33 MAC Pt. 1, R. 3.3.9
Construction Phase Submittals, Approvals, and Actions
Cite as 33 Miss. Admin. Code Pt. 1, R. 3.3.9
Construction Phase Submittals, Approvals, and Actions.
The following submittals, approvals, and actions will be required during the construction phase
of the project. The Department staff may establish other time frames within the loan agreement
when properly justified.
3.3.9.1 Within 30 days after the original loan offer all local funds necessary for the project must
be secured and proof of such must be submitted, to the Department.
3.3.9.2 Within 60 days after the original loan offer (1) the loan recipient must execute and submit
to the Department a copy of any remaining unexecuted contracts for
construction/repair/equipment/supplies and engineering planning/design and construction phase
services, or (2) if required by State law, must advertise, receive bids, award, execute and submit
any other contracts for construction/repairs/equipment included in the project, and must issue any
remaining notices to proceed, begin remaining construction/repair work, purchase any remaining
equipment/supplies funded under the loan agreement and transmit a copy of all notices to
proceed to the Department staff, and (3) if any contracts must be bid, a completed loan agreement
amendment request, as required by Section III.B.(5) of this regulation must be submitted.
3.3.9.3 By the date established in the loan agreement, the loan recipient must (1) meet with the
Department to discuss the findings of the financial capability analysis and agree to a schedule for
implementing the findings of this analysis and (2) enact the approved user charge ordinance or
corporate resolution and submit proof of such enactment.
3.3.9.4
1. Within 5 days after construction completion of each construction/repair contract, the loan
recipient must submit a determination of construction/repair completion and must request
a final construction observation by the Department staff.
2. Within 10 days after the current contract completion date, all change orders which include
time extensions, and/or documentation showing the loan recipient is implementing all
legal remedies provided in the contract documents for failure to complete construction
when required, must be submitted to the Department for approval, otherwise construction
and construction related work which occurs after the current contract completion date will
be unallowable.
3. The final construction/repair observation may be delayed by no more than 30 days after
the current construction completion date, unless further delayed by the Department staff
pursuant to review of the loan recipient's request and justification for such delay. Should
the Department staff decide that the determination of construction/repair completion and
request for final construction observation are being unreasonably delayed, a final
construction observation may be immediately performed by the Department staff.
3.3.9.5 Within 30 days after the final construction observation performed by the Department
staff, the loan recipient must submit: final payment requests; approvable summary change orders,
if applicable, for all construction/repair contracts; a complete set of record drawings for any new
construction work requiring design by a registered engineer and, if applicable, a certification
from a registered engineer that the project has been constructed substantially in accordance with
the approved plans, specifications, and contract documents; loan recipient's resolution of
acceptance of each construction/repair contract; final construction phase services contract
amendments, if any; and all other administrative forms and documents required by the loan
agreement and the Department staff. Payment requests submitted after this date are not
allowable, regardless of when the costs were incurred.
3.3.9.6 Any other submittals or actions required by the loan agreement must be performed when
so required and are subject to review and approval by the Department staff.