19 MAC Pt. 7, R. 16.04
Requirements
Cite as 19 Miss. Admin. Code Pt. 7, R. 16.04
Requirements
A. Testing of newly installed liquefied petroleum gas piping systems shall be conducted as
a “pressure test” in compliance with the provisions of NFPA 54, Chapter 8, paragraph
8.1 and its subparagraphs (2024) (Pressure Testing and Inspection).
B. Testing of liquefied petroleum gas piping systems that are already approved for service
shall be conducted through use of the procedures for a “leak check”, which shall
constitute the necessary pressure test described in Senate Bill 2787 (2026) when
performed in the manner specified by NFPA 54, Chapter 8, paragraph 8.2 and its
subparagraphs, as well as NFPA 54, Annex C(3)(2)(a) through (c) (2024). Leak checks
must also be in compliance with the provisions of Title 19 Mississippi Administrative
Code, Part 7, Chapter 14 (Leak Check Procedures and Requirements).