33 MAC Pt. 2, R. 3.7.5
Change Orders
Cite as 33 Miss. Admin. Code Pt. 2, R. 3.7.5
Change Orders.
3.7.5.1 General.
1. In the event a determination is made by a loan recipient after a construction contract is
executed that changes or modifications to the original contract are necessary or would
better serve the purpose of the loan recipient, such loan recipient may, at its discretion,
execute such change orders pertaining to the construction that are necessary under the
circumstances, as provided in the contract documents and when in accordance with state
law.
2. Change orders must not change, vary, or alter the basic purpose or effect of the project
unless allowed by the Department. Change orders must be technically adequate, the costs
must be necessary and reasonable, and eligible/ineligible costs must be appropriately
separated.
3.7.5.2 Change Order Submittals.
1. After completion of the claims resolution and/or change order negotiation process
between the loan recipient and the contracting party, a fully executed change order must
be submitted to the Department for review and approval, in order to obtain a DWSIRLF
loan eligibility/allowability determination.
2. If any change order is submitted to the Department that is not complete and fully
executed by the loan recipient, the contracting party, and the registered engineer if
appropriate, the Department may return such change order without review. However,
unilateral change orders executed by the loan recipient, and the registered engineer if
appropriate, and identified as such, that are issued in accordance with the contract
documents may be submitted to the Department for review and approval, in order to
obtain a DWSIRLF loan eligibility/allowability determination.
3. The loan recipient may submit a complete and fully executed change order which has
been executed conditional upon a DWSIRLF loan eligibility/allowability determination
by the Department.
4. All change orders must be submitted to the Department for review and approval in a
timely manner. The Department may withhold payments to the loan recipient if change
orders are not submitted in a timely manner.
5. If possible, approval of a change order should be secured from the Department before the
work is started, particularly for change orders including time extensions as per Rule
3.7.5.4 below. Approval may also be secured after the work is started; however, the loan
recipient must bear the cost if the work is determined to be ineligible or unallowable.
6. When the eligible cost of a project will be significantly reduced by a change order or
change orders, the Department may issue an amendment to the loan agreement
decreasing the loan amount, and the loan recipient must execute such amendment within
the time frame established by the Department.
3.7.5.3 Department Review.
In order to allow the Department to perform a technical and loan allowability review, requests
for change order approvals must conform to Department guidance, requirements and regulations.
3.7.5.4 Time Extensions.
Change orders which include time extensions exceeding 30 days beyond the original contract
completion date, and/or documentation that the loan recipient is implementing all legal remedies
provided in the contract documents for failure to complete construction when required, must be
submitted to the Department as specified in Rule 3.7.7 (9) of these regulations. Justification for
contract time extensions included in a change order must be prepared, but need not be submitted
to the Department unless the total time extensions for the contract exceed 30 days after the
original contract completion date, in which case justification for all time extensions must be
submitted to the Department for an allowability determination.