip
shall be rock surfaced to prevent erosion. Dip
spacing shall be sufficient to minimize erosion of the road surface.
(C) Culverts and Bridges.
1. Culvert design.
A. Culverts with an end area of thirty-five (35) square feet or less shall be
designed to safely pass the ten (10)-year,
twenty-four (24)-hour precipitation event
without a head of water at the entrance.
Culverts with an end area of greater than thirty-five (35) square feet and bridges with
spans of thirty feet (30') or less, shall be
designed to safely pass the twenty (20)-year,
twenty-four (24)-hour precipitation event.
Bridges with spans of more than thirty feet
(30') shall be designed to safely pass the one
hundred (100)-year, twenty-four (24)-hour
precipitation event or larger event as specified
in the permit and plan.
B. Drainage pipes and culverts shall
be constructed to avoid plugging or collapse
and erosion at inlets and outlets.
C. Culverts shall be covered by compacted fill to minimum depth of one foot (1').
D. Culverts shall be designed, constructed and maintained to sustain the vertical
soil pressure, the passive resistance of the
road foundation and the weight of vehicles to
be used.
2. Culverts or dips for road-surface
drainage only shall be constructed in accordance with the following:
A. Unless otherwise authorized or
required under subparagraph (11)(C)2.B. or
C. of this rule, culverts and dips shall be
spaced as follows. Spacing shall not exceed:
(I) One thousand feet (1000') on
grades of zero percent to three percent (0%–
3%);
(II) Six hundred feet (600') on
grades of three percent to six percent (3%–
6%);
(III) Four hundred feet (400') on
grades of six percent to ten percent (6%–
10%); and
(IV) Two hundred feet (200') on
grades of ten percent (10%) or greater;
B. Surface dips or culverts at closer
intervals than the maximum indicated in subparagraph (11)(C)2.A. of this rule shall be
installed if required in the permit and plan as
appropriate for the erosive properties of the
soil or to accommodate flow from small
intersecting drainages;
C. Surface dips or culverts may be
constructed at greater intervals than the maximum indicated in subparagraph (11)(C)2.A.
of this rule if authorized in the permit and
plan upon a finding that greater spacing will
not increase erosion;
D. Culverts and the bottoms of
drainage dips shall cross the road at not less
than a thirty degree (30°) angle downgrade;
E. A culvert may be designed to carry
less than the peak runoff from a ten (10)-year,
twenty-four (24)-hour precipitation event if
the ditch will not overtop and will remain stable; and
F. The inlet end of all culverts shall be
protected by a rock headwall or other material
approved in the permit and plan as adequate
protection against erosion of the headwall.
Surface Coal Mining and Related Activities
The water shall be discharged below the toe
of the fill through conduits or in riprapped
channels and shall not be discharged onto the
fill.
(D) Natural Drainage. Natural channel
drainageways shall not be altered or relocated
for road construction or reconstruction without the prior approval in the permit and plan
in accordance with 10 CSR 40-3.040(3) and
(4). The permit and plan may approve alterations and relocations only if—
1. The natural channel drainage is not
blocked;
2. No significant degradation occurs to
the hydrologic balance; and
3. There is no adverse impact on adjoining landowners.
(E) Stream Crossings. Drainage structures
are required for stream channel crossings.
Drainage structures shall not affect the normal flow or gradient of the stream, or
adversely affect fish migration or aquatic
habitat or related environmental values.
(12) Roads—Class II—Surfacing.
(A) Class II roads shall be surfaced with
rock, crushed gravel, asphalt or other material approved in the permit and plan as sufficiently durable for the anticipated volume of
traffic and weight and speed of vehicles to be
used.
(B) Acid- or toxic-forming substances shall
not be used in road surfacing.
(C) Vegetation shall not be cleared for
more than the width necessary for road and
associated ditch construction, to serve traffic
needs and for utilities.
(13) Roads—Class II—Maintenance.
(A) Class II roads shall be maintained in
such a manner that the required or approved
design criteria are met throughout the life of
the facility including surface and shoulders,
parking, side areas, approach structures, erosion-control devices and these traffic control
devices as are necessary for safe and efficient
utilization.
(B) Class II road maintenance shall include
basic custodial care as required to protect the
road investment and to prevent damage to
adjacent resources. This includes maintenance to control erosion, repair of structures
and drainage systems, removal of rocks and
debris, replacement of surface and restoration
of the road prism.
(C) A road damaged by a catastrophic
event, such as a flood or earthquake, shall be
repaired as soon as is practicable after the
damage has occurred.
(D) A road shall be maintained to meet the
performance standards applicable in this rule
and any additional criteria specified by the
regulatory authority.
(14) Roads—Class II—Restoration.
(A) Unless the retention of a Class II road
is approved in the permit and plan, as suitable
for the approved postmining land use, immediately after the road is no longer needed for
operations, reclamation or monitoring—
1. The road shall be closed to vehicular
traffic;
2. The natural drainage patterns shall be
restored;
3. All bridges and culverts shall be
removed;
4. Roadbeds shall be ripped, plowed and
scarified;
5. Fill slopes shall be rounded or
reduced and shaped to conform the site to
adjacent terrain and to meet natural drainage
restoration standards;
6. Cut slopes shall be reshaped to blend
with the natural contour;
7. Cross drains, dikes and water bars
shall be constructed to minimize erosion;
8. Terraces shall be constructed as necessary to prevent excessive erosion and to
provide long-term stability in cut-and-fill
slopes; and
9. Road surfaces shall be covered with
topsoil in accordance with 10 CSR 403.030(4)(B) and revegetated in accordance
with 10 CSR 40-3.120(1)–(6).
(B) Unless otherwise authorized in the permit and plan, all road surfacing materials
shall be removed, hauled or conveyed and
disposed of under 10 CSR 40-3.080(8).
(15) Roads—Class III—General.
(A) Each person who conducts surface
mining activities shall locate, design, construct or reconstruct, utilize and maintain
Class III roads and reclaim the area to meet
the requirements of sections (16)–(21) of this
rule and to control or prevent erosion;
siltation; the air pollution attendant to erosion, including road dust as well as dust
occurring on other exposed surfaces, by measures such as vegetating, watering, using
chemical or other dust suppressants, or otherwise stabilizing all exposed surfaces in
accordance with current, prudent engineering
practices; and water pollution and damage to
public or private property.
(B) To the extent possible using the best
technology currently available, Class III
roads shall not cause damage to fish, wildlife
and related environmental values and shall
not cause additional contributions of suspended solids to streamflow or to runoff outside
the permit area. These contributions shall not
be in excess of limitations of state or federal
law.
(C) All Class III roads shall be completely
removed and the land affected regraded to the
approximate original contour and revegetated
in accordance with the requirements of section (21) of this rule except where subsection
(16)(G) of this rule shall apply.
(D) To the extent that the anticipated volume or weight or speed of vehicles to be used
requires higher standards than those set forth
in sections (16)–(21) of this rule, these higher
standards shall be incorporated in the design,
construction and reconstruction or maintenance of Class III roads.
(16) Roads—Class III—Location.
(A) Class III roads shall be located on
ridges or on the most stable available slopes
to minimize erosion.
(B) No part of any Class III road shall be
located in the channel of an intermittent or
perennial stream unless specifically approved
in the permit and plan.
(C) Stream fords are prohibited unless they
are approved in the permit and plan as temporary routes across ephemeral or intermittent streams that will not adversely affect
stream sedimentation or fish, wildlife and
related environmental values. All other
stream crossings shall be made using temporary bridges, culverts or other structures
designed, constructed and maintained to meet
the requirements of section (18) of this rule.
(D) Class III roads shall be located to minimize downstream sedimentation and flooding.
(E) Not later than the date a permit application is submitted to the director for surface
mining activities for which a Class III road is
proposed, the location of the proposed road
shall be clearly marked in the field by flags
or stakes to enable the director to perform
on-site review.
(F) Class III roads shall not be located in
wet, steep or unstable areas where complete
restoration under section (21) of this rule cannot be accomplished.
(G) A Class III road may be constructed in
the same alinement as a Class I or Class II
road that is to be constructed on the same
location at a later date. This may be permitted if the requirements for the location of the
Class I or Class II road are met and the construction begins within six (6) months from
the time the Class III road is constructed.
(17)
Roads—Class
III—Design
and
Construction. Field design methods shall be
utilized for Class III roads.
(A) Vertical Alinement. Except where lesser grades are necessary to control site-specific conditions, maximum road grades shall be
as follows:
1. The overall grade shall not exceed
1v:10h (10%);
2. The pitch grade shall not exceed
1v:5h (20%); and
3. There shall not be more than one
thousand (1000) consecutive feet of maximum pitch grade.
(B) Horizontal Alinement. Class III roads
may meander so as to avoid large growths of
vegetation and other natural obstructions.
(C) Road Cuts. Sidecast construction may
be used.
(D) Road Embankments. Compaction on
embankments shall be required only to the
extent necessary to control erosion and maintain the road.
(E) Topsoil Removal. Topsoil shall be
removed and stockpiled only where excavation would require replacement of material
and redistribution of topsoil for proper revegetation.
(18) Roads—Class III—Drainage.
(A) General.
1. Class III road drainage shall consist
of temporary culverts in flowing streams, wet
areas and in ephemeral channels as necessary
to protect the facility during its life and to
minimize disturbance of the hydrologic balance.
2. Sediment control shall comply with
10 CSR 40-3.040(2) and (5).
(B) Culverts and Bridges. Temporary culverts shall be installed for all flowing
drainages and stream crossings. Temporary
culverts and bridges shall be sized to safely
pass the one (1)-year, six (6)-hour precipitation event.
(C) Natural Drainage. Natural channel
drainageways shall not be altered or relocated
for the purposes of Class III road construction.
(D) Stream Crossing. Temporary drainage
structures are required for crossing permanent streams. Drainage structures shall not
affect the normal flow or gradient of the
stream, adversely affect fish migration and
aquatic habitat or related environmental values.
(19) Roads—Class III—Surface.
(A) Class III road surfaces shall be adequate for the use of the road.
(B) Acid- or toxic-forming substances shall
not be used in road surfacing.
(C) Vegetation shall not be cleared for
more than the width necessary to serve traffic
needs and for utilities.
(20) Roads—Class III—Maintenance.
(A) Class III roads shall be sufficient to
ensure minimization of erosion for the life of
the road.
(B) Class III roads shall not be used if climatic conditions are such that usage may
cause degradation of water quality.
(C) A road damaged by a catastrophic
event, such as a flood or earthquake, shall be
repaired as soon as is practicable after the
damage has occurred.
(D) A road shall be maintained to meet the
performance standards applicable in this rule
and any additional criteria specified by the
regulatory authority.
(21) Roads—Class III—Restoration. Immediately after a Class III road is no longer needed for operations, reclamation or monitoring—
(A) The road shall be closed to vehicular
traffic;
(B) The natural drainage patterns shall be
restored;
(C) All bridges and culverts shall be
removed;
(D) Roadbeds shall be ripped, plowed and
scarified;
(E) Fill slopes shall be rounded or reduced
and shaped to conform the site to adjacent
terrain and meet natural drainage restoration
standards;
(F) Cut slopes shall be reshaped to blend
with the natural contour;
(G) Cross drains, dikes and water bars
shall be constructed to control erosion; and
(H) Road surfaces from which topsoil has
been removed shall be covered with topsoil in
accordance with 10 CSR 40-3.030(4)–(8) and
the surface shall be vegetated in accordance
with 10 CSR 40-3.120(1)–(6).
(22) Other Transportation Facilities. Railroad
loops, spurs, sidings, surface conveyor
systems, chutes, aerial tramways or other
transportation facilities shall be designed,
constructed or reconstructed and maintained
and the area restored, to—
(A) Prevent, to the extent possible using
the best technology currently available—
1. Damage to fish, wildlife and related
environmental values; and
2. Additional contributions of suspended
solids to streamflow or runoff outside the
permit area. These contributions shall not be
in excess of limitations of state or federal law;
(B) Control and minimize diminution or
degradation of water quality and quantity;
(C) Control and minimize erosion and siltation;
(D) Control and minimize air pollution;
and
(E) Prevent damage to public or private
property.
(23) Support Facilities and Utility Installations.
(A) Support facilities required for or used
incidentally to, the operation of the mine,
including, but not limited to, mine buildings,
coal loading facilities at or near the mine site,
coal storage facilities, equipment storage
facilities, fan buildings, hoist buildings,
preparation plants, sheds, shops and other
buildings shall be designed, constructed or
reconstructed and located to prevent or control erosion and siltation, water pollution and
damage to public or private property. Support
facilities shall be designed, constructed or
reconstructed, maintained and used in a manner which prevents to the extent possible
using the best technology currently available—
1. Damage to fish, wildlife and related
environmental values; and
2. Additional contributions of suspended
solids to streamflow or runoff outside the
permit area. These contributions shall not be
in excess of limitations of state or federal law.
(B) All surface mining activities shall be
conducted in a manner which minimizes
damages, destruction or disruption of services provided by oil, gas and water wells;
oil, gas and coal-slurry pipelines; railroads;
electric and telephone lines; and water and
sewage lines which pass over, under or
through the permit area, unless otherwise
approved by the owner of those facilities and
in the permit and plan.
AUTHORITY: sections 444.530 and 444.810
RSMo Supp. 1999.* Original rule filed Oct.
12, 1979, effective Feb. 11, 1980. Amended:
Filed July 3, 1990, effective Nov. 30, 1990.
Amended: Filed May 15, 1992, effective Jan.
15, 1993. Amended: Filed Sept. 15, 1994,
effective April 30, 1995. Amended: Filed
March 21, 2000, effective Oct.30, 2000.
*Original authority: 444.530, RSMo 1971, amended 1983,
1990, 1993, 1995; 444.810, RSMo 1979, amended 1983,
1993, 1995.