33 MAC Pt. 1, R. 3.3.5
Construction/Repair Deficiencies
Cite as 33 Miss. Admin. Code Pt. 1, R. 3.3.5
Construction/Repair Deficiencies.
1. In the event construction/repair procedures, materials or equipment appear to the
Department staff to be substandard, otherwise unsatisfactory, and/or not in conformity
with approved plans and specifications, the Department staff may determine such work
unallowable for DWSELF loan participation, unless the loan recipient takes such action,
through the registered engineer if applicable, in the manner provided for in the
construction/repair contract to correct any such deficiencies
2. The Department staff may immediately begin withholding DWSELF loan payments
should such substandard or unsatisfactory construction/repair work, materials, or
equipment become apparent and may require the loan recipient to repay any previously
paid amounts related to such work, within 30 days of such notification. Interest may be
charged on such delinquent repayments after expiration of the 30-day period at the rate
established in Section III.E.(6) of this regulation. Alternatively, the Department staff may
withhold such amounts from subsequent payment requests.
3. In addition to normal testing procedures required of the loan recipient, should questions
arise concerning the construction work, materials, or equipment, for DWSELF loan
allowability purposes the Department staff may request the loan recipient to perform
reasonable additional tests of construction materials, equipment, or processes which the
Department staff determines to be necessary to answer such questions during or after the
construction of the project. All tests, whether for the Department staff or the registered
engineer, must conform to current American Water Works Association, American
Association of State Highway and Transportation Officials, or American Society of
Testing and Materials published procedures, or similar acceptable criteria. The
Department staff will specify which tests are applicable, if not described in the approved
plans, specifications, and contract documents, for DWSELF loan allowability purposes.
Samples for testing must be furnished free of cost to the Department staff upon request at
the construction site.