33 MAC Pt. 2, R. 3.7.1
Construction
Cite as 33 Miss. Admin. Code Pt. 2, R. 3.7.1
Construction
3.7.1.1 Awarding Construction Contracts and Preconstruction Conference.
Upon receipt of the approval to execute the construction contracts and to issue the notice to
proceed, the loan recipient must do so and must transmit a copy of the executed construction
contracts and the notice to proceed to the Department within the time frame specified in the loan
agreement.
Source: Miss. Code Ann. ยง 41-3-16(3)(b)
3.7.1.2 The loan recipient will be responsible for assuring that every appropriate procedure and
incidental legal requirement are observed in advertisement for bids and awarding the
construction contracts. For projects designated as equivalency projects, all applicable federal
cross-cutting authorities must be implemented during construction. The plans, specifications, and
executed contract documents must not vary from those approved by the Department.
Source: Miss. Code Ann. ยง 41-3-16(3)(b)
3.7.1.3 The loan recipient may arrange and hold a preconstruction conference and must allow
attendance and participation by the Department if such is held.