20 CSR 4240-22.070
Resource Acquisition Strategy Selection
PURPOSE: This rule requires the utility to
select a preferred resource plan, develop an
implementation plan, and officially adopt a
resource acquisition strategy. The rule also
requires the utility to prepare contingency
plans and evaluate the demand-side resources
that are included in the resource acquisition
strategy.
(1) The utility shall select a preferred
resource plan from among the alternative
resource plans that have been analyzed pursuant to the requirements of 4 CSR 24022.060. The utility shall describe and document the process used to select the preferred
resource plan, including the relative weights
given to the various performance measures
and the rationale used by utility decisionmakers to judge the appropriate tradeoffs
between competing planning objectives and
between expected performance and risk. The
utility shall provide the names, titles, and
roles of the utility decision–makers in the
preferred resource plan selection process.
The preferred resource plan shall satisfy at
least the following conditions:
(A) In the judgment of utility decisionmakers, strike an appropriate balance
between the various planning objectives specified in 4 CSR 240-22.010(2);
(B) Invest in advanced transmission and
distribution technologies unless, in the judgment of the utility decision-makers, investing
in those technologies to upgrade transmission
and/or distribution networks is not in the
public interest;
(C) Utilize demand-side resources to the
maximum amount that comply with legal
mandates and, in the judgment of the utility
decision-makers, are consistent with the public interest and achieve state energy policies;
and
(D) In the judgment of the utility decisionmakers, the preferred plan, in conjunction
with the deployment of emergency demand
response measures and access to short-term
and emergency power supplies, has sufficient
resources to serve load forecasted under
extreme weather conditions pursuant to 4
CSR 240-22.030(8)(B) for the implementation period. If the utility cannot affirm the
sufficiency of resources, it shall consider an
alternative resource plan or modifications to
its preferred resource plan that can meet
extreme weather conditions.
(2) The utility shall specify the ranges or
combinations of outcomes for the critical
uncertain factors that define the limits within
which the preferred resource plan is judged to
be appropriate and explain how these limits
were determined. The utility shall also
describe and document its assessment of
whether, and under what circumstances,
other uncertain factors associated with the
preferred resource plan could materially
affect the performance of the preferred
resource plan relative to alternative resource
plans.
(3) The utility shall describe and document
its quantification of the expected value of better information concerning at least the critical
uncertain factors that affect the performance
of the preferred resource plan, as measured
by the present value of utility revenue requirements. The utility shall provide a tabulation
of the key quantitative results of that analysis
and a discussion of how those findings will be
incorporated in ongoing research activities.
(4) The utility shall describe and document
its contingency resource plans in preparation
for the possibility that the preferred resource
plan should cease to be appropriate, whether
due to the limits identified pursuant to 4 CSR
240-22.070(2) being exceeded or for any
other reason.
(A) The utility shall identify as contingency resource plans those alternative resource
plans that become preferred if the critical
uncertain factors exceed the limits developed
pursuant to section (2).
(B) The utility shall develop a process to
pick among alternative resource plans, or to
revise the alternative resource plans as necessary, to help ensure reliable and low cost service should the preferred resource plan no
longer be appropriate for any reason. The
utility may also use this process to confirm
the viability of contingency resource plans
identified pursuant to subsection (4)(A).
(C) Each contingency resource plan shall
satisfy the fundamental objective in 4 CSR
240-22.010(2) and the specific requirements
pursuant to 4 CSR 240-22.070(1).
(5) Analysis of Load-Building Programs. If
the utility intends to continue existing loadbuilding programs or implement new ones, it
shall analyze these programs in the context of
one (1) or more of the alternative resource
plans developed pursuant to 4 CSR 24022.060(3) of this rule, including the preferred
resource plan selected pursuant to 4 CSR
240-22.070(1). This analysis shall use the
same modeling procedure and assumptions
described in 4 CSR 240-22.060(4). The utility shall describe and document—
(A) Its analysis of load building programs,
including the following elements:
1. Estimation of the impact of loadbuilding programs on the electric utility’s
summer and winter peak demands and energy usage;
2. A comparison of annual average rates
in each year of the planning horizon for the
resource plan(s) with and without the loadbuilding program;
3. A comparison of the probable environmental costs of the resource plan(s) in
each year of the planning horizon with and
without the proposed load-building program;
4. A calculation of the performance
measures and risk by year; and
5. An assessment of any other aspects of
the proposed load-building programs that
affect the public interest; and
(B) All current and proposed load-building
programs, a discussion of why these programs are judged to be in the public interest,
and, for all resource plans that include these
programs, plots of the following over the
planning horizon:
1. Annual average rates with and without the load-building programs; and
2. Annual utility costs and probable
environmental costs with and without the
load-building programs.
(6) The utility shall develop an implementation plan that specifies the major tasks, schedules, and milestones necessary to implement
the preferred resource plan over the implementation period. The utility shall describe
and document its implementation plan, which
shall contain—
(A) A schedule and description of ongoing
and planned research activities to update and
improve the quality of data used in load analysis and forecasting;
(B) A schedule and description of ongoing
and planned demand-side programs and
demand-side rates, evaluations, and research
activities to improve the quality of demandside resources;
(C) A schedule and description of all supply-side resource research, engineering,
retirement, acquisition, and construction
activities, including research to meet expected environmental regulations;
(D) Identification of critical paths and
major milestones for implementation of each
demand-side resource and each supply-side
resource, including decision points for committing to major expenditures;
(E) A description of adequate competitive
procurement policies to be used in the acquisition and development of supply-side
resources;
(F) A process for monitoring the critical
uncertain factors on a continuous basis and
reporting significant changes in a timely fashion to those managers or officers who have
the authority to direct the implementation of
contingency resource plans when the specified limits for uncertain factors are exceeded;
and
(G) A process for monitoring the progress
made implementing the preferred resource
plan in accordance with the schedules and
milestones set out in the implementation plan
and for reporting significant deviations in a
timely fashion to those managers or officers
who have the authority to initiate corrective
actions to ensure the resources are implemented as scheduled.
(7) The utility shall develop, describe and
document, officially adopt, and implement a
resource acquisition strategy. This means that
the utility’s resource acquisition strategy shall
be formally approved by an officer of the utility who has been duly delegated the authority to commit the utility to the course of action
described in the resource acquisition strategy.
The officially adopted resource acquisition
strategy shall consist of the following components:
(A) A preferred resource plan selected pursuant to the requirements of section (1) of this
rule;
(B) An implementation plan developed
pursuant to the requirements of section (6) of
this rule; and
(C) A set of contingency resource plans
developed pursuant to the requirements of
section (4) of this rule and identification of
the point at which the critical uncertain factors would trigger the utility to move to each
contingency resource plan as the preferred
resource plan.
(8) Evaluation of Demand-Side Programs and
Demand–Side Rates. The utility shall describe
and document its evaluation plans for all
demand-side programs and demand-side rates
that are included in the preferred resource
plan selected pursuant to 4 CSR 24022.070(1). Evaluation plans required by this
section are for planning purposes and are separate and distinct from the evaluation, measurement, and verification reports required by
4 CSR 240-3.163(7) and 4 CSR 24020.093(7); nonetheless, the evaluation plan
should, in addition to the requirements of this
section, include the proposed evaluation
schedule and the proposed approach to achieving the evaluation goals pursuant to 4 CSR
240-3.163(7) and 4 CSR 240-20.093(7). The
evaluation plans for each program and rate
shall be developed before the program or rate
is implemented and shall be filed when the
utility files for approval of demand-side programs or demand-side program plans with
the tariff application for the program or rate
as described in 4 CSR 240-20.094(3). The
purpose of these evaluations shall be to develop the information necessary to evaluate the
cost-effectiveness and improve the design of
existing and future demand-side programs
and demand-side rates, to improve the forecasts of customer energy consumption and
responsiveness to demand-side programs and
demand-side rates, and to gather data on the
implementation costs and load impacts of
demand-side programs and demand-side rates
for use in future cost-effectiveness screening
and integrated resource analysis.
(A) Process Evaluation. Each demand-side
program and demand-side rate that is part of
the utility’s preferred resource plan shall be
subjected to an ongoing evaluation process
which addresses at least the following questions about program design.
1. What are the primary market imperfections that are common to the target market
segment?
2. Is the target market segment appropriately defined, or should it be further subdivided or merged with other market segments?
3. Does the mix of end-use measures
included in the program appropriately reflect
the diversity of end-use energy service needs
and existing end-use technologies within the
target market segment?
4. Are the communication channels and
delivery mechanisms appropriate for the target market segment?
5. What can be done to more effectively overcome the identified market imperfections and to increase the rate of customer
acceptance and implementation of each enduse measure included in the program?
(B) Impact Evaluation. The utility shall
develop methods of estimating the actual load
impacts of each demand-side program and
demand-side rate included in the utility’s preferred resource plan to a reasonable degree of
accuracy.
1. Impact evaluation methods. At a minimum, comparisons of one (1) or both of the
following types shall be used to measure program and rate impacts in a manner that is
based on sound statistical principles:
A. Comparisons of pre-adoption and
post-adoption loads of program or demandside rate participants, corrected for the
effects of weather and other intertemporal
differences; and
B. Comparisons between program and
demand-side rate participants’ loads and
those of an appropriate control group over the
same time period.
2. The utility shall develop load-impact
measurement protocols that are designed to
make the most cost-effective use of the following types of measurements, either individually or in combination:
A. Monthly billing data, hourly load
data, load research data, end-use load
metered data, building and equipment simulation models, and survey responses; or
B. Audit and survey data on appliance
and equipment type, size and efficiency levels, household or business characteristics, or
energy-related building characteristics.
(C) The utility shall develop protocols to
collect data regarding demand-side program
and demand-side rate market potential, participation rates, utility costs, participant
costs, and total costs.
AUTHORITY: sections 386.040, 386.250,
386.610, and 393.140, RSMo 2000.* This
rule originally filed as 4 CSR 240-22.070.
Original rule filed June 12, 1992, effective
May 6, 1993. Amended: Filed Oct. 25, 2010,
effective June 30, 2011. Moved to 20 CSR
4240-22.070, effective Aug. 28, 2019.
*Original authority: 386.040, RSMo 1939; 386.250,
RSMo 1939, amended 1963, 1967, 1977, 1980, 1987,
1988, 1991, 1993, 1995, 1996; 386.610, RSMo 1939; and
393.140, RSMo 1939, amended 1949, 1967.