10 CSR 40-6.050
Surface Mining Permit Applications—Minimum Requirements for Reclamation and Operations Plan
PURPOSE: This rule sets forth requirements
for reclamation and operations plans for surface mining permit applications pursuant to
sections 444.810, 444.820, and 444.825,
RSMo.
PUBLISHER’S NOTE: The secretary of state
has determined that the publication of the
entire text of the material which is incorporated by reference as a portion of this rule would
be unduly cumbersome or expensive. This
material as incorporated by reference in this
rule shall be maintained by the agency at its
headquarters and shall be made available to
the public for inspection and copying at no
more than the actual cost of reproduction.
This note applies only to the reference material. The entire text of the rule is printed here.
(1) Responsibilities. It is the responsibility
of—
(A) The applicant to provide to the commission and director all of the information
required by this rule except where specifically exempted in this rule.
(B) State and federal governmental agencies to provide information to the commission
and director where specifically required in
this rule.
(2) Operations Plan—General Requirements.
Each application shall contain a description
of the mining operations proposed to be conducted during the life of the mine within the
proposed mine plan area, including at a minimum, the following:
(A) A narrative description of the type and
method of coal mining procedures and proposed engineering techniques, anticipated
annual and total production of coal by tonnage, and the major equipment to be used for
all aspects of those operations; and
(B) A narrative explaining the construction, modification, use, maintenance, and removal of the following facilities (unless retention of these facilities is necessary for postmining land use as specified in 10 CSR 403.130):
1. Dams, embankments, and other
impoundments;
2. Overburden and topsoil handling and
storage areas and structures;
3. Coal removal, handling, storage,
cleaning, and transportation areas and structures;
4. Spoil, coal processing waste and noncoal waste removal, handling, storage, transportation, and disposal areas and structures.
Except for spoil, the narrative should be in
accordance with the appropriate section(s) of
10 CSR 40-3.080;
5. Mine facilities; and
6. Water and air pollution control facilities.
(3) Operations Plan—Existing Structures.
(A) Each application shall contain a
description of each existing structure proposed to be used in connection with
or to facilitate the surface coal mining and
reclamation operation. The description shall
include:
1. Location;
2. Plans of the structure which describe
its current condition;
3. Approximate dates on which construction of the existing structure was begun
and completed; and
4. A showing, including relevant monitoring data or other evidence, whether the
structure meets the performance standards of
10 CSR 40-3 and 10 CSR 40-4, or if the
structure does not meet the performance standards of 10 CSR 40-3 and 10 CSR 40-4, a
showing whether the structure meets the performance standards of 10 CSR 40-2.
(B) Each application shall contain a compliance plan for each existing structure proposed to be modified or reconstructed for use
in connection with or to facilitate the surface
coal mining and reclamation operation. The
compliance plan shall include:
1. Design specifications for the modification or reconstruction of the structure to
meet the design and performance standards of
10 CSR 40-3 and 10 CSR 40-4;
2. A construction schedule which shows
dates for beginning and completing interim
steps and final reconstruction;
3. Provisions for monitoring the structure during and after modification or reconstruction to ensure that the performance standards of 10 CSR 40-3 and 10 CSR 40-4 are
met; and
4. A showing that the risk of harm to the
environment or to public health or safety is
not significant during the period of modification or reconstruction.
(4) Operations Plan—Blasting.
(A) Blasting Plan. Each permit application
shall contain a blasting plan for the proposed
permit area, explaining how the applicant
will comply with the requirements of 10 CSR
40-3.050(1)–(6). This plan shall include, at a
minimum, information setting forth the limitations the operator will meet with regard to
ground vibration and air blast, the bases for
those limitations, and the methods to be
applied in controlling the adverse effects of
blasting operations.
(B) Monitoring System. Each application
shall contain a description of any system to be
used to monitor compliance with the standards of 10 CSR 40-3.050(5), including the
type, capability, and sensitivity of any blast
monitoring equipment and proposed procedures and locations of monitoring.
(C) Blasting Near Underground Mines.
Blasting operations within five hundred feet
(500') of active underground mines require
approval of the state and federal regulatory
authorities concerned with the health and
safety of underground miners.
(5) Operations Plan—Maps and Plans. Each
application shall contain maps and plans of
the proposed mine plan and adjacent areas as
follows:
(A) The maps and plans shall show the
lands proposed to be affected throughout the
operation and any change in a facility or feature to be caused by the proposed operations,
if the facility or feature was shown under 10
CSR 40-6.040(14) and (15);
(B) The following shall be shown for the
proposed permit area unless specifically
required for the mine plan area or adjacent
area by the requirements of this section:
1. Buildings, utility corridors, and facilities to be used;
2. The area of land to be affected within
the proposed mine plan area according to the
sequence of mining and reclamation;
3. Each area of land for which a performance bond will be posted under 10 CSR 407;
4. Each coal storage, cleaning, and loading area;
5. Each topsoil, spoil, coal waste, and
noncoal waste storage area. Except for topsoil
and spoil, the narrative should be in accordance with the appropriate section(s) of 10
CSR 40-3.080;
6. Each water diversion, collection, conveyance, treatment storage, and discharge
facility to be used;
7. Each air pollution collection and control facility;
8. Each source of waste and each waste
disposal facility relating to coal processing or
pollution control in accordance with 10 CSR
40-3.080(1)–(6);
9. Each facility to be used to protect and
enhance fish and wildlife and related environmental values;
10. Each explosive storage and handling
facility; and
11. Location of each siltation structure,
permanent water impoundment, coal processing waste bank and coal processing waste
dam and embankment in accordance with
section (11), and fill area for the disposal of
excess spoil in accordance with section (16).
(C) Maps, plans, and cross-sections
required under paragraphs (5)(B)4., 5., 6.,
10., and 11. of this rule shall be prepared by
or under the direction of and certified by a
qualified registered professional engineer,
with assistance from experts in related fields
such as land surveying and landscape architecture except that—
1. Maps, plans, and cross-sections for
siltation structures may only be prepared by a
qualified registered professional engineer;
and
2. Spoil disposal facilities, maps, plans,
and cross-sections may only be prepared by a
qualified registered engineer.
(6) Air Pollution Control Plan. The application shall contain an air pollution control plan
which includes the following:
(A) An air quality monitoring program, if
required for approval, to provide sufficient
data to evaluate the effectiveness of the fugitive dust control practices under subsection
(6)(B) of this rule to comply with applicable
federal and state air quality standards; and
(B) A plan for fugitive dust control practices, as required under 10 CSR 40-3.090.
(7) Fish and Wildlife Plan.
(A) The fish and wildlife plan requirements
shall
be
consistent
with
the
Endangered Species Act of 1973, as amended
(16 U.S.C. Section 1531, et seq.); section
444.855.2(17),
RSMo;
10
CSR
403.040(18); and 10 CSR 40-3.100.
(B) Each application shall contain a fish
and wildlife plan which provides—
1. A statement of how, to the extent possible using the best technology currently
available, the plan will minimize disturbances
and adverse impacts on fish and wildlife and
related environmental values during surface
coal mining and reclamation operations and
how enhancement of these resources will be
achieved, where practicable. The plan shall
be consistent with the requirements of 10
CSR 40-3.100; cover the mine plan area and
portions of adjacent areas as determined by
the director pursuant to 10 CSR 406.040(11); and
2. If the applicant states that it will not
be practicable, in accordance with paragraph
(7)(B)1. of this rule, to achieve a condition
which clearly shows a trend toward enhancement of fish and wildlife resources at the time
revegetation has been successfully completed
under 10 CSR 40-3.120, a statement shall be
provided which establishes, to the satisfaction
of the director, why it is not practicable to
achieve this condition.
(C) A statement must be included in the
fish and wildlife plan explaining how the
applicant will utilize impact control measures, management techniques, and monitoring methods to protect or enhance the following, if they are to be affected by the proposed
activities:
1. Listed or proposed threatened or
endangered species of plants or animals listed
by the secretary under the Endangered
Species Act of 1973, as amended (16 U.S.C.
1531, et seq.) and their critical habitats;
2. Species such as eagles, migratory
birds, or other animals protected by state or
federal law, and their habitats, or other
species identified through the consultation
process pursuant to 10 CSR 40-6.040(11); or
3. Habitats of unusually high value for
fish and wildlife, such as important streams,
wetlands, riparian areas, cliffs supporting
raptors, areas offering special shelter or protection, migration routes, reproduction and
nursery areas and wintering areas, and
and Reclamation Operations and Coal Exploration
including those sites listed as having significance in the Missouri Natural Features
Inventory.
(D) Each fish and wildlife plan shall
include a description of how, to the extent
possible using the best technology currently
available, the operator will minimize disturbances and adverse impacts on fish and
wildlife and related environmental values,
including compliance with the Endangered
Species Act, during the surface coal mining
and reclamation operations and how enhancement of these resources will be achieved
where practicable. This description shall—
1. Be consistent with the requirements
of this section and 10 CSR 40-3.100;
2. Apply, at a minimum, to species and
habitats identified under subsection (7)(C);
and
3. Include—
A. Protective measures that will be
used during the active mining phase of operation. Such measures may include the establishment of buffer zones, the selective location and special design of haul roads and
powerlines, species and habitats, and the
monitoring of surface water quality and quantity; and
B. Enhancement measures that will be
used during the reclamation and postmining
phase of operation to develop aquatic and terrestrial habitat. Such measures may include
restoration of streams and other wetlands,
retention of ponds and impoundments, establishment of vegetation for wildlife food and
cover, and the replacement of perches and
nest boxes. Where the plan does not include
enhancement measures, a statement shall be
given explaining why enhancement is not
practicable.
(8) Reclamation Plan—General Requirements.
(A) Each application shall contain a plan
for reclamation of the lands within the proposed permit area, showing how the applicant
will comply with section 444.855, RSMo, 10
CSR 40-3 and 10 CSR 40-4, and the environmental protection performance standards of
the regulatory program. The plan shall
include, at a minimum, all information
required under sections (8)–(17).
(B) Each plan shall contain the following
information for the proposed permit area:
1. A detailed timetable for the completion of each major step in the reclamation
plan;
2. A detailed estimate of the cost of
reclamation of the proposed operations
required to be covered by a performance bond
under 10 CSR 40-7 with supporting calculations for the estimates;
3. A plan for backfilling, soil stabilization, compacting, and grading, with contour
maps or cross-sections that show the anticipated final surface configuration of the proposed permit area in accordance with 10 CSR
40-3.110(1)–(6);
4. A plan for removal, storage, and
redistribution of topsoil, subsoil, and other
material to meet the requirements of 10 CSR
40-3.030(1)–(5);
5. A plan for revegetation as required in
10 CSR 40-3.120(1)–(7), including, but not
limited to, descriptions of the:
A. Schedule of revegetation;
B. Species and amounts per acre of
seeds and seedlings to be used;
C. Methods to be used in planting and
seeding;
D. Mulching techniques;
E. Irrigation, if appropriate and pest
and disease control measures, if any;
F. Measures proposed to be used to
determine the success of revegetation as
required in 10 CSR 40-3.120(6), including a
plan for revegetation and liability release as
required in 10 CSR 40-3.120(1)–(7) and also
including, but not limited to:
(I) A map showing locations of proposed test plots and reference areas on a scale
not less than one inch equals five hundred
feet (1"=500');
(II) A map delineating the area
which will be proposed for release based on
the outcome of the test plots;
(III) A statement indicating when
mining occurred at the area proposed for
release;
(IV) Documentation that the reference areas chosen are representative of the
soils in the permit area before mining and
that test plots chosen are representative of the
reconstructed soils in the permit area;
(V) A statement indicating which
crop(s) will be used to prove success of
revegetation, what harvesting method will be
employed to gather the necessary data and
what statistics will be employed to assure random sampling if harvesting will be done from
a portion of the test plots and reference areas;
(VI) A statement that plots will be
treated equally with regard to seeding dates,
fertilization for the same yield goal, herbicide
use, tillage type and frequency, row spacing,
planting rates, and harvest dates;
(VII) How the plots will be marked
in the field;
(VIII) If the land to be used for
plots is not under company control, a statement from the company granting the commission the right of entry must be included;
(IX) An account of the method to
be used to randomly choose the plots;
(X) A soil testing plan that includes, at a minimum, tests for pH, nitrogen,
phosphorus, potassium, calcium, magnesium, sulfur, and lime requirement; and
(XI) A plan discussing how the
vegetation on the affected area will be maintained until Phase III release is approved;
G. A soil testing plan for evaluation of
the results of topsoil handling and reclamation procedures related to revegetation; and
H. Nutrient and soil amendment
plans;
6. A description of the measures to be
used to maximize the use and conservation of
the coal resources;
7. A description of measures to be
employed to ensure that all debris, acid- and
toxic-forming materials, and materials constituting a fire hazard are disposed of in accordance with 10 CSR 40-3.080(8) and 10 CSR
40-3.110(3) and a description of the contingency plans which have been developed to
preclude sustained combustion of materials;
8. A description, including appropriate
cross-sections and maps of the measures to be
used to seal or manage mine openings and to
plug, case, or manage exploration holes,
other bore holes, wells, and other openings
within the proposed permit area, in accordance with 10 CSR 40-3.020(1)–(3); and
9. A description of steps to be taken to
comply with the requirements of the Clean
Air Act (42 U.S.C. Section 7401) and Clean
Water Act (33 U.S.C. Section 1251) and
other applicable air and water quality laws
and regulations and health and safety standards.
(9) Reclamation Plan—Protection of Hydrologic Balance.
(A) Sampling and Analysis. All water quality analyses performed to meet the requirements of this section shall be conducted
according to the methodology in the Standard
Methods for the Examination of Water and
Wastewater 22nd Edition 2012, published by
American Public Health Association, 800 I
Street, NW, Washington, DC 20001, which is
incorporated by reference, or the methodology
in 40 CFR Parts 136 and 434. This subsection
does not incorporate any later amendments or
additions. Water quality sampling performed
to meet the requirements of this section shall
be conducted according to either methodology listed previously when feasible.
(B) Each plan shall contain a detailed
description, with appropriate maps and crosssection drawings of the measures to be taken
during and after the proposed surface mining
activities in accordance with 10 CSR 40-3 to
ensure the protection of—
1. The quality of surface and ground
water systems, both within the proposed mine
plan and adjacent areas, from the adverse
effects of the proposed surface mining activities;
2. The rights of present users of surface
and ground water; and
3. The quantity of surface and ground
water both within the proposed mine plan
area and adjacent area from adverse effects of
the proposed surface mining activities or to
provide alternative sources of water in accordance with 10 CSR 40-6.040(8) and 10 CSR
40-3.040(14), where the protection of quantity cannot be ensured.
(C) The description shall include:
1. A plan for the control, in accordance
with 10 CSR 40-3, of surface and ground
water drainage into, through, and out of the
proposed mine plan area; and
2. A plan for the treatment, where
required under 10 CSR 40-3 and 10 CSR 404 and the regulatory program, of surface and
ground water drainage from the area to be
disturbed by the proposed activities and proposed quantitative limits on pollutants in discharges subject to 10 CSR 40-3.040(2),
according to the more stringent of the following:
A. 10 CSR 40-3 and 10 CSR 40-4 and
the regulatory program; or
B. Other applicable state and federal
laws;
3. A plan for the restoration of the
approximate recharge capacity of the mine
plan area in accordance with 10 CSR 403.040(12);
4. A plan for the collection, recording,
and reporting of ground and surface water
quality and quantity data, according to 10
CSR 40-3.040(13); and
5. If the determination of the probable
hydrologic consequences (PHC) required by
subsection (9)(D) of this rule indicates that
adverse impacts on or off the proposed permit area may occur to the hydrologic balance,
or that acid-or toxic-forming material is present that may result in the contamination of
ground or surface water supplies, then information supplemental to that required under
10 CSR 40-6.040(6) and (7), shall be provided to evaluate this PHC and to plan remedial
and reclamation activities. This supplemental
information may be based upon drilling,
aquifer tests, hydrogeologic analysis of the
water-bearing strata, flood flows, or analysis
of other water quality or quantity characteristics.
(D) The description shall include a determination of the probable hydrologic consequences of the proposed surface mining activities, on the proposed mine plan area and
adjacent area, with respect to the hydrologic
regime and the quantity and quality of water
in surface and ground water systems under all
seasonal conditions, including the contents of
dissolved and total suspended solids, total
iron, pH, total manganese, and any other
parameters required by the director.
1. The PHC determination shall be
based on baseline hydrologic, geologic, and
other information collected for the permit
application and may include data statistically
representative of the site.
2. The PHC determination shall include
findings on:
A. Whether adverse impacts may
occur to the hydrologic balance;
B. Whether acid- or toxic-forming
materials are present that could result in the
contamination of surface or ground water
supplies;
C. Whether the proposed operation
may approximately result in contamination,
diminution, or interruption of an underground or surface source of water within the
proposed permit or adjacent areas which is
used for domestic, agricultural, industrial, or
other legitimate purpose;
D. What impact the proposed operation will have on—
(I) Sediment yield from the disturbed area;
(II) Acidity, total suspended and
dissolved solids, and other important water
quality parameters of local impact;
(III) Flooding or stream flow alteration;
(IV) Ground and surface water
availability; and
(V) Other characteristics as required by the regulatory authority.
3. An application for a permit revision
shall be reviewed by the regulatory authority
to determine whether a new or updated PHC
determination shall be required.
(E) Cumulative Hydrologic Impact Assessment.
1. The director shall provide an assessment of the probable cumulative hydrologic
impacts (CHIA) of the proposed operation
and all anticipated mining upon surface and
ground water systems in the cumulative
impact area. The CHIA shall be sufficient to
determine, for purposes of permit approval,
whether the proposed operation has been
designed to prevent material damage to the
hydrologic balance outside the permit area.
The director may allow the applicant to submit data and analyses relevant to the CHIA
with the permit application.
2. An application for a permit revision
shall be reviewed by the director to determine
whether a new or updated CHIA shall be
required.
(10) Reclamation Plan—Postmining Land
Uses.
(A) Each plan shall contain a detailed
description of the proposed use following
reclamation of the land within the proposed
permit area, including a discussion of the
utility and capacity of the reclaimed land to
support a variety of alternative uses and the
relationship of the proposed use to existing
land use policies and plans. This description
shall explain—
1. How the proposed postmining land
use is to be achieved and the necessary support activities which may be needed to
achieve the proposed land use;
2. Where range or grazing is the proposed postmining use, the detailed management plans to be implemented;
3. Where a land use different from the
pre-mining land use is proposed, all materials
needed for approval of the alternative use
under 10 CSR 40-3.130; and
4. The consideration which has been
given to making all the proposed surface mining activities consistent with surface owner
plans and applicable state and local land use
plans and programs.
(B) The description shall be accompanied
by a copy of the comments concerning the
proposed use by the legal or equitable owner
of record of the surface of the proposed permit area and the state and local government
agencies which would have to initiate, implement, approve, or authorize the proposed use
of the land following reclamation.
(11) Reclamation Plan—Ponds, Impoundments, Banks, Dams, and Embankments.
(A) General. Each application shall include a general plan and a detailed plan for
each proposed siltation structure, water
impoundment, and coal processing waste
bank, dam, or embankment within the proposed mine plan area.
1. Each general plan shall—
A. Be prepared by, or under the direction of, and certified by a qualified registered
professional engineer with assistance from
experts in related fields such as land surveying and landscape architecture;
B. Contain a description, map, and
cross-section of the structure and its location;
C. Contain preliminary hydrologic
and geologic information required to assess
the hydrologic impact of the structure;
D. Contain a survey describing the
potential effect on the structure from subsidence of the subsurface strata resulting from
and Reclamation Operations and Coal Exploration
past underground mining operations if underground mining has occurred;
E. Contain a certification statement
which includes a schedule setting forth the
dates that any detailed design plans for structures that are not submitted with the general
plan will be submitted to the director. The
commission or director shall have approved,
in writing, the detailed design plan for a
structure before construction of the structure
begins; and
F. Contain the calculated theoretical
detention time and all supporting documentation and drawings used to establish the
required detention times under 10 CSR
40-3.040(6)(C)1. and 3.
2. Impoundments meeting the Class B
or C criteria for dams in TR-60, which is
incorporated by reference, shall comply with
the requirements of this section for structures
that meet or exceed the size or other criteria
of the Mine Safety and Health Administration
(MSHA). Each detailed design plan for a
structure that meets or exceeds the size or
other criteria of the MSHA, 30 CFR
77.216(a), shall—
A. Be prepared by, or under the direction of, and certified by a qualified registered
professional engineer with assistance from
experts in related fields such as geology, land
surveying, and landscape architecture;
B. Include any geotechnical investigation, design, and construction requirements
for the structure;
C. Describe the operation and maintenance requirements for each structure; and
D. Describe the timetable and plans
to remove each structure, if appropriate.
3. Each detailed design plan for a structure that does not meet the size or other criteria of 10 CSR 40-6.050(11)(A)2. shall—
A. Be prepared by, or under the direction of, and certified by a qualified registered
professional engineer and all coal processing
waste dams and embankments covered by 10
CSR 40-3.080(9)–(11) shall be certified by a
qualified registered professional engineer;
B. Include any design and construction requirements for the structure, including
any required geotechnical information;
C. Describe the operation and maintenance requirements for each structure; and
D. Describe the timetable and plans
to remove each structure, if appropriate.
(B) Siltation Structures. Siltation structures, whether temporary or permanent, shall
be designed in compliance with the requirements of 10 CSR 40-3.040(6). Any siltation
structure or earthen structure which will
remain on the proposed mine plan area as a
permanent water impoundment shall also be
designed to comply with the requirements of
10 CSR 40-3.040(10). Each plan, at a minimum, shall comply with the requirements of
the MSHA, 30 CFR 77.216-1, and 30 CFR
77.216-2.
(C) Permanent and Temporary Impoundments. Permanent and temporary impoundments shall be designed to comply with the
requirements of 10 CSR 40-3.040(10). Each
plan for an impoundment meeting the size or
other criteria of the Mine Safety and Health
Administration shall comply with the requirements of 30 CFR 77.216-1 and 30 CFR
77.216-2. The plan required to be submitted
to the district manager of MSHA under 30
CFR 77.216 shall be submitted to the director as part of the permit application in accordance with subsection (11)(A).
(D) Coal Processing Waste Banks. Coal
processing waste banks shall be designed to
comply with the requirements of 10 CSR 403.080(1)–(4).
(E) Coal Processing Waste Dams and
Embankments. Coal processing waste dams
and embankments shall be designed to comply with the requirements of 10 CSR 403.080(9)–(11). Each plan shall comply with
the requirements of the MSHA, 30 CFR
77.216-1, and 30 CFR 77.216-2 and shall
contain the results of a geotechnical investigation of the proposed dam or embankment
foundation area to determine the structural
competence of the foundation which will support the proposed dam or embankment structure and the impounded material. The
geotechnical investigation shall be planned
and supervised by an engineer or engineering
geologist, according to the following:
1. The number, location, and depth of
borings and test pits shall be determined
using current prudent engineering practice
for the size of the dam or embankment, quantity of material to be impounded, and subsurface conditions;
2. The character of the overburden and
bedrock, the proposed abutment sites, and
any adverse geotechnical conditions which
may affect the particular dam, embankment,
or reservoir site shall be considered;
3. All springs, seepage, and groundwater flow observed or anticipated during wet
periods in the area of the proposed dam or
embankment shall be identified on each plan;
and
4. Consideration shall be given to the
possibility of mudflows, rock-debris falls, or
other landslides into the dam, embankment,
or impounded material.
(F) If the structure meets the Class B or C
criteria for dams in TR-60, or meets the size
or other criteria of 30 CFR 77.216(a), each
plan under subsections (11)(B), (C), and (E)
of this rule shall include a stability analysis of
each structure. The stability analysis shall
include, but not be limited to, strength
parameters, pore pressures, and long-term
seepage conditions. The plan shall also contain a description of each engineering design
assumption and calculation with a discussion
of each alternative considered in selecting the
specific design parameters and construction
methods.
(12) Reclamation Plan—Surface Mining Near
Underground Mining. For surface mining
activities within the proposed permit area to
be conducted within five hundred feet (500')
of an underground mine, the application shall
describe the measures to be used to comply
with 10 CSR 40-3.070.
(13) Diversions. Each application shall contain descriptions, including maps and crosssections of stream channel diversions and
other diversions to be constructed within the
proposed permit area to achieve compliance
with 10 CSR 40-3.040(3) and (4).
(14) Protection of Public Parks and Historic
Places.
(A) For any public parks or historic places
that may be adversely affected by the proposed operations, each plan shall describe the
measures to be used to minimize or prevent
these impacts and obtain approval as required
in 10 CSR 40-5.010(3)(F).
(B) For any public parks or any places listed on the National Register of Historic Places
that may be adversely affected by the proposed operation, each plan shall describe the
measure to be used to prevent impacts, or if
valid existing rights exist, as determined
under 10 CSR 40-5.010(7), or joint agency
approval is to be obtained under 10 CSR 405.010(8)(D), to minimize adverse impacts.
(C) The director may require the applicant
or operator to protect historic or archaeological properties listed on or eligible for listing
on the National Register of Historic Places
through appropriate mitigation and treatment
measures prior to the commencement of any
specific mining operation which would affect
these properties.
(15) Relocation or Use of Public Roads. Each
application shall describe, with appropriate
maps and cross-sections, the measures to be
used to ensure that the interests of the public
and affected landowners are protected if,
under 10 CSR 40-5.010(5)(B), the applicant
seeks to have the commission or director
approve—
(A) Conducting the proposed surface mining activities within one hundred feet (100')
of the right-of-way line of any public road,
except where mine access or haul roads join
that right-of-way; or
(B) Relocating a public road.
(16) Disposal of Excess Spoil.
(A) Each application shall contain descriptions, including appropriate maps and crosssection drawings, of the proposed disposal
site and design of the spoil disposal structures
according to 10 CSR 40-3.060(1)–(4). These
plans shall describe the geotechnical investigation, design, construction, operation,
maintenance, and removal, if appropriate, of
the site and structures.
(B) Each application shall contain the
results of a geotechnical investigation of the
proposed disposal site, including the following:
1. The character of bedrock and any
adverse geologic conditions in the disposal
area;
2. A survey identifying all springs, seepage, and groundwater flow observed or anticipated during wet periods in the area of the
disposal site;
3. A survey of the potential effects of
subsidence of the subsurface strata due to
past and future mining operations;
4. A technical description of the rock
materials to be utilized in the construction of
those disposal structures containing rock
chimney cores or underlain by a rock
drainage blanket; and
5. A stability analysis including, but not
limited to, strength parameters, pore pressures, and long-term seepage conditions.
These data shall be accompanied by a
description of all engineering design assumptions and calculations and the alternatives
considered in selecting the specific design
specifications and methods.
(C) If, under 10 CSR 40-3.060(1)(I), rocktoe buttresses or key way cuts are required,
the applicant shall include the following:
1. The number, location, and depth of
borings or test pits which shall be determined
with respect to the size of the spoil disposal
structure and subsurface conditions; and
2. Engineering specifications utilized to
design the rock-toe buttress or key way cuts
which shall be determined in accordance with
paragraph (16)(B)5. of this rule.
(17) Transportation Facilities.
(A) Each application shall contain a
detailed description of each road, conveyor,
or rail system to be constructed, used, or
maintained within the proposed permit area.
The description shall include a map, appropriate cross-sections, and the following:
1. Design drawings and specifications
for each road width, road gradient, road surface, road cut, fill embankment, culvert,
bridge, drainage ditch, low water crossings,
and drainage structure;
2. A report of appropriate geotechnical
analysis, where approval of the commission or
director is required for alternative specifications or for steep cut slopes under 10 CSR 403.140(1)(D), (3)(C), (8)(D), or (10)(C) or 10
CSR 40-3.290(3)(C), (8)(D), or (10)(C);
3. A description of measures to be taken
to obtain approval for alteration or relocation
of a natural drainageway under 10 CSR 403.140(4)(D), (11)(D), or (18)(C) or 10 CSR
40-3.290 (4)(D), (11)(D), or (18)(C);
4. A description of measures, other than
use of a rock headwall, to be taken to protect
the inlet end of a ditch relief culvert, for
approval under 10 CSR 40-3.140(2)(C),
(9)(C), or (16)(C) and 10 CSR 403.290(2)(C), (9)(C), or (16)(C);
5. A general description of each road,
conveyor, or rail system to be constructed,
used, or maintained within the proposed mine
plan area shall be contained in each plan;
6. The drawings and specifications of
each proposed road that is located in the
channel of an intermittent or perennial stream
as necessary for approval of the road in
accordance with 10 CSR 40-3.140(2)(B),
(9)(B), and
(16)(B) and 10 CSR 403.290(2)(B), (9)(B), and (16)(B);
7. Drawings and specifications for each
low water crossing of perennial or intermittent stream channels indicating that the protection of the stream is maximized by the low
water crossings being designed, constructed,
and maintained to prevent erosion of the
structure or stream bed and additional contributions of suspended solids to stream flow;
8. The drawings and specifications for
each proposed ford of perennial or intermittent streams that are used as a temporary
route, as necessary for approval of the ford by
the regulatory authority in accordance with
10 CSR 40-3.140(4)(A) or (11)(A); and
9. Descriptions of the plans to remove
and reclaim each road that would not be
retained under an approved postmining land
use and the schedule for this removal and
reclamation.
(B) Class I and II Road Certification. The
plans and drawings for each Class I and II
road shall be prepared by, or under the direction of, and certified by a qualified registered
professional engineer, experienced in the
design and construction of roads, as meeting
the requirements of this chapter; current,
prudent engineering practices; and any design
criteria established by the regulatory authority.
(18) Support Facilities. Each applicant for a
surface coal mining and reclamation permit
shall submit a description, plans, and drawings for each support facility to be constructed, used, or maintained within the proposed
permit area. The plans and drawings shall
include a map, appropriate cross-sections,
design drawings, and specifications sufficient
to demonstrate compliance with 10 CSR 403.140(23) for each facility.
AUTHORITY: section 444.530, RSMo 2000.*
Original rule filed Oct. 12, 1979, effective
Feb. 11, 1980. Amended: Filed April 14,
1980, effective Aug. 11, 1980. Amended:
Filed Dec. 10, 1980, effective April 11, 1981.
Amended: Filed Jan. 5, 1987, effective July
1, 1987. Amended: Filed Dec. 15, 1987,
effective April 1, 1988. Amended: Filed Jan.
4, 1989, effective April 1, 1989. Amended:
Filed March 2, 1989, effective May 15, 1989.
Amended: Filed May 2, 1989, effective Aug.
1, 1989. Amended: Filed July 3, 1990, effective Nov. 30, 1990. Amended: Filed May 15,
1992, effective Jan. 15, 1993. Amended:
Filed Sept. 15, 1994, effective April 30,
1995. Amended: Filed March 21, 2000, effective Oct. 30, 2000. Amended: Filed Dec. 17,
2012, effective July 30, 2013.
*Original authority: 444.530, RSMo 1971, amended 1983,
1990, 1993, 1995.