36 MAC Pt. 2, R. 205.3
009-010 Procurement Process: Multi-Year Prepayment Approvals
Cite as 36 Miss. Admin. Code Pt. 2, R. 205.3
009-010 Procurement Process: Multi-Year Prepayment Approvals
In accordance with the authority granted under Section 7-7-27 Mississippi Code Annotated, the
Department of Finance and Administration (DFA), by letter dated June 18, 2010, attached below,
granted ITS the authorization to approve contracts for multi-year prepayment of information
technology services and software licensing for ITS customer agencies. You may view this letter
on page 74.
This authorization is specifically applicable to projects requiring ITS approval and does NOT
apply to projects made under ITS' purchasing delegations to agencies.
Prior to granting any approval for a multi-year prepayment, ITS must carefully review the licensing
or services to be provided to ensure prepayment is both a standard business model for the licenses
or services being purchased and is advantageous to the State. If approved, ITS will ensure that
contracts for these purchases contain appropriate protective language to reduce the risk of
prepayment.
Once the prepayment has been approved, ITS will issue a project-specific approval letter to the
customer agency, in addition to the usual CP-1 Acquisition Approval Document. The approval
letter will cite the authorization granted to ITS by DFA.
Agencies must attach a copy of the ITS approval letter to the payment voucher (PV).
ITS Process for Approval of Prepayment for Technology Under a Blanket Waiver from DFA
1. ITS receives a request from a customer for technology services or software licensing that could
potentially include a multi-year prepayment. The most common situations for consideration
of prepayment are warranty extensions, prepaid hardware support or software licensing, and
prepaid hosting when the vendor must make a significant up-front investment in infrastructure.
2. ITS includes language in the Request for Proposals (RFP), Letter of Configuration (LOC),
Request for Quotations (RFQ), or Invitation to Bid (ITB) specifying that vendors must:
a) provide pricing for one year as well as multi-year prepayment options that provide
significant savings for the State so that the risks and benefits of prepayment can be
evaluated; and/or
b) define and justify any prepayment requirements in vendor’s business model for these
services or software
3. ITS evaluates proposals, including assessment of any significant cost benefits or vendor
requirements for prepayment. If prepayment is required, ITS evaluates vendor’s justification
to ensure this is a standard business model supported by the industry and by the vendor’s up-
front investments. If prepayment is an option, ITS evaluates the cost savings to ensure the
benefit of prepayment outweighs the risks.
4. ITS discusses the evaluation of prepayment options with the customer. If customer requests
acceptance of a prepayment proposal, customer documents that decision in writing to ITS.
5. If a prepayment proposal is accepted, ITS includes language in the resulting project contract
concerning the state’s ability to terminate based on non-appropriation of funds and a
requirement for a pro-rated refund of prepayment to the state upon any allowable termination
of the contract.
6. ITS issues and uploads to MAGIC a CP-1 Acquisition Approval Document for the acquisition,
documenting the services or licenses, amount and timeframe covered by the prepayment.
7. ITS sends a letter to the customer documenting the specifics of the prepayment authority, citing
DFA’s authorization for ITS to approve such contracts.
8. ITS sends a copy of the executed contract to the customer for upload to the Merlin
Award/Contract Interface.
9. Customer proceeds with the purchase, using the information uploaded to MAGIC by the ITS
CP-1 process to encumber funds and make payment. Customer will attach a copy of the
project-specific prepayment approval letter from ITS to the payment voucher.
AUTHORIZATION LETTER FROM DFA: Waiver for ITS to approve multi-year payments