26 MAC Pt. 2, Ch. 1, R. 1.27
APPLICATION TO PLUG
Cite as 26 Miss. Admin. Code Pt. 2, Ch. 1, R. 1.27
APPLICATION TO PLUG. Any drilling well completed as a dry hole, from
which the rig is to be moved away, shall be mudded and cemented, provided, however, that
authorization to the contrary has not been given by the Board.
Before any work is commenced to abandon any well drilled for the discovery of oil or gas,
the owner or operator thereof shall give written notice to the Board of his intent to abandon such
well on Form No. 6, along with a proposed procedure for plugging said well, prior to beginning
operations of plugging said well. Upon receipt of such notice, the Board may issue plugging
permit and may send a duly authorized representative to the location specified to be present at
the time indicated in such notice, to witness the plugging of such well. In the case of an
emergency, the application may be made orally or by telegraph, and the Supervisor may orally or
by telegraph authorize the work; however, written application must be filed within five (5) days
after emergency authorization is given even though the work has already been commenced or
completed and a written permit shall be issued which shall contain the emergency authorization.
Plugging operations shall begin within 120 days of approval of the Form 6 and shall proceed
with due diligence until completed, however, an extension of time may be granted by the Board
for good cause shown upon public notice and hearing.
No surface or production casing shall be pulled from any abandoned well without first filing
Form No. 6 and upon completion of said work, report on Form No. 7 the manner in which the
well was plugged and the amount of pipe pulled.