10 CSR 45-8.010
General
PURPOSE: This rule lists the basic technical
issues expected to be addressed in a completed application for a Metallic Minerals Waste
Management Permit and references other
rules containing technical information.
(1) The closure and inspection-maintenance
plans shall establish and explain the technical
processes and steps proposed to accomplish
and maintain closure. Issues expected to be
addressed shall include, but should not be
limited to:
(A) The design, construction, and maintenance of waste control structures, tailings
dams, waste stockpiles, and supporting facilities;
(B) The characterization of waste products;
(C) The methods for control and protection
of surface water;
(D) The methods for protection of groundwater and aquifers;
(E) The geology and seismicity of the area;
(F) The potential for subsidence;
(G) The reuse and off-site removal of
wastes; and
(H) The surface reclamation of waste management areas.
(2) Consistent with section 444.362, RSMo
and 10 CSR 45-6.020, the owner/operator
shall comply with the appropriate technical
requirements, standards, and guidelines published in the rules of other state and federal
environmental programs. Supplemental guidelines for preparation, review, and approval of
closure and inspection-maintenance plans
are—
(A) 10 CSR 45-8.020 Groundwater Protection;
(B) 10 CSR 45-8.030 Metallic Minerals
Waste Management Control Structures; and
(C) 10 CSR 45-8.040 Reclamation-Reuse.
AUTHORITY: sections 444.362 and 444.380,
RSMo 2016.* Original rule filed Oct. 2, 1990,
effective April 29, 1991. Amended: Filed
March 26, 2018, effective Nov. 30, 2018.
*Original authority: 444.362, RSMo 1989 and 444.380,
RSMo 1989, amended 1993, 1995.