33 MAC Pt. 14
Drinking Water Systems Improvements Revolving Loan Fund Program Regulations DW SRF
Cite as 33 Miss. Admin. Code Pt. 14
STATE OF MISSISSIPPI
LOCAL GOVERNMENTS AND RURAL WATER SYSTEMS IMPROVEMENTS BOARD
Title 33: Public Health - Local Governments & Rural Water Systems Improvements Board
Part 14: Drinking Water Systems Improvements Revolving Loan Fund Program Regulations DW SRF
Lead Service Line Replacement Intended Use Plan
STATE OF MISSISSIPPI
DRINKING WATER SYSTEMS IMPROVEMENTS
REVOLVING LOAN FUND PROGRAM
BIL LEAD SERVICE LINE REPLACEMENT
INTENDED USE PLAN FOR FFY-2022
AMENDED 2026
Approved by the Board
4/24/2026
LOCAL GOVERNMENTS AND RURAL WATER SYSTEMS
IMPROVEMENTS BOARD
P. O. BOX 1700 SUITE U-232
JACKSON, MISSISSIPPI 39215-1700
(Blank)
STATE OF MISSISSIPPI
LOCAL GOVERNMENTS AND RURAL WATER SYSTEMS IMPROVEMENTS BOARD
Title 33: Public Health - Local Governments & Rural Water Systems Improvements Board
Part 14: Drinking Water Systems Improvements Revolving Loan Fund Program Regulations DW SRF
Lead Service Line Replacement Intended Use Plan
DRINKING WATER SYSTEMS IMPROVEMENTS REVOLVING LOAN FUND
BIL LEAD SERVICE LINE REPLACEMENT
INTENDED USE PLAN FOR FFY-2022
TABLE OF CONTENTS
I.
A.
B.
C.
II.
GOALS OF MISSISSIPPI’S DRINKING WATER SYSTEMS IMPROVEMENTS
A.
1.
2.
A.
B.
1.
2.
C.
1.
2.
3.
4.
V.
A.
B.
C.
A.
1.
2.
3.
C.
D.
APPENDICES I
APPENDIX A FUNDS REPORT ............................................................................................................. II
APPENDIX B - PROJECTED SCHEDULE OF OUTLAYS FOR BIL LSLR CAPITALIZATION
GRANT SET-ASIDES ............................................................................................................................. III
APPENDIX C - PROJECTED PAYMENT (FEDERAL LETTER OF CREDIT) SCHEDULE ..... IV
APPENDIX D - PROJECTED SCHEDULE OF DRAWDOWNS AGAINST FEDERAL LETTER
OF CREDIT (ACH DRAW SCHEDULE) ............................................................................................. V
APPENDIX E – LEAD LINE INVENTORY WORKPLAN ................................................................ VI
APPENDIX F - MISSISSIPPI STATE PROGRAM MANAGEMENT SET-ASIDE ANNUAL
WORK PLAN VIII
APPENDIX H – INFRASTRUCTURE INVESTMENT AND JOBS ACT ......................................... XI
Amendment to the FFY-2022 BIL Lead Service Line Replacement Intended Use Plan
Since approval of the FFY-2022 Lead Service Line Replacement (LSLR) Intended Use Plan, no
projects have advanced to loan execution under the LSLR capitalization grant. The Mississippi
State Department of Health (MSDH) has determined that the existing application and priority
ranking process described in the FFY-2022 IUP has limited participation in the program,
particularly for small and rural water systems seeking assistance with lead service line
inventories.
To address this issue and facilitate implementation of the FFY-2022 LSLR capitalization grant,
the Department is amending this IUP to revise the project application process, expand principal
forgiveness incentives for inventory activities, and implement targeted outreach to eligible public
water systems.
These amendments are intended to support the obligation of available funds and advance the
objectives of the Bipartisan Infrastructure Law (BIL) Lead Service Line Replacement program.
I.
INTRODUCTION
A. State of Mississippi’s Drinking Water State Revolving Loan Fund
The Safe Drinking Water Act Amendments of 1996 (SDWA) established the national
Drinking Water State Revolving Fund (DWSRF) Program. The Bipartisan Infrastructure
Law (BIL), also known as the Infrastructure Investment and Jobs Act (IIJA) of 2021, (P.L.
117-8) additionally amended Section 1452 of the SDWA and appropriated funds for Lead
Service Line Replacement. This Intended Use Plan identifies the State of Mississippi’s
proposed use of Federal Fiscal Year (FFY) 2022 DWSRF Lead Service Line Replacement
(LSLR) allotment of $30,518,000.
The DWSRF program allows the Environmental Protection Agency (EPA) to make
capitalization (Cap) grants to states to, in turn, provide low-cost loans to public water
systems to help achieve or maintain compliance with SDWA requirements. Accordingly,
the State Legislature (through Section 41-3-16, MS Code of 1972 Annotated) created what
is now called the Drinking Water Systems Improvements Revolving Loan Fund
(DWSIRLF) Program, to receive the federal DWSRF capitalization grants from EPA, and
to provide low-cost loans to the state’s public water systems to finance needed
infrastructure improvements. This legislation also allows the DWSIRLF, subject to the
authority of State Law, to make loans that may utilize additional subsidization beyond
standard DWSIRLF loans as well as setting appropriate criteria to determine eligible
recipients.
That same legislation created the "Local Governments and Rural Water Systems
Improvements Board" (Board), to oversee the administration of the DWSIRLF Program.
The Mississippi State Department of Health (Department), as the state’s drinking water
primacy agency, supplies the staff and facilities necessary to administer the program. The
Board is composed of the following nine (9) members: the State Health Officer, who shall
serve as chairman of the Board; the Executive Director of the Mississippi Development
Authority; the Executive Director of the Department of Environmental Quality; the
Executive Director of the Department of Finance and Administration; the Executive
Director of the Mississippi Association of Supervisors; the Executive Director of the
Mississippi Municipal League; the Executive Director of the American Council of
Engineering Companies; the State Director of the United States Department of Agriculture,
Rural Development; and a manager of a rural water system. Each agency director may
appoint a designee to serve in his or her place on the Board. The Governor appoints the
rural water system manager. In the creation of the Program, it was the intent of the
Legislature that the Board endeavor to ensure that the costs of administering the DWSIRLF
Program are as low as possible in order to provide the water consumers of Mississippi with
safe drinking water at affordable prices.
As a condition of receiving the DWSRF Cap grants, the SDWA requires that each state
annually prepare an Intended Use Plan (IUP) designed to outline how a state will utilize
DWSRF funds to assist in protecting public health.
The DWSIRLF BIL LEAD SERVICE LINE REPLACEMENT (LSLR) Fund consists of
federal funds. Federal funds are provided to the states in the form of awarded Cap grants.
Each state’s allotment of those grants is based on EPA’s Needs Survey that is performed
every four years. No State matching funds are required to be deposited into this Fund.
B. Program Overview
The basic framework under which the DWSIRLF Program operates is established by two
documents. The first document is the Drinking Water State Revolving Fund Loan Program
Operating Agreement (Operating Agreement) between the Mississippi State Department
of Health and the Environmental Protection Agency, Region IV. The current Operating
Agreement was agreed to by both parties and approved on March 21, 2022. The Operating
Agreement establishes the basic framework of the DWSIRLF that is not expected to change
from year-to-year. The second document is the IUP which describes how the State of
Mississippi will use the funding received from the EPA Cap grant which is received each
year. The original BIL LSLR IUP for FFY-2022 was dated June 29, 2023 and accompanied
the Program’s application to EPA for the FFY-2022 LSLR Cap Grant.
The amount of the FFY-2022 EPA Cap Grant for the BIL LSLR fund is $30,518,000. The
Program intends to apply for set-asides as described in Section V. These funds must be
used in the period of July 2023 through June 2026. As a condition of the FFY-2022 Cap
Grant the program agrees to comply with DWSRF regulations, the general grant
regulations at 40 CFR part 200, and specific conditions of the capitalization grant and to
enter data into SRF Data System no less than quarterly. This IUP describes in detail the
goals (overall and five-year), the structure, and the financial status of the Program; the role
of the set-aside activities within the state; and the distribution of funds toward public water
system improvement projects and the criteria used to determine their ranking within the
priority system. Those desiring to receive a copy of this document may contact Jonathan
Diaz, Program Support Specialist, at (601) 576-7518.
C. Public Input, Review, and Comment Procedures
To ensure that the public has an ample opportunity to review and comment upon the IUP,
the Department and the Board follows the requirements of the “Mississippi Administrative
Procedures Law” prior to final submission of the IUP to EPA. A public notice period of at
least twenty-five (25) days allows for review and comment before an oral proceeding.
After adoption by the Board, a second filing with the Secretary of State’s Office occurs; if
no additional comments are received the IUP becomes law 30 days after the second filing.
Public notice will be given in The Clarion Ledger, a newspaper of statewide circulation,
for written and oral comments on this IUP. An oral proceeding is scheduled for 9:00 a.m.
on July 28, 2023. A transcript of the oral proceeding, recording any comments and
recommended solutions, will be submitted to the EPA along with the Final IUP. Those
desiring to receive a copy of the oral proceeding transcript should contact Jonathan Diaz,
Program Support Specialist, at (601) 576-7518. A copy of the “Mississippi Administrative
Procedures Law” may be obtained from the Mississippi Secretary of State’s Office and can
also be found on the Mississippi State Department of Health’s website at
www.healthyms.com/dwsrf.
II.
Goals of Mississippi’s Drinking Water Systems Improvements Revolving Loan Fund
(DWSIRLF) Program – LSLR Fund
The LSLR Fund was created by the BIL to provide funding through the DWSIRLF
Program for a five-year duration. Overall and Five-Year Goals for the LSLR Fund include:
A. Overall Goal:
Improve public health by providing funding and technical support to public water systems
in Mississippi for the removal of lead materials in drinking water service lines and related
activities.
B. Five-Year Goals:
1. Improve public health by providing technical support to small (less than 10,000
population) public water systems in Mississippi for the completion of lead service line
inventories. This goal can lead into providing capital project funding for the removal
of lead service lines identified during these inventories.
2. Provide funding and technical support to public water systems in Mississippi in
planning for full, not partial, lead service line replacement. This helps to address the
equity challenge that for some property owners, the cost to replace their portion of lead
service lines is prohibitively high1.
3. Improve program participation by reducing administrative and technical barriers for
public water systems, particularly small and rural systems, seeking assistance for lead
service line inventory and replacement activities.
4. Facilitate implementation of lead service line inventory and replacement activities by
allowing flexible funding approaches that align with system capacity while maintaining
compliance with federal and state requirements.
III.
Structure of the Mississippi DWSIRLF
The Mississippi DWSIRLF BIL LSLR is structured around one fund. The portion of the
fund designated for projects will consist of 49% principal forgiveness. The balance of the
1 USEPA, Combined SRF Implementation of BIL Memo, March 8, 2022
project fund will be repaid. This will sustain the Base DWSIRLF program and help it to
achieve its respective goals. The funds are broken down further into designated accounts,
each having a specific function.
A. DWSIRLF BIL LSLR Loan/Operations Fund
Monies in the Fund support a majority of the functions of the DWSIRLF LSLR. These
functions include program administration, set-aside operations, and most importantly
provide disbursements to public water systems for eligible projects. The DWSIRLF LSLR
is a reimbursement program, meaning that after the loan is awarded, costs associated with
planning, designing, and constructing the project are reimbursed to the recipient. Cap
grants from EPA will be deposited into this Fund’s account.
1. Types of Eligible Projects:
Lead Service Line Replacement projects and associated activities directly
connected to the identification, planning, design, and replacement of lead service
lines are eligible for funding by the Program. 100% of lead service lines must be
replaced for lead service line projects, including privately and publicly-owned
portions of the line.
Eligible activities may include lead service line inventory, planning, design, and
full replacement of lead service lines. The Department may implement multiple
funding approaches for these activities in order to improve participation by public
water systems and facilitate completion of program objectives.
Public water systems that have identified known lead service lines or galvanized
requiring replacement (GRR) through prior reporting shall prioritize projects that
include full replacement of those service lines. Inventory activities may be included
as part of such projects where necessary to support final project scope and
implementation.
100% of the service line replaced is defined by replacing pipes up to the point of
premise plumbing. The portion of the service line that is DWSIRLF-eligible (refer
to Figure 1) is the entire service line from the public water main to the point at
which it connects with premise plumbing. Premise plumbing is defined as piping
on the other side of the isolation valve. That connection may be inside or outside
of homes and buildings. Note that premise plumbing is not eligible for DWSIRLF
funding.
The DWSIRLF Program could consider whether reasonable cost for repair to the
private-owned structure, if damaged during privately-owned LSL replacement, is
eligible for DWSIRLF funding.
Source: EPA, Addressing Lead in Drinking Water with the DWSRF, 816-F-18-005, March 2019.
2. Set-aside Accounts:
The set-aside accounts reside under the umbrella of the Fund and are distinctly
designated by reporting categories. A listing of the set-asides taken by Mississippi
includes the following as part of the FFY-2022 IUP:
a. Administrative Set-aside: Provides financial support to administer the LSLR
loan Program and other non-project-related activities.
b. Small System Technical Assistance Set-aside: Provides technical assistance to
small water systems.
c. State Program Management Set-aside: Provides additional financial support to
MSDH – Bureau of Public Water Supply for Public Water System Supervision
Program – Lead and Copper Revised Rule.
d. Local Assistance and Other State Programs: Provides funding for small
systems to inventory their systems in support of identifying potential lead
service lines for replacement.
IV.
Financial Status of the DWSIRLF
This section outlines all sources of funding available to the DWSIRLF LSLR Program
and indicates intended uses. This section also describes the financial assistance terms
available through the Program.
A. Source and Use of Funds
Using the FFY-2022 BIL LSLR Capitalization Grant allotment for Mississippi of
$30,518,000 to provide for both loans and set-aside activities.
The “set-asides” use for the FFY-2022 BIL LSLR Cap grant are outlined in Section V of
this IUP. Necessary work plans showing utilization of these funds are found in the
appendices of this IUP.
B.
Financial Planning Process
In accordance with the goals of the LSLR fund of the DWSIRLF Program, the Board has
made the following financial decisions regarding the Fund:
1. Application for the Full Amount of the BIL LSLR Cap Grant
The Board intends that the MSDH apply for the full amount of the State LSLR Cap
grant allotment under the federal DWSRF, including the set-asides described in
Section V below. No State match is required for the FFY-2022 LSLR Cap grant.
2. Interest Rate Determination
It is the Board’s decision to offer 0% interest on DWSIRLF loans from the BIL
LSLR fund.
C. Financial Terms of Loans
The following terms will be used for the purpose of making loans to the public water
systems within the State of Mississippi.
1. Funding Limit
Under state law, the Board has the discretion to set the maximum amount for
DWSIRLF loans. For FFY-2022 IUP, the Board has set a maximum loan amount
of $5,000,000 per borrower. The Board may allow (on a case-by-case basis if
requested by the borrower and the need has been justified) the maximum loan limit
to be exceeded by a vote of the Board. Furthermore no more than one loan per
borrower will be allowed. At the end of the fiscal year, if funds are available,
systems previously receiving an award may obtain an additional award(s) or an
increase to a previous award, if no other eligible systems are evident.
2. Interest Rate
Terms for BIL LSLR loans will be 0% interest rate, with repayment periods as
follows:
1. For Lead Service Line Inventory project loans, a standard five-year repayment
term, with the maximum repayment term of 10 years. The reason for the shorter
repayment terms is that these projects are not capital projects and do not
improve or build a physical asset owned by the water system.
2. For Lead Service Line Replacement project loans, a standard 20-year
repayment term. The maximum loan amortization allowable will be 30 years,
or 40 years for disadvantaged communities. These maximums may not,
however, exceed the design life of the project.
Interest will accrue based on the current loan agreement in conjunction with the
DWSIRLF Regulations.
3. FFY-2022 BIL LSLR Cap Grant Special Provisions
The FFY-2022 BIL LSLR Cap Grant requires 49% subsidization of the BIL LSLR
Cap Grant Amount. This subsidization is expected to be in the form of “principal
forgiveness”, “negative interest rates,” or a combination of the two.
4. Other Related Issues
a. Type of Assistance Provided: The assistance to be provided under the
DWSIRLF Program will be loans to public, tax-exempt entities which are
authorized under state law to collect, treat, store, and distribute piped water for
human consumption; able to enter into a DWSIRLF loan agreement; and have
the ability to repay the DWSIRLF loan. With the funds provided through the
FFY-2022 BIL LSLR Cap Grant, the DWSIRLF program will be able to make
loans that will have an amount of “principal forgiveness.” The amount of
principal forgiveness for the BIL LSLR FFY-2022 Cap Grant is 49% of the
total Cap Grant. The Board has set a limit of 70% of the requested loan amount
which a loan recipient may receive in subsidy for one loan. Once the limit of
the appropriation subsidy funds has been reached for the FFY-2022 Cap Grant,
loans will return to the DWSIRLF’s standard terms without principal
forgiveness. In all cases, loans will be LSLR projects and associated activities
directly connected to the identification, planning, design, and replacement of
LSLs.
b. Project Costs Eligibility: Eligible/allowable project costs will include those
costs that are eligible, reasonable, necessary, and allocable to the project, within
the established project scope and budget, in conformance with the DWSIRLF
regulations and approved by MSDH.
c. Loan Participation: DWSIRLF loan participation will be at 100% of eligible
project costs, less any funding made available from other agencies for these
same eligible project costs.
d. Pre-Award Costs: Project costs incurred prior to loan award will be DWSIRLF
loan eligible provided:
i.
The debt is for work that has begun after the DWSIRLF loan award date.
ii.
The project is in compliance with all applicable DWSIRLF Program
regulations and obtains MSDH approval of all applicable documents
prior to award of the DWSIRLF loan.
iii.
The prospective loan recipient agrees that by incurring costs prior to
loan award, it proceeds at its own risk and relieves the Board, the
Department, and the Department’s staff of all responsibility and liability
should such costs later be determined unallowable for any reason or
should such funding not become available for any reason.
iv.
The prospective loan recipient agrees that by incurring costs prior to
loan award, no future commitment of funding a refinanced project is
provided.
e. Priority List: The LSLR Priority List for the FFY-2022 IUP expires on
January 2, 2024. Projects listed in the FFY-2022 LSLR Priority List that did
not receive funding by this date may be reconsidered for funding through the
revised application and selection processes described in this IUP.
Because the Priority List expired on January 2, 2024 and no projects have been
funded under the FFY-2022 LSLR capitalization grant, the Department may
add additional projects to the planning portion of the Priority List through the
revised application process described in Section VI.E.
Projects identified through this process may be added to the Priority List and
funded to ensure the obligation of available funds and achievement of the
program objectives.
5. Principal Forgiveness for Lead Service Line Inventory Projects
The Department has determined that limited participation in the LSLR program has
prevented the obligation of FFY-2022 LSLR funds. To encourage participation by
eligible water systems, the Department may prioritize principal forgiveness for lead
service line inventory projects.
Inventory projects may receive principal forgiveness up to 100 percent of eligible
project costs, particularly for small systems and disadvantaged communities, in order
to encourage participation in the program and improve the accuracy of lead service
line inventories statewide. The Department may implement varying approaches to
providing principal forgiveness for inventory activities based on system size, project
scope, and program priorities.
Principal forgiveness for construction projects involving lead service line replacement
will continue to follow the methodology currently outlined in this IUP, with a
maximum principal forgiveness of 70 percent of eligible project costs based on the
median household income (MHI) of the service area. Public water systems with
known lead service lines or galvanized requiring replacement (GRR) are expected to
prioritize replacement activities consistent with program requirements.
The Department will administer principal forgiveness in a manner that maintains
compliance with the federal requirement that at least 49 percent of the capitalization
grant be provided as additional subsidy.
V.
Set-Aside Activities
The SDWA allows each state to set-aside up to 31 percent of its federal Cap grant to support
non-project-related drinking water programs which includes administration of the loan
program, technical assistance to public water systems, state program management, and
other special activities. The FFY-2022 LSLR Capitalization Grant amount of $30,518,000,
the state plans to use $5,523,060 of the FFY-2022 LSLR Capitalization grant to support
set-aside activities, further defined in the following Sections A through D. These non-
project-related programs will be operated by MSDH within the agency itself or through
contracts with other agencies or organizations. Contracts between the MSDH and other
agencies or organizations will be approved by the Board. Work plans showing how the
set-asides funds will be expended are included as appendices within this LSLR IUP;
additionally, progress reports will be included in the Annual Report.
A. Administration
The SDWA-DWSRF amendments in the 2017 Water Infrastructure Improvements
for the Nation Act (Pub. L. 114-332) (2017 WIIN Act – EPA memorandum dated
June 6, 2017) states that the Administrative Set-Asides that can be taken the greatest
of: $400,000, 1/5 percent of the current valuation of the fund, or an amount equal
to 4 percent of all grant awards to the fund for the fiscal year. The EPA Combined
SRF BIL Implementation Memo dated March 8, 2022 states that set-asides for the
LSLR Cap Grant are consistent with the DWSRF regulations. The State plans to
use the maximum allowable (4%) for "Administrative" purposes from the FFY-
2022 LSLR Cap Grant.
The state will continue to exercise its right to reserve the administrative amounts
from previous Cap Grants. Reserving previous years’ 4% administrative set-aside
can ensure that the Program will continue to operate with an adequate DWSIRLF
staff for proper management of the Program.
B. Small System Technical Assistance
The state will use the Small Systems Technical Assistance (up to 2%) set-aside
from the BIL LSLR FFY-2022 Cap Grant to provide funding for LSL inventories
to small water systems. With approval by the Board, the state may use this set-aside
to support lead service line inventory activities for small systems, including those
that require assistance to complete or update inventory information.
The Department may implement targeted approaches to assist small systems,
including the use of standardized scopes of work, procurement documents, and
technical requirements to facilitate completion of lead service line inventories,
consistent with applicable state and federal procurement requirements.
This assistance will be made available in a manner determined by the Department
to best support participation by small and disadvantaged systems, consistent with
federal program objectives and program requirements. More detail is provided in
the State of Mississippi’s Set-Aside Work Plan included as Appendix E to this IUP.
C.
State Program Management
The state intends to use the full 10% set-aside from the FFY-2022 LSLR Cap grant,
as authorized by Section 1452(g) (2) of the Safe Drinking Water Act of 1996 for
State Program Management related to LCRR and LSLR. The funds will be used
for Public Water System Supervision (PWSS) activities conducted under Section
1443(a) of the Act. However, a work plan for these activities is still being
developed.
D. Local Assistance and Other State Programs
The state intends to use the Local Assistance and Other State Programs set-aside
from the FFY-2022 BIL LSLR Cap grant to provide funding for lead service line
inventory activities for eligible public water systems.
The Department may implement multiple approaches for providing this assistance,
including targeted assistance for small systems and broader funding opportunities
for other eligible systems. These approaches may include grouping of similar
activities where appropriate, use of standardized procurement and contract
documents, and varying procurement methods based on project size and scope,
consistent with applicable state and federal procurement requirements.
Assistance may be provided through contracts, direct support, system-procured
services, or other mechanisms determined by the Department to facilitate timely
and effective completion of lead service line inventories.
Systems that have identified known lead service lines or galvanized requiring
replacement (GRR) are expected to pursue projects that include replacement
activities, although inventory updates may be included as necessary to support
those projects.
This assistance will be made available in a manner determined by the Department
to best support participation, equitable distribution of funds, and completion of
program objectives. The State of Mississippi’s Set-aside Work Plan is included as
Appendix E
VI.
Priority System
The SDWA provides the state with the flexibility to determine how to best utilize the LSLR
Cap grant. To meet the goals of public water systems in the State of Mississippi and this
FFY-2024 LSLR IUP, the Department may utilize multiple approaches to identify and fund
eligible projects. Projects which meet the following will be given priority:
1. Address the most serious risk to human health related to lead in service lines and
associated activities directly connected to the identification, planning, design and
replacement of lead service lines.
2. Assist systems most in need, on a per household basis.
A. Funding and Ranking Rationale
Projects will be placed on the fundable portion of the Priority List according to both priority
ranking and readiness to proceed. The term “ready to proceed” means that all loan
application requirements established in the Program regulations are met, and all documents
necessary for loan award are approved. If a project cannot reasonably be expected to meet
the Priority System deadlines, then the project will not be placed on the current year’s
Priority List but will be placed on the Planning List. It is the Board’s judgment with input
from the DWSIRLF staff as to when a project is ready to proceed. Loans will be awarded
to projects (within available funds) that are above the funding line on the current year’s
Priority List, that have met all Priority System deadlines and are ready to proceed.
Additionally, when potential loan recipients are deciding on the needs for their public water
supplies, they should ensure that all public health and state safe drinking water laws are
followed.
The Department may implement different evaluation and selection approaches for eligible
projects depending on project type, including lead service line inventory activities and lead
service line replacement projects. For inventory-focused projects, evaluation may consider
factors such as the number of service lines with unknown material, the proportion of
unknown service lines within the system, median household income, and readiness to
proceed. In evaluating projects, the Department may consider lead service line inventory
data available at the time of application or project development, including the number and
proportion of service lines with unknown material or identified lead or galvanized requiring
replacement.
Public water systems that have identified known lead service lines or galvanized requiring
replacement (GRR) are expected to pursue projects that include replacement activities.
Inventory work for such systems may be included where necessary to support project
development and implementation
1. Funding Lists and Bypass Procedure
Should any projects on the FFY-2024 LSLR Priority List (which are above the
funding line) fail to comply with the deadlines in Section D, the project shall be
bypassed, and the funds reserved for said project will be released. Released funds
will first be made available to listed projects, to ensure that all projects above the
funding line meeting priority system deadlines are funded. Any remaining funds
will be made available to the highest-ranking project(s) shown below the funding
line that is ready for loan award at the time funds become available. If no projects
above the funding line are ready for loan award at the time funds become available,
projects shown below the funding line will be funded on a first-come, first-served
basis as they become ready for loan award and until the released funds are awarded.
This same process will continue as each deadline passes and released funds become
available.
2. Loan Decreases
Any funds recovered from loan decreases during the year will be used:
a) first to fund bid overruns, if funds from the loan increase reserve are not
sufficient to cover the bid overruns;
b) then to ensure that all projects above the funding line meeting the priority
system deadlines are funded (for at least the amount shown on the priority list);
and
c) then to fund other loans and/or increases on a first-come, first-served basis.
Any funds not obligated for these purposes may be made available for new loan
awards ready to proceed on a first-come, first-served basis.
3. Subsidization from FFY-2022 LSLR Cap Grant
49% of the FFY-2022 LSLR Cap Grant will be subsidized. Based on the Grant of
$30,518,000, the required amount of subsidization is $14,953,820. The
DWSIRLF’s subsidization will be in the form of “Principal Forgiveness” (PF) to
individual public water supplies that are considered disadvantaged communities,
and which received reimbursements with Federal LSLR Cap Grant funds during
the lifetime of the project, from loan initiation through loan closeout. If the amount
of PF which a project is eligible exceeds the amount of Federal LSLR Cap grant
funds which it received, the amount of PF extended will be limited to the amount
of Federal Cap grant funds used for reimbursement.
Subsidization may be used over a two-year period. Subsidization remaining from
a previous year may be awarded to loans which are eligible for PF over a two-year
period. Subsidization for FFY-2024 LSLR Priority List projects may be awarded
to projects eligible for PF in FFY-2025 and FFY-2026.
Disadvantaged Community Program
a. DWSRF LSLR Capitalization Grant Funds
During FFY-2024, the following Principal Forgiveness (PF) methodology will
be used to meet the requirements of the BIL (P.L. 117-8) for providing subsidy
for disadvantaged systems. For the LSLR fund, 49% will be subsidized. The
FFY-2022 LSLR federal appropriation for the Program is $30,518,000. The
principal forgiveness (49%) allowable to eligible borrowers is $14,953,820.
The amount of PF for which a potential “Loan Recipient” (LR) may be eligible
will be determined by calculating the percentage of the “Median Household
Income” (MHI) of the potential LR versus the MHI of the State of Mississippi
($54,915) as a whole.
90% < LR MHI < 100%
- 49% Principal Forgiveness
80% < LR MHI < 90%
- 56% Principal Forgiveness
70% < LR MHI < 80%
- 63% Principal Forgiveness
LR MHI < 70%
- 70% Principal Forgiveness
PF will be extended to projects until all mandated subsidy funds are obligated.
Due to the limited amount of PF funds, the maximum amount of PF funds a
loan recipient may receive for a project will be 70% of the project budget, which
is capped at $5,000,000. The amount of PF given will be assigned at loan award.
Once subsidy funds are depleted, only standard loans will be made with
DWSIRLF funds.
In the event that a LR declines their loan that includes PF, the released PF may
be reallocated to other projects for the present fiscal year that are eligible for
PF, or the PF may be carried over to projects for the next fiscal year.
If returned PF funds are reallocated to projects awarded during the existing
fiscal year. The reallocation of PF will be given first to projects which did not
receive their full allowable amount based on the above table up to the maximum
allowed limit.
In all cases, the amount of PF which is awarded to a project may not exceed the
amount of Federal Cap grant funds which the project was reimbursed during
the construction of the project.
B.
Priority System Categories
DWSRF LSLR Priority System
Project Categories applicable to the DWSRF Base/Supplemental IUP that have been
eliminated from this LSLR IUP because they are not applicable are Categories I
through II and IV through XII. Projects for the LSLR Priority List will be ranked from
Categories III through XIII in priority order; that is, all Category III projects are ranked
higher than subsequent category projects, etc. Ranking is established in like manner
for the remaining categories. Adjustments are made as necessary to comply with the
set-aside provisions of the Federal SDWA and as established by the Board [Section
1542(a) (2) of SDWA]. As stated previously, the order of Categories III - XIII is
intended to give highest priority to those projects that address the most serious risks to
human health. Projects within each category will be ranked as described in Section C.
All projects must meet the requirement of the LSLR Cap Grant appropriation; that they
are lead service line replacement projects or project activities directly connected to the
identification, planning, design, and replacement of lead service; for example, lead
service line inventory projects. 100% of lead service lines must be replaced for lead
service line projects, including privately and publicly-owned portions of the line.
1. Category III – Primary Drinking Water Standards
This category includes projects to facilitate compliance with Primary Drinking Water
Standards. To qualify for this category, projects must correct deficiencies resulting in
non-compliance with the primary drinking water standards.
2. Category XIII – Other
This category includes projects that do not meet the criteria of any other listed category
and have been determined LSLR loan eligible in accordance with the DWSIRLF
program regulations.
C. Priority Ranking Criteria
For certain project types, including lead service line inventory projects and projects
identified through the revised application process described in Section VI.E, the
Department may apply alternative evaluation methods that do not rely solely on the
Priority Ranking Criteria described in this section. These alternative methods may
consider factors such as the number and proportion of service lines with unknown
material, the presence of known lead or galvanized requiring replacement (GRR),
system capacity, and readiness to proceed
The criteria for ranking projects within each category is intended to give priority to
projects that: (1) benefit the most people per dollar expended; (2) assist systems most
in need on a per household affordability basis as required by the SDWA; (3) encourage
participation in short-term and long-term technical assistance programs; and (4)
encourage certifying and providing support for a system’s Asset Management Plan.
These considerations are addressed by the Priority Ranking Criteria in the following
manner:
1.
Benefit/Cost
Benefit/Cost points assigned to each project will be determined using the following
formula:
Benefit/Cost Points
=
Number of benefiting connections
Total eligible cost of improvements (in $1.0 millions)
The number of benefiting connections must be included in the facilities plan
submitted by the applicant; be defined as the sum of individual connections
currently experiencing deficiencies that will be corrected by the improvement;
and include only existing residences, businesses, and public buildings. Applicants
must furnish information (including hydraulic analysis, if necessary) to support
their estimate of the number of benefiting connections. The total eligible cost is in
millions of dollars (i.e., $800,000 = $0.8 M).
2. Affordability Factor
An affordability factor will be assigned to each project to reflect the relative needs
of applicants on a per household basis. The Benefit/Cost points calculated in
Section C.1. will be adjusted using the affordability factor in the following formula:
Adjusted Benefit/Cost Points = (Affordability Factor) x (Benefit/Cost Points)
The affordability factor used in the calculation is defined as the ratio of the “Median
Household Income” (MHI) for the State of Mississippi ($54,915) to the MHI for
the affected community. The affordability factor used in the calculation will be no
less than 1.0 and no greater than 1.5.
3. Participation in Short-Term & Long-Term Assistance Programs
The MSDH, with the Board’s approval, has contracted with Mississippi State
University Extension Service to provide both short-term and long-term assistance
to designated water systems in the state based on their scores on the latest Capacity
Assessment Form (CAF). This assistance is provided at no cost to the water
systems.
Participation by the water systems in these assistance programs is voluntary;
however, any water system that has participated in either of these assistance
programs within the past two years will be eligible to receive additional priority
points equal to 5% of their Adjusted Benefit/Cost Points. Water systems that have
implemented all the recommendations made by Mississippi State University
Extension Service will receive additional priority points equal to 5% of their
Adjusted Benefit/Cost Points for a total of 10%. Documentation of participation in
either of these assistance programs and implementation of the recommendations
made by Mississippi State University Extension Service must be included in the
facilities plan before additional priority points will be granted.
Assistance Points = ** x (Adjusted Benefit/Cost Points)
** 5% if the water system participates in the assistance, or 10% if the
water system participates in the assistance and implements all
recommendations
4. Asset Management Plan
Any water system certifying and providing support of their Asset Management
Plan’s implementation or maintenance to MSDH will be eligible to receive
additional priority points equal to 10% of their Adjusted Benefit/Cost Points.
Asset Management Plan = 0.10 x (Adjusted Benefit/Cost Points)
7. Ranking Within Each Category
Within each category, projects will be ranked in order based on the total points
assigned the project using the following formula:
Total Priority Points = Adjusted Benefit/Cost Points + Affordability Points +
Assistance Program Points + Asset Management Plan Points
Projects receiving the most priority points will be given the highest ranking on the
Priority List. In case of a tie in the number of priority points, projects with the
lowest median household income will receive the highest ranking.
D. Priority System Deadlines
1. Those that have submitted Request for Ranking: by January 2, 2024, a complete
DWSIRLF facilities plan, prepared in accordance with the DWSIRLF loan program
regulations, must be submitted to MSDH.
A complete DWSIRLF facilities plan includes: all Intergovernmental Review
(IGR) agency comments; proof of publication of advertisement for public hearing;
a transcript of the public hearing comments; copies of any comments received from
the public; and a summary of how each comment was addressed. The loan
applicant should provide a copy of the facilities plan to USDA - Rural Utilities
Service (RUS); if the loan applicant has an existing debt with RUS, their approval
to incur the additional debt must be obtained and provided as part of the plan.
Any significant changes made to the facilities plan (i.e., changes in the chosen
alternative location of the facility, cost increases that substantially affect the
financial capability of the loan recipient) after this date will be considered a first
submittal of the facilities plan. The loan applicant will then be in violation of the
Priority System deadline and the project will be placed on the planning portion of
the priority list. If the change is made after adoption of the IUP, funds reserved for
this project may be released and made available to other projects.
2. By May 1, 2024, a completed DWSIRLF loan application and all associated
documents as described in the DWSIRLF regulations must be submitted to the
Department. Prior to preparing these documents, the potential applicant and/or its
registered engineer must request and receive a DWSIRLF application and
guidance. It is recommended that they request a pre-application conference with
DWSIRLF staff as early in the application process as practical. This deadline also
applies to all projects competing for released funds during FFY-2024 and to be able
to qualify for the Previous Year Certified Projects Category in the FFY-2024 IUP.
3. By August 1, 2024, all approvable documents and responses to comments necessary
for loan award must be submitted to the Department for its review and approval.
E. Revised Application Process for LSLR Projects
Since approval of the FFY-2022 LSLR Intended Use Plan, no projects have advanced
to loan execution under the existing Priority System. The Department has determined
that the standard DWSIRLF facilities plan and loan application process has limited
participation in lead service line inventory and replacement activities, particularly for
small and rural water systems.
To address this issue and facilitate implementation of the FFY-2022 LSLR
capitalization grant, the Department may implement a revised application process for
LSLR projects.
For lead service line inventory projects, the Department may waive or modify certain
application requirements, including the submission of a full facilities plan, where
appropriate. Applications may be submitted through an alternative or simplified
process developed by the Department.
Inventory project applications may be evaluated based on factors including the
number of service lines with unknown material, the proportion of unknown service
lines, median household income, and readiness to proceed.
Public water systems that have identified known lead service lines or galvanized
requiring replacement (GRR) are expected to pursue projects that include replacement
activities. Inventory updates may be included as part of such projects where
necessary.
Projects funded through this process must meet all eligibility requirements established
by the Safe Drinking Water Act and the Bipartisan Infrastructure Law.
VII. FFY-2022 LSLR PRIORITY LIST
Implementation of Priority List:
The FFY-2022 LSLR Priority List remains part of this Intended Use Plan. However, due to limited participation under the
original application and ranking process, the Department may utilize revised application and funding approaches as
described in this IUP to identify and fund additional eligible projects.
Projects not included on the original Priority List may be added to the planning portion of the Priority List and funded, as
necessary, to support program implementation and achieve the objectives of the FFY-2022 LSLR capitalization grant, in
accordance with applicable state and federal requirements.
Fiscal Year - 2022 Mississippi Drinking Water Systems Improvements Revolving Loan Fund Program
Priority List – BIL Lead Service Line Replacement
Project
Project Description
Zip
Code
Priority
Points
Service
Area
Population
Eligible
PF
Amount
Loan
Amount
Request
Statewide
Cum. $
Category XIII: Other
Waveland, City of
Survey and Identify Lead Service Lines
39576
26250
$90,000
$200,000
$200,000
Bay St. Louis, City of
Survey and Identify Lead Service Lines
39520
12316
$37,500
$250,000
$450,000
Kiln Utility and Fire District
Survey and Identify Lead Service Lines
39556
$22,500
$150,000
$600,000
FMH Water Assoc.
Surveying & Inventory of Lead Service Lines
38756
$72,000
$160,000
$760,000
Lorman Waterworks Assoc.
Surveying & Inventory of Lead Service Lines
39096
$56,250
$125,000
$885,000
CS&I Water Assoc.
Surveying & Inventory of Lead Service Lines
39150
$24,750
$55,000
$940,000
McNair-Stampley Waterworks
Surveying & Inventory of Lead Service Lines
39069
$72,000
$160,000
$1,100,000
Renshaw Water Assoc.
Surveying & Inventory of Lead Service Lines
39194
$11,700
$26,000
$1,126,000
Ebenezer Water Assoc.
Surveying & Inventory of Lead Service Lines
39095
$18,000
$40,000
$1,166,000
South Holmes Water Assoc.
Surveying & Inventory of Lead Service Lines
39146
$29,250
$65,000
$1,231,000
South Sunflower Water Assoc.
Surveying and Inventorying Lead Service Line
38753
$31,500
$70,000
$1,301,000
Hermanville Community Water
Surveying & Inventory of Lead Service Lines
39086
$31,500
$70,000
$1,371,000
Midway Community Water
Surveying & Inventory of Lead Service Lines
39039
$56,250
$0 $1,496,000
Romola Water Assoc.
Surveying & Inventory of Lead Service Lines
39150
$18,000
$40,000
$1,536,000
Pilgrim Rest Water Assoc.
Surveying & Inventory of Lead Service Lines
39232
$11,250
$25,000
$1,561,000
Project
Project Description
Zip
Code
Priority
Points
Service
Area
Population
Eligible
PF
Amount
Loan
Amount
Request
Statewide
Cum. $
Category XIII: Other
Greenville, City of
Replacement of Lead Service Lines
38701
30000
$500,000 $2,266,275
$3,827,275
Acona Water Assoc.
Surveying & Inventory of Lead Service Lines
39095
$45,000
$100,000
$3,927,275
Pearl, City of
Surveying & Inventory of Lead Service Lines
39288
$0 $1,500,000
$5,427,275
Natchez Waterworks
Surveying & Inventory of Lead Service Lines
39120
$500,000 $1,350,000
$6,777,275
Copiah Water Assoc.
Surveying & Inventory of Lead Service Lines
39083
$131,250
$375,000
$7,152,275
Union Church Waterworks Assoc. Surveying & Inventory of Lead Service Lines
39668
$36,000
$0
$7,232,275
Double Ponds Water Assoc.
Surveying & Inventory of Lead Service Lines
39474
$72,000
$160,000
$7,392,275
Black Bayou Water Assoc.
Surveying & Inventory of Lead Service Lines
38756
$191,250
$425,000
$7,817,275
L&F Water Assoc.
Surveying & Inventory of Lead Service Lines
39117
$40,500
$90,000
$7,907,275
ACL Water Assoc.
Surveying & Inventory of Lead Service Lines
39145
$0
$160,000
$8,067,275
North Hinds Water Assoc.
Surveying & Inventory of Lead Service Lines
39071
$0
$500,000
$8,567,275
Central Yazoo Water Assoc.
Surveying & Inventory of Lead Service Lines
39194
$148,750
$425,000
$8,992,275
Southeast Rankin Water Assoc.
Surveying and Inventorying Lead Service Line
39051
$0
$250,000
$9,242,275
Providence Water Assoc.
Surveying & Inventory of Lead Service Lines
39090
$45,500
$130,000
$9,372,275
Evergreen Water Assoc.
Surveying & Inventory of Lead Service Lines
39043
$0
$175,000
$9,547,275
Taylorsville Water Assoc.
Surveying and Inventorying Lead Service Line
39043
$0
$100,000
$9,647,275
Eagle Lake Water District
Surveying & Inventory of Lead Service Lines
39812
$35,000
$100,000
$9,747,275
C & C Water Assoc.
Surveying & Inventory of Lead Service Lines
39094
$35,000
$100,000
$9,847,275
Hwy 28 Water Assoc.
Surveying & Inventory of Lead Service Lines
39111
$31,500
$90,000
$9,937,275
H&H Water Assoc.
Surveying & Inventory of Lead Service Lines
39080
$61,250
$175,000 $10,112,275
East Madison Water Assoc.
Surveying & Inventory of Lead Service Lines
39046
$157,500
$450,000 $10,562,275
Taylorsville, Town of
Surveying and Inventorying Lead Service Line
39168
$43,750
$125,000 $10,687,275
Port Gibson, Town of
Survey & Inventory Lead Service Lines
39150
$135,414
$300,920 $10,988,195
Pisgah Water Assoc.
Surveying & Inventory of Lead Service Lines
39161
$0
$150,000 $11,138,195
Willow Grove Water Assoc.
Surveying and Inventorying Lead Service Line
39428
$31,250
$125,000 $11,263,195
Topisaw Creek Water Assoc.
Surveying and Inventorying Lead Service Line
39662
$41,250
$275,000 $11,538,195
Southern Rankin Water Assoc.
Surveying and Inventorying Lead Service Line
39073
$52,500
$210,000 $11,748,195
Mize, Town of
Surveying & Inventory of Lead Service Lines
39116
$14,000
$40,000 $11,788,195
Lake City Water Assoc.
Surveying & Inventory of Lead Service Lines
39071
$31,250
$125,000 $11,913,195
Yokena Jeff Davis
Surveying and Inventorying Lead Service Line
39180
$35,000
$140,000 $12,053,195
Project
Project Description
Zip
Code
Priority
Points
Service
Area
Population
Eligible
PF
Amount
Loan
Amount
Request
Statewide
Cum. $
Category XIII: Other
Union Water Assoc.
Surveying and Inventorying Lead Service Line
39151
$600
$40,000 $12,093,195
Star Water Company
Surveying and Inventorying Lead Service Line
39167
$0
$75,000 $12,168,195
Sylvarena Water Assoc.
Surveying and Inventorying Lead Service Line
39153
$17,500
$50,000 $12,218,195
Braxton, Town of
Surveying & Inventory of Lead Service Lines
39044
$22,500
$50,000 $12,268,195
Goshen Water Assoc.
Surveying & Inventory of Lead Service Lines
39051
$0
$25,000 $12,293,195
Vicksburg, City of
Survey & Inventory Lead Service Lines
38701
29238
$190,895 $2,483,640 $14,776,835
Puckett, Town of
Surveying & Inventory of Lead Service Lines
39151
$12,500
$50,000 $14,826,835
Winterville Water Assoc.
Surveying and Inventorying Lead Service Line
38703
$11,250
$25,000 $14,851,835
Senatobia Lakes Estates
Surveying & Inventory of Lead Service Lines
38668
$8,750
$25,000 $14,876,835
Bay Springs, Town of
Surveying & Inventory of Lead Service Lines
39422
$450,000 $1,000,000 $15,876,835
Wiggins, City of
Inventory Lead Service Lines
39577
$250,000 $1,000,000 $16,876,835
Clarkdale Water Assoc.
Replacement of Lead Service Lines
39301
$500,000 $2,066,000 $18,942,835
Harland Creek Water Assoc.
Replacement of Lead Service Lines
39095
$500,000 $2,484,300 $21,427,135
Jackson, City of
Replacement of Lead Service Lines
39216
150000
$500,000 $5,000,000 $26,427,135
Mount Olive, Town of
Surveying and Inventorying Lead Service Lines
39119
$450,000 $1,000,000 $27,427,135
Fayette, City of
Surveying & Inventory of Lead Service Lines
39069
$56,250
$125,000 $27,552,135
Collins, City of
Surveying and Inventorying Lead Service Lines
39428
$175,000
$500,000 $28,052,135
VIII. EXPECTED PUBLIC HEALTH OUTCOMES & PERFORMANCE MEASURES
The objective of this program is to disperse all available loan and grant funds in a timely
manner to achieve the public health protection benefits resulting from the projects
identified in the FFY-2022 LSLR IUP, and to ensure compliance with loan agreements, as
required by state and federal laws and regulations.
Because no projects have yet been funded under the FFY-2022 LSLR capitalization grant,
the Department will track additional performance indicators to evaluate program
implementation.
These measures include:
• number of public water systems applying for lead service line inventory funding
• number of assistance agreements executed for LSLR projects
• amount of FFY-2022 LSLR funds obligated
• number of service lines with unknown material identified and/or resolved
through inventory activities
• number of lead service lines and galvanized requiring replacement (GRR)
addressed through funded projects
The success of the DWSIRLF Program will be defined by the ability of the MSDH to
successfully meet commitments in the FFY-2022 LSLR IUP and Set-Aside Work Plan.
Additionally, the majority of the projects as proposed should have minimal impact on the
environment due to the nature of their design. Where necessary, appropriate environmental
reviews will occur and proper permitting through the Mississippi Department of
Environmental Quality will be required to ensure minimal impact on the environment.
APPENDICES
APPENDIX A
DRINKING WATER SYSTEMS IMPROVEMENTS REVOLVING LOAN FUND PROGRAM - LEAD LINE REPLACEMENT
ANTICIPATED FUNDS REPORT - June 1, 2023
FFY-2022 Funding (Federal and State)
National Title I DWSRF Appropriation - Mississippi's Allotment
+
$30,518,000
State Match Required (20% of Mississippi's Allotment)
+
$0
2022 Capitalization Grant for BIL LSLR
=
$30,518,000
State Match Status
State Match Required
+
$0
2023 Legislated State Match
-
$0
Remaining State Match Required
=
$0
2022 Cap Grant Set-Asides
DWSRF Administration [SDWA Sec. 1452(g)(2) - either $400,000, 1/5 % of the fund's
current valuation, or up to 4% of the award]
+
$135,000
Small Systems Technical Assistance [SDWA Sec. 1452(g)(2) - 2%]
+
$610,360
Local Assistance and Other State Program [SDWA Sec. 1452(k)(2) - 15%]
+
$4,577,700
State Program Management [SDWA Sec. 1452(g)(2) -10%]
+
$0
Total 2022 Cap Grant Set-Asides
=
$5,323,060
2022 Cap Grant Funds Available for Loan Obligation
2022 DWSRF Capitalization & BIL Supplemental Grants
+
$30,518,000
2022 Cap Grant Set-asides
-
($5,323,060)
Total Cap Grant Funds Available for Loan Obligation
=
$25,194,940
Funds Anticipated to be Available for Loan Awards
Cap Grant Federal and State Funds Anticipated to be Available for Loan Obligation
+
$25,194,940.
Unobligated Funds Carried Over
+
$0.00
Loan Increase Reserve
-
$0.00
Total Funds Anticipated to be Available for Loan Awards
=
$25,194,940
Funds Needed for Projects on the FFY-2022 Priority List & FFY-2023 & After
Planning List
Funds Needed for Projects on the Priority List and FFY-2023 & After Planning List
+
$28,052,135
Funds Anticipated to be Available for Loan Awards
-
($25,194,940)
Total Fund Need Remaining for Projects on the Priority List and FFY-2023 & After Planning List
=
$2,857,195
APPENDIX B - PROJECTED SCHEDULE OF OUTLAYS
FOR BIL LSLR CAPITALIZATION GRANT SET-ASIDES
FFY 2024 BIL LSLR Cap Grant
Federal Set-Asides
FFY 2024 Q1
FFY 2024 Q2
FFY 2024 Q3
FFY 2024 Q4
Totals
Administrative
$33,750
$33,750
$33,750
$33,750
$135,000
Small System Tech Assist.
$152,590
$152,590
$152,590
$152,590
$610,360
State Program Management.
$1,144,425
$1,144,425
$1,144,425
$1,144,425
$4,577,700
Local Asst. & Other St. Programs
$0
$0
$0
$0
$0
Total:
$1,330,765
$1,330,765
$1,330,765
$1,330,765
$5,323,060
Appendix C - Projected Payment (Federal Letter of Credit) Schedule
(Schedule of Increases to ACH Ceiling)
FFY-2024
FFY-2022
Cap Grant
No. 1 of 4
1st Quarter
FFY-2024
$7,629,500
$7,629,500
FFY-2022
Cap Grant
No. 2 of 4
2nd Quarter
FFY-2024
$7,629,500
$15,259,000
FFY-2022
Cap Grant
No. 3 of 4
3rd Quarter
FFY-2024
$7,629,500
$22,888,500
FFY-2022
Cap Grant
No. 4 of 4
4th Quarter
FFY-2024
$7,629,500
$30,518,000
APPENDIX D - PROJECTED SCHEDULE OF DRAWDOWNS AGAINST FEDERAL
LETTER OF CREDIT
(ACH DRAW SCHEDULE)
FFY-2024
Outlay
Quarter
Federal Outlay
Amount
Cumulative Outlay
Amount
1st Quarter
$7,629,500
$7,629,500
2nd Quarter
$7,629,500
$15,259,000
3rd Quarter
$7,629,500
$22,888,500
4th Quarter
$7,629,500
$30,518,000
APPENDIX E – Lead ServiceLine Inventory Workplan
INTRODUCTION
The Mississippi State Department of Health (MSDH), Bureau of Public Water Supply
(Department), will use the Small System Technical Assistance Set-Aside & Local
Assistance and Other State Programs Set-aside of the DWSRF LSLR in a Lead Service
Line Inventory Program. The program will be surveying the State’s drinking water system to
identify, plan, and assist water systems in inventorying their service line to identify lead
service lines for replacement projects.
SELECTION PROCESS
The contract for coordination of the program will run on a State Fiscal Year Basis. A
contract is currently being developed in accordance with State contracting requirements.
A Request for Qualifications will be advertised statewide. Qualifications received will be
reviewed by the Department to select the best qualified candidate for the agency.
Recommendations for award of a contract will be presented to the Board at their regularly
scheduled Board meeting; following authorization by the Board, the coordination contract
will be awarded.
PROGRAM ACTIVITIES
The state will use the Small Systems Technical Assistance and Local Assistance and Other
State Programs set-asides from the BIL LSLR FFY-2022 Cap Grant to support lead service
line inventory activities for eligible public water systems.
The Department may implement multiple approaches to deliver inventory services based on
system needs, project scope, and program priorities. These approaches may include the use of
Department-procured contracts, system-procured services, or other delivery methods
determined appropriate by the Department.
To facilitate efficient implementation, the Department may develop standardized scopes of
work, technical requirements, procurement documents, and reporting formats for use by
participating systems and contractors, consistent with applicable state and federal
procurement requirements.
The Department may group similar inventory activities into project packages where
appropriate to improve efficiency and cost-effectiveness. Project packages may vary in size
and complexity depending on system characteristics and inventory needs.
Funding levels for inventory activities may be developed using planning-level estimates,
including per-connection or per-meter cost assumptions, with final funding based on eligible
costs and procurement results.
Systems that have identified known lead service lines or galvanized requiring replacement
(GRR) are expected to pursue projects that include replacement activities. Inventory updates
may be included as necessary to support development and implementation of those projects.
The activities described herein will be accomplished through a structured process that may
include identification of eligible systems, coordination with public water systems,
development of inventory plans, execution of field activities, and submission of required data
and reporting consistent with program requirements.
Identification – The contractor will survey our priority list and/or communication with the
Program’s Project Management Staff or the Department’s Regional Engineers while
identifying the proper set-aside category to fund the potential inventory.
Communication – Staff from the contractor will meet with system officials to inform them
of the program, explain what Lead Line Inventories looks like for their system, and
encourage them to take advantage of funding through our program.
Mobilization – Once the communication phase has been completed and the system request
to move forward, staff of the contractor will mobilize to the selected site and commence with
the plan and inventory of the System’s service lines. Acceptable methods of inventory will be
determined and outlined by the Department to the contractor.
Confirmation – Staff of the contractor will provide the Program’s Project Management staff
with results and recommendations for a Lead Service Line Replacement Project.
SCHEDULE FOR COMPLETING ACTIVITIES
The schedule for completing Lead Line Inventory Program activities under this work plan
will be the schedule established by set contractual dates.
AGENCY RESPONSIBILITIES
The Program will be monitoring contractors throughout the process to ensure effective
completion of contractual assignments.
EVALUATION PROCESS TO ASSESS THE SUCCESS OF SET-ASIDE ACTIVITIES
The success of these set-asides will be defined by the ability of the MSDH through the
solicited contractor(s) to identify, plan, and assist water systems in Lead Line Inventories that
lead to Lead Line Replacement Projects to create safer drinking water for all consumers of
Mississippi’s drinking water.
APPENDIX F - MISSISSIPPI STATE PROGRAM MANAGEMENT
SET-ASIDE ANNUAL WORK PLAN
Section 1452(g)(2) - Safe Drinking Water Act Amendments of 1996
In Development
Appendix G - Certifications
In addition to the ten (10) assurances included below, the state acknowledges that there are six
(6) additional assurances that the state has agreed to in either the Operating Agreement between
the State and EPA Region IV or the annual capitalization grants. These two documents are
hereby incorporated into this IUP by reference.
1.
The state certifies that all drinking water facility projects in this IUP identified in Section
VII as being subject to the federal cross-cutting requirements are or will be in compliance
with all such requirements prior to the state entering into an assistance agreement with
the recipient.
2.
The state certifies that it will make an annual report to the Regional Administrator on the
actual uses of the funds and how the state has met the goals and objectives for the
previous two fiscal years as identified in the IUPs; and to annually have conducted an
independent audit of the funds to be conducted in accordance with generally accepted
government accounting standards.
3.
The state certifies that this IUP will be subjected to public review and comment prior to
final submission to EPA. The state certifies that it will follow the “Mississippi
Administrative Procedures Law” in seeking public review and comments on this IUP. A
copy of the “Mississippi Administrative Procedures Law” can be obtained from the
Mississippi Secretary of State’s Office and can be found on the Mississippi State
Department of Health’s website at www.healthyms.com/dwsrf.
An oral proceeding will be held to receive written and oral comments on this IUP. A
transcript of the public hearing recording the comments and recommended solutions will
be submitted to EPA along with the Final IUP. Anyone desiring to receive a copy of the
oral proceeding transcript should contact Jonathan Diaz, Program Support Specialist, at
(601) 576-7518 to request copies.
4.
The state certifies that all drinking water facility projects in this IUP are on the project
Priority List developed pursuant to the requirements of Section 1452(b)(3)(B), SDWA.
5.
The state certifies that it will enter into binding commitments for 120% of the amount of
each payment (LOC) under the capitalization grant within one year after receipt of each
payment (LOC).
6.
The state certifies that it will commit and expend all Drinking Water Systems
Improvements Revolving Loan Fund (DWSIRLF) Program monies as efficiently as
possible, and to disburse the funds in a timely and expeditious manner.
7.
The state certifies that it will conduct environmental reviews on all DWSIRLF cross-
cutter equivalency projects in accordance with the State Environmental Review Process
(SERP).
8.
The state certifies that prior to adding any new projects to the “FFY-2022 and After
Planning List” for the purpose of funding such a project during FFY-2022 that the state
will follow the “Mississippi Administrative Procedures Law” in amending this IUP to
allow for public review and comments.
9.
The state certifies that it has developed and implemented a Capacity Development (CD)
strategy to assist public water systems in acquiring and maintaining technical,
managerial, and financial capacity as required in Section 1420(c) of the 1996
Amendments to the SDWA. This CD program is currently approved by EPA.
10.
The state certifies the State’s Operator Certification Program is currently approved by
EPA.
APPENDIX H – INFRASTRUCTURE INVESTMENT AND JOBS ACT
Sections of the Infrastructure Investment and Jobs Act (H.R. 3684) that impact the Drinking
Water SRFs:
I.
Funding
The bill appropriates $30.713 billion for the Drinking Water State Revolving Funds
(SRFs) over five years. (This is actual funding.) (See Division J – Appropriations, Title
VI Department of Interior, Environment and Related Agencies, State and Tribal
Assistance Grants: Starts on page 2,565 of the bill.)
II.
Reauthorization & Policy
The bill includes The Drinking Water and Wastewater Infrastructure Act (S. 914) which
reauthorizes funding levels for the SRFs and amends SRF provisions in the Clean Water
Act and the Safe Drinking Water Act. (See Division E – Drinking Water and Wastewater
Infrastructure: Starts with Section 50001 on page 1,887 of the bill.)
III.
Buy America / Buy American
The bill expands domestic preference procurement provisions for programs across
government, including the SRFs. (See Division G – Other Authorizations, Title IX Build
America, Buy America: Starts with 70901 on page 2,303 of the bill.)
I.
Funding
The bill provides three pots of funding for SRFs over the next five years:
• Any Eligible Project:
o $11,713,000,000 for the Drinking Water SRF for any eligible project.
• Lead Remediation:
o $15 billion for the Drinking Water SRF for lead service line replacement,
including planning, identification, and design (includes inventories).
• Emerging Contaminants Remediation:
o $4 billion for remediation of emerging contaminants with a focus on PFAS/PFOA
for the Drinking Water SRF.
Key points for this supplemental appropriation:
• Funding is intended to be in addition to annual appropriations.
• Funding is available “until expended.”
• State match is not required for appropriations dedicated to lead service line replacement
and remediation of emerging contaminants.
• State match is 10% for 2022-2023 and 20% for 2024-2026 for appropriations for any
eligible project.
• 100% of the capitalization grant for emerging contaminants must be used for additional
subsidy. A flat 49% of the annual capitalization grant for any eligible project and lead
service line replacement must be used for additional subsidy.
• Additional subsidy must be provided in the form of assistance agreements with 100%
principal forgiveness or grants.
Year
Drinking Water SRF
Any Eligible Project
State
Match
Mandated
Additional
Subsidy
$1,902,000,000
10%
49%
$2,202,000,000
10%
49%
$2,403,000,000
20%
49%
$2,603,000,000
20%
49%
$2,603,000,000
20%
49%
Total
$11,713,000,000
Year
Drinking Water SRF
Emerging
Contaminants
State
Match
Mandated
Additional
Subsidy
$800,000,000
0%
100%
$800,000,000
0%
100%
$800,000,000
0%
100%
$800,000,000
0%
100%
$800,000,000
0%
100%
Total
$4,000,000,000
Year
Drinking Water SRF
Lead
State
Match
Mandated
Additional
Subsidy
$3,000,000,000
0%
49%
$3,000,000,000
0%
49%
$3,000,000,000
0%
49%
$3,000,000,000
0%
49%
$3,000,000,000
0%
49%
Total
$15,000,000,000
Total
$30,713,000,000
II.
Reauthorization & Policy
The bill includes The Drinking Water and Wastewater Infrastructure Act of 2021 (S.
914) which passed the U.S. Senate on Thursday, April 29, by a vote of 89 – 2 (9 not voting).
The bill contained the following provisions. (Policy provisions apply to annual
appropriations, not supplemental appropriations in the bill.)
Funding
• Reauthorizes Drinking Water SRFs at the same levels for the next five years:
o 2022: $2.4 billion
o 2023: $2.75 billion
o 2024: $3 billion
o 2025 and 2026: $3.25 billion
• Reauthorizes SWIFIA: $5 million annually for the next five years, 2022 through
2026.
Additional Subsidy
• Defines additional subsidization as “forgiveness of principal, grants, negative interest
loans, other loan forgiveness, and through buying, refinancing, or restructuring debt”
for both SRFs and excludes loans with 0% or higher interest are not additional from
being considered additional subsidy.
• Mandates minimum additional subsidy for as long as there are eligible applications:
o Drinking Water SRFs: Increases additional subsidy from 6% to 12% of the
capitalization grant for additional subsidy for disadvantaged communities.
III.
Buy America / Buy American
The legislation also expands domestic preference procurement requirements for SRF projects
from American Iron and Steel to construction materials and manufactured products.