36 MAC Pt. 2, R. 205.5
009-070 Procurement Process: Deadlines for Submitting Requests
Cite as 36 Miss. Admin. Code Pt. 2, R. 205.5
009-070 Procurement Process: Deadlines for Submitting Requests
Each year, ITS sends a reminder to our customers of approximate turnaround times required to
conduct IT procurements, as well as the corresponding deadlines for submitting projects that must
be completed during the current state and federal fiscal years. These timelines are intended to help
ensure procurement requests are submitted to ITS in time for completion within the customer's
desired time frames and in time to receive approval for any expenditure with a funding deadline
or other external time constraints.
This handbook shows an estimate of projected time required for processing each procurement type
and dollar amount (Procurement Limits Policies: Section 015-010 and 015-020). Unless you have
already had specific discussions with ITS procurement staff regarding a project schedule, the high
end of each range should be used as a guideline for when requests should be submitted to ITS to
ensure the procurement is completed in time to meet your needs.
In addition, the associated deadlines for State and Federal Fiscal Year acquisitions are listed in
the table below. Note that requests for personnel services and maintenance contracts under the
purview of ITS that are to be paid from either the old or new fiscal year funds and that begin on or
near the beginning of the state or federal fiscal year should also be submitted by the fiscal year
deadline. (e.g. maintenance that should be renewed effective July 1)
Continually review your state and federal funding and your information systems needs and submit
all procurement requests to ITS according to the deadlines and timeframes shown. Some complex
requests, such as those requiring extensive systems analysis or engineering surveys prior to RFP
development, take more time than indicated on the schedules below. ITS will work with you to
develop a project plan and timetable to address these types of requests. ITS will work with you to
have all other requests submitted by the deadline dates completed within the timeframes shown
and by the June 30 and September 30 funding deadlines when applicable.
We believe the schedules shown below give you and our staff sufficient time to ensure each project
receives adequate attention for the size and complexity of the acquisition. Each June and
September, procurement requests are at risk of not meeting the funding deadlines because they
were not submitted in time to complete the purchase in compliance with state and federal laws.
When the procurement timeline is too compressed, ITS staff cannot complete procurements that
(a) meet all legal requirements for competitive proposals; (b) provide a thorough and legally
defensible evaluation of vendor proposals; and (c) develop project contracts that adequately protect
the customer’s interests. Also, ITS develops staffing plans based on the requests we have received
and may not have adequate staff resources available to process requests received after these
deadlines.
ITS understands that our customers sometimes don’t have information concerning the availability
of funds for technology acquisitions until after these deadlines. ITS is committed to assisting you
at any time, to the best of our ability. The options (we are aware of) for helping you to complete
your purchases with tighter timeframes and/or those submitted after these deadlines are: (1) you
can use your own staff and/or contract staff for more of the preliminary research and preparation
of the request and to assist available ITS staff throughout the procurement; or (2) you may request
an exemption on a Procurement Request Form and, with ITS’ approval, make the purchase
yourself, assuming the responsibility for following all purchasing laws. ITS assistance for
projects requiring a tighter timeframe or received after the deadlines may be charged at a
higher hourly rate to cover our additional expenses.
If you are unable to have the formal request prepared by the scheduled submission date but
are aware of upcoming purchases that have a funding deadline, call Lynn Ainsworth at 601-
432-8150 or Tina Wilkins at 601-432-8161 on or before these deadline dates. We will work
to help you meet your objectives in the required time frame.
Category
Time Required
for Procurement
Process:
Submission Deadline
for June 30 Funds:
Submission
Deadline for
September 30
Funds:
Requests requiring
Board approval and an
RFP
3 - 8 months
January 1
April 1
Requests not requiring
Board approval but
requiring an RFP
2 - 5 months
February 1
May 1
Exemption requests
requiring ITS Board
approval;
Requests for sole
source certification;
Competitive
procurements not
requiring Board
approval and using
existing procurement
instruments
1 - 3 months
April 1
July 1
All other procurement
requests
1 month +/-
June 1
September 1
Notes:
(a)
The lifecycle cost includes all costs associated with obtaining the item or service and with
maintaining and operating it for its projected lifecycle. Examples of costs in each category include:
(1) Initial and/or one-time costs: purchase price, freight, installation, and cost to exercise purchase
option; (2) Ongoing costs: maintenance, lease, rental, associated personnel costs, and telephone
line charges. Lifecycle costs are computed over a three to five year period, unless factors relevant
to a specific project dictate a different time period.
(b)
Contact ITS to see if there is an existing procurement instrument that can be used for your
acquisition.