39 MAC Pt. IV
Mississippi Distributed Generator Interconnection and Distributed Generation
Cite as 39 Miss. Admin. Code Pt. IV
TITLE 39: UTILITIES
PART IV: Mississippi Distributed Generator Interconnection and Distributed Generation
Subpart I: Mississippi Distributed Generator Interconnection Rule
Chapter 01: Introduction
The Mississippi Distributed Generation Interconnection Rule (MDGIR) sets forth standards to
establish the technical and procedural requirements for Distributed Generator Facilities (DGFs) to
be interconnected and operated in Parallel with the Electric Distribution System (EDS) owned or
operated by Electric Utilities (EUs) in Mississippi under the jurisdiction of the Mississippi Public
Service Commission (Commission). Capitalized terms used in this rule have the meaning
specified in the section titled DEFINITIONS.
Chapter 02: Definitions
When used in this chapter, the following terms and phrases shall have the following meaning:
100 âAdverse System Impactâ means a negative effect, due to technical or operational limits
on conductors or equipment being exceeded, that compromises the safety and reliability
of the EDS.
101 âApplicable Laws and Regulationsâ means all duly promulgated and applicable
federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments,
directives, or judicial or administrative orders, permits and other duly authorized actions
of any Governmental Authority.
102 âCertificate of Completionâ means a certificate in a completed form approved by the
Commission containing information about the Interconnection Equipment to be used, its
installation and local inspections.
103 âCertified Interconnection Equipmentâ or âCertified Equipmentâ or âCertifiedâ
means a designation that the Interconnection Equipment meets the following
requirements:
1. The Interconnection Equipment has been tested by a Nationally Recognized Testing
Laboratory (NRTL) recognized by the United States Occupational Safety and Health
Administration (OSHA) in accordance with the following relevant codes and standards:
a. IEEE 1547.1 Standard for Conformance Tests Procedures for Equipment
Interconnecting Distributed Resources with Electric Power Systems; and
b. Underwriters Laboratories (âULâ), UL 1741 Inverters, Converters, and Controllers
for Use in Independent Power Systems;
2. The Interconnection Equipment shall meet the requirements of the most current
approved version of each code and standard listed above, as amended and
supplemented at the time the Interconnection Request is submitted to be deemed
Certified;
3. The Interconnection Equipment has been labeled and is publicly listed by such NRTL
at the time of the interconnection application;
4. The Interconnection Customer verifies that the intended use of the Interconnection
Equipment falls within the use or uses for which the Interconnection Equipment is
labeled and is listed by the NRTL;
5. If the Interconnection Equipment is an integrated equipment package such as an
inverter, then the Interconnection Customer shall show that the generator or other
electric source being utilized is compatible with the Interconnection Equipment and is
consistent with the testing and listing specified for this type of Interconnection
Equipment;
6. If the Interconnection Equipment includes only interface components (switchgear,
multi-function relays, or other interface devices), an Interconnection Customer shall
demonstrate that the generator or other electric source being utilized is compatible with
the Interconnection Equipment and is consistent with the testing and listing specified
for this type of Interconnection Equipment; and
7. Certified Interconnection Equipment shall not require further design testing or
Production Testing, as specified by IEEE Standard 1547 Sections 5.1 and 5.2, or
additional Interconnection Equipment modification to meet the requirements.
However, nothing herein shall preclude the need for an on-site Witness Test or
operational test by the Interconnection Customer.
104 âCommissionâ means the Mississippi Public Service Commission.
105 âCommissioning Testsâ means the tests applied to a DGF by an Interconnection
Customer after construction is completed to verify that the DGF does not create Adverse
System Impacts. At a minimum, the scope of the Commissioning Tests performed shall
include the commissioning test specified by IEEE Standard 1547 section 5.4
âCommissioning Tests.â
106 âDistributed Generator Facilityâ or âDGFâ means the equipment used by an
Interconnection Customer to generate or store electricity that operates in Parallel with the
EDS. A DGF typically includes an electric generator, prime mover, and the
Interconnection Equipment required to safely interconnect with the EDS or local electric
power system.
107 âDistribution System Upgradeâ means a required addition or modification to the EU's
EDS at or beyond the Point of Common Coupling (PCC) to accommodate the
interconnection of a DGF. Distribution System Upgrades do not include Interconnection
Facilities.
108 âElectric Utilityâ or âEUâ means an electric public utility that distributes electricity to
customers and is subject to the jurisdiction of the Commission pursuant to the provisions
of Mississippi Code Annotated §§ 77-3-1, et seq.
109 âElectric Distribution Systemâ or âEDSâ means the facilities and equipment used to
transmit electricity to ultimate usage points such as homes and industries from
interchanges with higher voltage transmission networks that transport bulk power over
longer distances. The voltage levels at which EDSs operate differ among areas but
generally carry less than 69 kilovolts of electricity. EDS has the same meaning as the
term Area EPS, as defined in 3.1.6.1 of IEEE Standard 1547.
110 âFacilities Studyâ means an engineering study conducted by the EU to determine the
required modifications to the EUâs EDS, including the cost and the time required to build
and install such modifications as necessary to accommodate an Interconnection Request.
111 âFault Currentâ means the electrical current that flows through a circuit during an
electrical fault condition. A fault condition occurs when one or more electrical conductors
contact ground or each other. Types of faults include phase to ground, double-phase to
ground, three-phase to ground, phase-to-phase, and three-phase.
112 âFeasibility Studyâ means a study performed to identify the existence of obvious
adverse impacts before additional studies are undertaken for the proposed project to
continue in the process.
113 âGovernmental Authorityâ mean any federal, state, local or other governmental
regulatory or administrative agency, court, commission, department, board, or other
governmental subdivision, legislature, rulemaking board, tribunal, or other governmental
authority having jurisdiction over the Parties, their respective facilities, or the respective
services they provide, and exercising or entitled to exercise any administrative, executive,
police, or taxing authority or power; provided, however, that such term does not include
the Interconnection Customer, EU or any affiliate thereof.
114 âIEEE Standard 1547â means the Institute of Electrical and Electronics Engineers, Inc.
(IEEE) Standard 1547 (2003) ''Standard for Interconnecting Distributed Resources with
Electric Power Systems,'' as amended and supplemented at the time the Interconnection
Request is submitted.
115 âIEEE Standard 1547.1â means the IEEE Standard 1547.1 (2005) ''Conformance Test
Procedures for Equipment Interconnecting Distributed Resources with Electric Power
Systems,'' as amended and supplemented at the time the Interconnection Request is
submitted.
116 âInterconnection Agreementâ or âAgreementâ means a form of interconnection
agreement approved by the Commission which is applicable to Interconnection Requests
pertaining to DGFs. The agreement between the Interconnection Customer and the EU
governs the connection of the DGF to the EUâs EDS, as well as the ongoing operation of
the DGF after it is connected to the EUâs EDS.
117 âInterconnection Applicationâ or âApplicationâ means a form of interconnection
application approved by the Commission which is applicable to Interconnection Requests
pertaining to DGFs. This application provides the information needed by the EU to
review the request for interconnection. For the Level 1 review process, the Application
and Agreement are part of the same document.
118 âInterconnection Customerâ means an entity that submits an Interconnection Request
for a DGF to an EU's EDS.
119 âInterconnection Equipmentâ means a group of equipment, components, or an
integrated system connecting an electric generator with a local electric power system or
an EDS that includes all interface equipment including switchgear, protective devices,
inverters or other interface devices. Interconnection equipment may be installed as part
of an integrated equipment package that includes a generator or other electric source.
120 âInterconnection Facilitiesâ means facilities and equipment required by the EU to
accommodate the interconnection of a DGF. Collectively, Interconnection Facilities
include all facilities and equipment between the DGF and the PCC, including
modification, additions, or upgrades that are necessary to physically and electrically
interconnect the DGF to the EDS. Interconnection facilities are sole use facilities and do
not include Distribution System Upgrades.
121 âInterconnection Requestâ means an Interconnection Customer's request, in the form
of an Application approved by the Commission, requesting the interconnection of a new
DGF, or to increase the capacity or modify operating characteristics of an existing
approved DGF that is interconnected with the EU's EDS.
122 âLine Sectionâ means that portion of an EU's distribution system connected to an
Interconnection Customer, bounded by automatic sectionalizing devices or the end of the
distribution line.
123 âLocal Electric Power Systemâ or âLocal EPSâ means facilities that deliver electric
power to a load that are contained entirely within a single premises or group of premises.
Local electric power system has the same meaning as the term local electric power system
defined in 3.1.6.2 of IEEE Standard 1547.
124 âMinor Equipment Modificationâ means changes to the DGF that do not have a
material impact on safety or reliability of the EDS.
125 âMississippi Distributed Generation Interconnection Rule (MDGIR)â means the
most current version of the procedures for interconnecting Distributed Generator
Facilities adopted by the Mississippi Public Service Commission.
126 âNameplate Capacityâ means the maximum rated output of a generator, prime mover,
or other electric power production equipment under specific conditions designated by the
manufacturer and is usually indicated on a nameplate physically attached to the power
production equipment.
127 âNationally Recognized Testing Laboratoryâ or âNRTLâ means a qualified private
organization that meets the requirements of the Occupational Safety and Health
Administration's (OSHA) regulations. NRTLs perform independent safety testing and
product certification. Each NRTL shall meet the requirements as set forth by OSHA in
the NRTL program.
128 âParallel Operationâ or âParallelâ means the sustained state of operation over 100
milliseconds, which occurs when a DGF is connected electrically to the EDS and thus
has the ability for electricity to flow from the DGF to the EDS.
129 âPoint of Common Couplingâ or âPCCâ means the point where the DGF is electrically
connected to the EDS. Point of common coupling has the same meaning as defined in
3.1.13 of IEEE Standard 1547.
130 âPrimary Lineâ means a distribution line rated at greater than 600 volts.
131 âProduction Testâ means production test as defined in IEEE Standard 1547.
132 âQueue Positionâ means the order of a valid Interconnection Request, relative to all
other pending valid Interconnection Requests, that is established based upon the date and
time of receipt of the valid Interconnection Request by the EU.
133 âRadial Distribution Circuitâ means a circuit configuration where independent feeders
branch out radially from a common source of supply. From the standpoint of a utility
system, the area described is between the generating source or intervening substations
and the customerâs entrance equipment. A radial distribution system is the most common
type of connection between a utility and load in which power flows in one direction from
the utility to the load.
134 âScoping Meetingâ means a meeting between representatives of the Interconnection
Customer and EU conducted for the purpose of discussing alternative interconnection
options, exchanging information including any EDS data and earlier study evaluations
that would be reasonably expected to impact interconnection options, analyzing
information, and determining the potential feasible points of interconnection.
135 âSecondary Lineâ means a service line subsequent to the Primary Line that is rated for
600 volts or less, also referred to as the customerâs service line.
136 âSystem Impact Studyâ means a study that identifies the electric system impacts that
would result if the proposed DGF were interconnected without DGF modifications or
EDS modifications, focusing on the Adverse System Impacts identified in the Feasibility
Study.
137 âUL Standard 1741â means Underwriters Laboratories' standard titled ''Inverters
Converters, and Controllers for Use in Independent Power Systems,â as amended and
supplemented at the time the Interconnection Request is submitted.
138 âWitness Testâ means verification (through on-site observation) by the EU that the
installation evaluation required by IEEE Standard 1547 Section 5.3 and the
Commissioning Test required by IEEE Standard 1547 Section 5.4, have been adequately
performed. For Interconnection Equipment that has not been Certified, the Witness Test
shall also include the verification by the EU of the on-site design tests as required by
IEEE Standard 1547 Section 5.1 and verification by the EU of Production Tests required
by IEEE Standard 1547 Section 5.2. All tests verified by the EU are to be performed in
accordance with the applicable test procedures specified by IEEE Standard 1547.1.
Chapter 03: INTERCONNECTION REQUESTS, FEES, AND FORMS
100 Interconnection Customers seeking to interconnect a DGF shall submit an
Interconnection Request to the EU that owns the EDS to which interconnection is sought,
using an application approved by the Commission. Electronic versions of such
Commission-approved Application forms shall be posted on the EUâs website. The EU
shall establish processes for accepting Interconnection Requests electronically,
specifically through online submission. Such online submission portal should include, at
a minimum, information on interconnection times and procedures, a repository of relevant
forms that allow for electronic entry of text, an application status tracker, and a searchable
interconnection queue that is updated on a regular basis.
101 When an Interconnection Customer is not currently a customer of the EU at the proposed
PCC, upon request from the EU, the Interconnection Customer shall provide proof of site
control evidenced by a property tax bill, deed, lease agreement, or other legally binding
contract.
102 Interconnection fees shall be governed as follows for all Interconnection Requests and
shall be published on each EUâs website:
1. An EU may not charge an application, or other fee, to an applicant that requests
Level 1 interconnection review. However, if an application for Level 1
interconnection review is denied because it does not meet the requirements for
Level 1 interconnection review and the applicant resubmits the application under
another review procedure in accordance with the MDGIR, the EU may impose a
fee for the resubmitted application, consistent with this section.
2. For a Level 2 interconnection review, the EU may charge fees of up to $50.00 plus
$1.00 per kilowatt of the customer-generator facility's capacity, plus the reasonable
cost of any required minor modifications to the electric distribution system or
additional review. Costs for such minor modifications or additional review will be
based on the EU's non-binding, good faith estimates and the ultimate actual
installed costs. Costs for engineering work done as part of any additional review
will not exceed $100.00 per hour.
3. For a Level 3 interconnection review, the EU may charge fees of up to $100.00 plus
$2.00 per kilowatt of the customer-generator facility's capacity, as well as charges
for actual time spent on any required impact or facilities studies. Costs for
engineering work done as part of an impact study or interconnection facilities study
will not exceed $100.00 per hour. If the EU must install facilities in order to
accommodate the interconnection of the customer generating facility, the cost of
such facilities will be the responsibility of the applicant.
103 When the EU determines that an Interconnection Request is complete, a modification of
DGF design by the Interconnection Customer other than a Minor Equipment Modification
that is not agreed to in writing by the EU shall require submission of a new
Interconnection Request.
Chapter 04: INTERCONNECTION REVIEW LEVELS
100 The EU shall review Interconnection Requests using one of the three levels of review
procedures established below. The EU shall first use the level of DGF Agreement
specified by the Interconnection Customer in the Application. The EU may not impose
additional requirements not specifically authorized unless the EU and the Interconnection
Customer mutually agree to do so in writing.
101 When an Interconnection Request is for an increase in capacity for an existing DGF, the
Interconnection Request shall be evaluated on the basis of the new total Nameplate
Capacity of the DGF.
102 When an Interconnection Request is for a DGF that includes multiple energy production
devices at a site for which the Interconnection Customer seeks a single PCC, the
Interconnection Request shall be evaluated on the basis of the aggregate Nameplate
Capacity of the multiple devices.
Chapter 05: LEVEL 1 INTERCONNECTION REVIEWS
100 The EU shall use Level 1 review procedures to evaluate Interconnection Requests when:
1. The DGF is inverter-based;
2. The DGF has a Nameplate Capacity of 20 kW or less; and
3. The Interconnection Equipment proposed for the DGF is Certified.
101 For Level 1 Interconnection Review, the EU shall first evaluate the potential for Adverse
System Impacts using the following screens, which must be satisfied:
1. For interconnection of a proposed DGF to a Line Section on a Radial Distribution
Circuit, the aggregated generation on the Line Section, including the proposed
DGF, shall not exceed 15% of the Line Section annual peak load.
2. When a proposed DGF is to be interconnected to a single-phase shared Secondary
Line, the aggregate generation capacity on the shared Secondary Line, including
the proposed DGF, may not exceed 20 kW.
3. When a proposed DGF is single-phase and is to be interconnected to a center tap
neutral of a 240 volt service, its addition may not create an imbalance between the
two sides of the 240 volt service of more than 20% of the nameplate rating of the
service transformer.
4. Construction of facilities by the EU on its own system is not required to
accommodate the DGF.
102 The Level 1 Interconnection Review shall then be conducted in accordance with the
following procedures:
1. An EU shall, within 10 business days after receipt of the Interconnection Request,
inform the Interconnection Customer in writing or by electronic mail that the
Interconnection Request is complete or incomplete and indicate what, if any,
materials are missing.
2. When an Interconnection Request is complete, the EU shall assign a Queue
Position.
3. The EU shall, within 15 business days after notifying a Level 1 applicant that the
application is complete, indicate that the DGF equipment meets all Level 1 criteria,
verify the DG can be interconnected safely and reliably using Level 1 screens, and
provide a conditionally approved Level 1 Interconnection Application Form and
Agreement to the Interconnection Customer.
103 Unless the EU determines and demonstrates to the Interconnection Customer that a DGF
cannot be interconnected safely or reliably to its system and provides a letter to the
Interconnection Customer explaining its reasons for denying an Interconnection Request,
the EUâs final approval of the Interconnection Agreement is subject to the following
conditions:
1. âThe DGF has been approved by local or municipal electric code officials with
jurisdiction over the interconnection;
2. The EU has received the required information on the Certificate of Completion
from the Interconnection Customer. Completion of local inspections may be
designated on inspection forms used by local inspecting authorities; and
3. The EU has completed its Witness Test in accordance with the MDGIR.
104 Within 10 business days of the estimated commissioning date indicated on the
Interconnection Request, the EU shall, upon reasonable notice and at a mutually
convenient time, conduct a Witness Test of the DGF to ensure that all equipment has been
appropriately installed and that all electrical connections have been made in accordance
with applicable codes.
105 When a DGF is not approved under a Level 1 review, the Interconnection Customer may
submit a new Interconnection Request for consideration under Level 2 or Level 3
procedures.
Chapter 06: LEVEL 2 INTERCONNECTION REVIEWS
100 The EU shall use the Level 2 Interconnection Review procedure to evaluate an
Interconnection Request when:
1. The DGF has a Nameplate Capacity rating of 2 MW or less;
2. The Interconnection Equipment proposed for the DGF is Certified; and
3. The aggregated total of the Nameplate Capacity of all of the generators on the
circuit, including the proposed DGF, is 2 MW or less.
101 No construction of facilities by an EU shall be required to accommodate the DGF, except
as permitted by an additional review for minimal modifications of the EDS, as described
in these Level 2 procedures.
102 For Level 2 Interconnection Review, the EU first shall evaluate the potential for Adverse
System Impacts using the following screens, which must be satisfied:
1. For interconnection of a proposed DGF to a radial distribution circuit, the
aggregated generation on the Line Section, including the proposed DGF, may not
exceed 15% of the Line Section annual peak load.
2. The proposed DGF, in aggregation with other generation on the distribution circuit,
may not contribute more than 10% to the distribution circuit's maximum Fault
Current at the point on the Primary Line nearest the Point of Common Coupling
(PCC).
3. The proposed DGF, in aggregate with other generation on the distribution circuit,
may not cause any distribution protective devices and equipment (including
substation breakers, fuse cutouts, and line reclosers), or other customer equipment
on the EDS to be exposed to Fault Currents exceeding 87.5% of the short circuit
interrupting capability. The Interconnection Request may not receive approval for
interconnection on a circuit that already exceeds 87.5% of the short circuit
interrupting capability.
4. When a DGF is to be connected to three-phase, three-wire primary EU distribution
lines, a three-phase or single-phase generator shall be connected phase-to-phase.
5. When a DGF is to be connected to three-phase, four-wire primary EU distribution
lines, a three-phase or single-phase generator shall be connected line-to-neutral and
shall be effectively grounded.
6. When the proposed DGF is to be interconnected on a single-phase shared
Secondary Line, the aggregate generation capacity on the shared Secondary Line,
including the proposed DGF, shall not exceed 20 kW.
7. When a proposed DGF is single-phase and is to be interconnected on a center tap
neutral of a 240 volt service, its addition may not create an imbalance between the
two sides of the 240 volt service of more than 20% of the nameplate rating of the
service transformer.
8. A DGF, in aggregate with other generation interconnected to the distribution side
of a substation transformer feeding the circuit where the DGF proposes to
interconnect, may not exceed 10 MW in an area where there are known or posted
transient stability limitations to generating units located in the general electrical
vicinity.
9. No construction of facilities by an EU on its own system shall be required to
accommodate the DGF.
103 The Level 2 Interconnection Review shall then be conducted in accordance with the
following procedures:
1. An EU shall, within 10 business days after receipt of the Interconnection Request,
inform the Interconnection Customer in writing or by electronic mail that the
Interconnection Request is complete or incomplete and indicate what, if any,
materials are missing. As part of this process, the EU shall assign a Queue Position.
The Queue Position of the Interconnection Request shall be used to determine the
potential Adverse System Impact of the DGF based on the relevant screening
criteria. If there are higher queued Interconnection Requests on the same radial line
circuit, the EU shall evaluate the Interconnection Requests by performing any Level
2 screens requiring aggregate capacity calculations and determine if the DGF in
combination with the higher queued Interconnection Requests exceeds any of the
aggregate capacity requirements. If an aggregate capacity requirement is exceeded,
the EU shall notify the Interconnection Customer and shall not be obligated to meet
the timeline for reviewing the Interconnection Request until such time as the EU
has completed the review of all other Interconnection Requests that have a higher
Queue Position and impact the aggregate capacity calculation that has been
exceeded.
2. At the time an EU determines additional information is required to complete an
evaluation, the EU shall request the information. The time necessary to complete
the evaluation may be extended by mutual agreement of the parties, but only to the
extent of the time required for receipt of the additional information. During an
extension of time to submit additional information, the EU may not alter the
Interconnection Customer's Queue Position.
3. Within 20 business days after the EU notifies the Interconnection Customer that it
has received a completed Interconnection Request, the EU shall:
a. Evaluate the Interconnection Request using the Level 2 screening criteria;
b. Review any analysis provided by the Interconnection Customer, using the
same criteria used by the customer; and
c. Provide the Interconnection Customer with the EU's evaluation, including
a comparison of the results of its own analyses with those of
Interconnection Customer, if applicable. When an EU does not have a
record of receipt of the Interconnection Request and the Interconnection
Customer can demonstrate that the original Interconnection Request was
delivered, the EU shall expedite its review to complete the evaluation of
the Interconnection Request within 20 business days of the
Interconnection Customer's re-submittal.
104 The EU shall provide the Interconnection Customer a DGF Interconnection Agreement
within 5 business days of its determination that the Interconnection Request passes the
Level 2 screening criteria.
105 When a DGF has failed to meet one or more of the Level 2 screens, the EU shall offer to
perform additional review for minimal modifications of the EDS to determine whether
minimal modifications to the EDS would enable the interconnection to be made
consistent with safety, reliability and power quality criteria. The EU shall provide the
Interconnection Customer with a nonbinding, good faith estimate of the costs of
additional review for minimal modifications of the EDS. The EU shall undertake the
additional review for minimal modifications of the EDS or the modifications only after
the Interconnection Customer consents to pay for the review and modifications.
106 If the DGF fails one or more of the Level 2 screening criteria but the EU determines that
minimal modifications to the EDS would enable the DGF to interconnect safely and
reliably, the EU shall provide the Interconnection Customer a DGF Interconnection
Agreement within 5 business days of making that determination.
107 If the EU finds that the DGF cannot be interconnected with minimal modifications to the
EDS, the EU shall provide the Interconnection Customer a letter explaining its reasons
for denying the Interconnection Request. The Interconnection Customer may submit a
new Interconnection Request for consideration under a Level 3 interconnection review.
108 An Interconnection Customer shall have 30 business days to sign and return the
Agreement. When an Interconnection Customer does not sign the DGF Interconnection
Agreement within 30 business days, the Interconnection Request shall be deemed
withdrawn unless the Interconnection Customer requests in writing prior to the expiration
of the 30 business day period to extend the deadline. The EU may not unreasonably deny
the request for extension.
109 The DGF Interconnection Agreement shall not become final until:
1. The milestones agreed to in the DGF Interconnection Agreement are satisfied;
2. The DGF is approved by electric code officials with jurisdiction over the
interconnection;
3. The Interconnection Customer provides a Certificate of Completion to the EU.
Completion of local inspections may be designated on inspection forms used by
local inspecting authorities; and
4. The Witness Test was successfully completed per the terms and conditions found
in the Agreement.
110 If the DGF is not approved under a Level 2 review, the EU shall provide the
Interconnection Customer a letter explaining its reasons for denying the Interconnection
Request. The Interconnection Customer may submit a new Interconnection Request for
consideration under a Level 3 interconnection review. The Queue Position assigned to
the Level 2 Interconnection Request shall be retained provided the request is made within
15 business days of notification that the current Interconnection Request is denied.
Chapter 07: LEVEL 3 INTERCONNECTION REVIEWS
100 The EU shall use the Level 3 review procedure to evaluate an Interconnection Request
when the Interconnection Customer requests Level 3 review.
101 The Level 3 review shall be conducted in accordance with the following process:
1. An EU shall, within 10 business days of receipt of an Interconnection Request,
inform the Interconnection Customer in writing or by electronic means that the
Interconnection Request is complete or incomplete and indicate what, if any,
materials are missing.
2. When the Interconnection Request is deemed not complete, the EU shall provide
the Interconnection Customer with a written list detailing information required to
complete the Interconnection Request. The Interconnection Customer shall have
10 business days to provide appropriate data in order to complete the
Interconnection Request, or the Interconnection Request shall be considered
withdrawn. The parties may agree to extend the time for receipt of the additional
information. The Interconnection Request shall be deemed complete when the
required information has been provided by the Interconnection Customer, or the
parties have agreed that the Interconnection Customer may provide additional
information at a later time.
3. When an Interconnection Request is complete, the EU shall assign a Queue
Position. The Queue Position of an Interconnection Request shall be used to
determine the cost responsibility necessary for the facilities to accommodate the
interconnection. The EU shall notify the Interconnection Customer about other
higher-queued Interconnection Customers that have the potential to impact the cost
responsibility.
4. Level 3 Scoping Meetings shall be conducted as follows:
a. By mutual agreement of the parties, the Scoping Meeting, interconnection
Feasibility
Study,
interconnection
System
Impact
Study,
or
interconnection Facilities Study provided for in a Level 3 review may be
waived;
b. If agreed to by the parties, a Scoping Meeting shall be held within 10
business days, or other mutually agreed to time, after the EU has notified
the Interconnection Customer that the Interconnection Request is deemed
complete, The purpose of the meeting shall be to review the
Interconnection Request, existing studies relevant to the Interconnection
Request, and the results of the Level 1 or Level 2 screening criteria;
c. When the parties agree at a Scoping Meeting that an interconnection
Feasibility Study shall be performed, the EU shall provide to the
Interconnection Customer, no later than 5 business days after the Scoping
Meeting, an interconnection Feasibility Study agreement, including an
outline of the scope of the study and a nonbinding good faith estimate of
the cost to perform the study;
d. When the parties agree at a Scoping Meeting that an interconnection
Feasibility Study is not required, the EU shall provide to the
Interconnection Customer, no later than 5 business days after the Scoping
Meeting, an interconnection System Impact Study agreement, including
an outline of the scope of the study and a nonbinding good faith estimate
of the cost to perform the study; and
e. When the parties agree at the Scoping Meeting that an interconnection
Feasibility Study and System Impact Study are not required, the EU shall
provide to the Interconnection Customer, no later than 5 business days
after the Scoping Meeting, an interconnection Facilities Study agreement
including an outline of the scope of the study and a nonbinding good faith
estimate of the cost to perform the study.
5. Any required interconnection studies shall be carried out using the following
guidelines:
a. An interconnection Feasibility Study shall include the following analyses
and conditions for the purpose of identifying and addressing potential
Adverse System Impacts to the EU's EDS that would result from the
interconnection:
b. Initial identification of any circuit breaker short circuit capability limits
exceeded as a result of the interconnection;
c. Initial identification of any thermal overload or voltage limit violations
resulting from the interconnection;
d. Initial review of grounding requirements and system protection;
e. Description and nonbinding estimated cost of facilities required to
interconnect the DGF to the EU's EDS in a safe and reliable manner; and
f. Additional evaluations at the expense of the Interconnection Customer,
when an Interconnection Customer requests that the interconnection
Feasibility Study evaluate multiple potential points of interconnection.
6. An interconnection System Impact Study shall evaluate the impact of the proposed
interconnection on both the safety and reliability of the EU's EDS. The study shall
identify and detail the system impacts that result when the proposed DGF is
interconnected without project or system modifications, focusing on the Adverse
System Impacts identified in the interconnection Feasibility Study and potential
impacts including those identified in the Scoping Meeting. The study shall consider
all generating facilities that, on the date the interconnection System Impact Study
is commenced, are directly interconnected with the EU's system, have a pending
higher Queue Position to interconnect to the system, and have a signed a DGF
Interconnection Agreement.
a. An interconnection System Impact Study shall be performed when the
interconnection Feasibility Study identifies a potential distribution system
Adverse System Impact. The EU shall send the Interconnection Customer
an interconnection System Impact Study agreement within 5 business
days of transmittal of the interconnection Feasibility Study report. The
agreement shall include an outline of the scope of the study and a good
faith estimate of the cost to perform the study. The System Impact Study
shall include:
i.
A load flow study;
ii.
Identification of affected systems;
iii.
An analysis of equipment interrupting ratings;
iv.
A protection coordination study;
v.
Voltage drop and flicker studies;
vi.
Protection and set point coordination studies;
vii.
Grounding reviews; and
viii.
Impact on system operation.
b. An interconnection System Impact Study shall consider the following
criteria:
i.
A short circuit analysis;
ii.
A stability analysis;
iii.
Alternatives for mitigating Adverse System Impacts on
affected systems;
iv.
Voltage drop and flicker studies;
v.
Protection and set point coordination studies; and
vi.
Grounding reviews.
c. The interconnection System Impact Study shall provide the following:
i.
The underlying assumptions of the study;
ii.
The results of the analyses;
iii.
A list of any potential impediments to providing the
requested interconnection service;
iv.
Required Distribution System Upgrades; and
v.
A nonbinding good faith estimate of cost and time to
construct any required Distribution System Upgrades.
d. The parties shall use an interconnection System Impact Study agreement
approved by the Commission.
7. The interconnection Facilities Study shall be conducted as follows:
a. Within 5 business days of completion of the interconnection System
Impact Study, the EU shall send a report to the Interconnection Customer
with an interconnection Facilities Study agreement, which includes an
outline of the scope of the study and a nonbinding good faith estimate of
the cost to perform the study;
b. The interconnection Facilities Study shall estimate the cost of the
equipment, engineering, procurement and construction work including
overheads needed to implement the conclusions of the interconnection
Feasibility Study and the interconnection System Impact Study to
interconnect the DGF. The interconnection Facilities Study shall
identify:
i.
The electrical switching configuration of the equipment,
including transformer, switchgear, meters and other station
equipment;
ii.
The nature and estimated cost of the EU's Interconnection
Facilities and Distribution System Upgrades necessary to
accomplish the interconnection; and
iii.
An estimate of the time required to complete the
construction and installation of the facilities;
c. The parties may agree to permit an Interconnection Customer to
separately arrange for a third party to design and construct the required
Interconnection Facilities. The EU may review the design of the facilities
under the interconnection Facilities Study agreement. When the parties
agree to separately arrange for design and construction and to comply with
security and confidentiality requirements, the EU shall make all relevant
information and required specifications available to the Interconnection
Customer to permit the Interconnection Customer to obtain an
independent design and cost estimate for the facilities, which shall be built
in accordance with the specifications;
d. Upon completion of the interconnection Facilities Study, and with the
agreement of the Interconnection Customer to pay for the
Interconnection Facilities and Distribution System Upgrades identified
in the interconnection Facilities Study, the EU shall provide the
Interconnection Customer with a DGF Interconnection Agreement
within 5 business days; and
8. When an EU determines, as a result of the interconnection studies conducted under
a Level 3 review, that it is appropriate to interconnect the DGF, the EU shall provide
the Interconnection Customer with a DGF Interconnection Agreement. If the
Interconnection Request is denied, the EU shall provide a written explanation
setting forth the reasons for denial;
9. An Interconnection Customer shall have 30 business days from receipt of the DGF
Interconnection Agreement, unless another mutually agreeable time frame is
reached, to sign and return the DGF Interconnection Agreement to the EU. If an
Interconnection Customer does not sign the DGF Interconnection Agreement
within 30 business days, the Interconnection Request shall be deemed withdrawn
unless the Interconnection Customer requests in writing, prior to the expiration of
the 30 business-day period, to extend the deadline. The EU may not unreasonably
deny the request for extension. When construction is required, the interconnection
of the DGF shall proceed according to milestones agreed to by the parties in the
DGF Interconnection Agreement. The DGF Interconnection Agreement may not
be final until:
a. The milestones agreed to in the DGF Interconnection Agreement are
satisfied;
b. The DGF is approved by electric code officials with jurisdiction
over the interconnection;
c. The Interconnection Customer provides a Certificate of Completion to the
EU. Completion of local inspections may be designated on inspection
forms used by local inspecting authorities; and
d. The Witness Test was successfully completed per the terms and
conditions found in the Agreement.
102 An interconnection System Impact Study is not required when the interconnection
Feasibility Study concludes there is no Adverse System Impact, or when the study
identifies an Adverse System Impact, but the EU is able to identify a remedy without the
need for an interconnection System Impact Study.
103 The parties shall use a form of interconnection Feasibility Study agreement approved by
the Commission.
Chapter 08: TECHNICAL STANDARDS
100 The technical standard to be used in evaluating all Interconnection Requests under
Level 1, Level 2, and Level 3 reviews, unless otherwise provided for in these
procedures, is IEEE Standard 1547. IEEE 1547.2, âApplication Guide for IEEE 1547
Standard for Interconnecting Distributed Resources with Electric Power Systems,â shall
be used as a guide (but not a requirement) to detail and illustrate the interconnection
protection requirements that are provided in IEEE 1547.
Chapter 09: POINT OF COMMON COUPLING
100 To minimize the cost of interconnecting multiple DGFs, the EU or the Interconnection
Customer may propose a single PCC for multiple DGFs located at a single site. If the
Interconnection Customer rejects the EUâs proposal for a single PCC, the Interconnection
Customer shall pay the additional cost, if any, of providing a separate PCC for each DGF.
If the EU rejects the customerâs proposal for a single PCC without providing a written
technical explanation, the EU shall pay the additional cost, if any, of providing a separate
PCC for each DGF.
Chapter 10: RECORDS AND REPORTS
100 An EU shall maintain records of the following for a minimum of 3 years:
1. The total number of and the Nameplate Capacity of the Interconnection Requests
received, approved and denied under Level 1, Level 2, and Level 3 reviews;
2. The number of Interconnection Requests that were not processed within the
timelines established in this rule;
3. The number of Scoping Meetings held and the number of feasibility studies, impact
studies, and facility studies performed and the fees charged for these studies;
4. The justifications for the actions taken to deny Interconnection Requests; and
101 An EU shall provide a report to the Commission containing the information required in
paragraphs (a)-(d) above, on or before February 1st each year.
Chapter 11: INFORMATION FOR PROSPECTIVE
INTERCONNECTIONCUSTOMERS
100 An EU shall designate a contact person and contact information on its website and for the
Commissionâs website for submission of all Interconnection Requests and from whom
information on the Interconnection Request process and the EU's EDS can be obtained
regarding a proposed DGF. The information shall include studies and other materials
useful to an understanding of the feasibility of interconnecting a DGF at a particular point
on the EU's EDS, except to the extent that providing the materials would violate security
requirements or confidentiality agreements, or otherwise would be contrary to Mississippi
or federal law and regulations. In appropriate circumstances, the EU may require
execution of a confidentiality agreement prior to release of information about the EUâs
EDS.
101 When the EU determines that an Interconnection Request is complete, a modification of
DGF design by the Interconnection Customer other than a Minor Equipment Modification
that is not agreed to in writing by the EU shall require submission of a new
Interconnection Request.
Chapter 12: ADDITIONAL TECHNICAL REQUIREMENTS
100 DGFs shall be capable of being isolated from the EU. For Level 2 and Level 3
interconnection, the isolation shall be by means of a lockable, visible-break isolation
device whose status is clearly indicated and is accessible by the EU. The isolation device
shall be installed, owned and maintained by the owner of the DGF and located between
the DGF and the PCC. A draw-out type circuit breaker with a provision for padlocking at
the draw-out position can be considered an isolation device for purposes of this
requirement. A draw-out type circuit breaker has a switching device capable of making,
carrying and breaking currents under normal and abnormal circuit conditions such as
those of a short circuit. A draw-out circuit breaker can be physically removed from its
enclosure creating a visible break in the circuit. For the purposes of these regulations, the
draw-out circuit breaker shall be capable of being locked in the open, draw-out position.
Level 1 interconnections do not require an external isolation device.
101 A Level 2 or Level 3 Interconnection Customer may elect to provide the EU access to an
isolation device that is contained in a building or area that may be unoccupied and locked
or not otherwise readily accessible to the EU, by installing a lockbox provided by the EU
that shall provide ready access to the isolation device. The Interconnection Customer shall
install the lockbox in a location that is readily accessible by the EU, and the
Interconnection Customer shall permit the EU to affix a placard in a location of its
choosing that provides clear instructions to EU operating personnel on access to the
isolation device. In the event that the Interconnection Customer fails to comply with the
terms of this subsection and the EU needs to gain access to the isolation device, the EU
shall not be held liable for any damages resulting from any necessary EU action to isolate
the Interconnection Customer.
102 Any metering necessitated by a DGF shall be installed, operated and maintained in
accordance with applicable tariffs. Any such metering requirements shall be clearly
identified as part of the DGF Interconnection Agreement executed by the Interconnection
Customer and the EU.
103 The EU shall design, procure, construct, install, and own any Distribution System
Upgrades. The actual cost of the Distribution System Upgrades, including overheads,
shall be directly assigned to the Interconnection Customer. The Interconnection
Customer may be entitled to financial contribution from any other EU customers who
may in the future utilize the upgrades paid for by the Interconnection Customer. Such
contributions shall be governed by the rules, regulations, and decisions of the
Commission.
104 The Interconnection Customer shall design its DGF to maintain a composite power
delivery at continuous rated power output at the Point of Common Coupling at a power
factor within the power factor range required by the EUâs applicable tariff for a
comparable load customer. EU may also require the Interconnection Customer to follow
a voltage or VAR schedule if such schedules are applicable to similarly situated
generators in the control area on a comparable basis and have been approved by the
Commission. The specific requirements for meeting a voltage or VAR schedule shall be
clearly specified in Attachment 3 of the âMississippi Distributed Generator
Interconnection Rule Level 2 and Level 3 Agreement for Interconnection of Distributed
Generator Facilities.â Under no circumstance shall these additional requirements for
voltage support or reactive power exceed the normal operating capabilities of the DGF.
The requirements in this paragraph may be additional to requirements in IEEE 1547.
Chapter 13: DISPUTES
100 A party shall attempt to resolve all disputes regarding interconnection as provided in the
MDGIR promptly, equitably, and in a good faith manner.
101 When a dispute arises, a party may seek immediate resolution through complaint
procedures available through the Commission by providing written notice to the
Commission and the other party stating the issues in dispute.
102 When disputes relate to the technical application of the MDGIR, the Commission may
designate a technical consultant to resolve the dispute. Upon Commission designation,
the parties shall use the technical consultant to resolve disputes related to interconnection.
Costs for dispute resolution conducted by the technical consultant shall be established by
the technical consultant and subject to review by the Commission. The EU and the
Interconnection Customer shall share equally the costs of an outside arbitrator unless they
mutually agree to a different payment arrangement.
103 Pursuit of dispute resolution shall not affect an Interconnection Customer with regard to
consideration of an Interconnection Request or an Interconnection Customer's Queue
Position.
TITLE 39: UTILITIES
PART IV: Mississippi Distributed Generator Interconnection and Distributed Generation
Subpart II: Mississippi Distributed Generation Rule
Chapter 01: Introduction
100 The Mississippi Distributed Generation Rule (MDGR) sets forth technical and procedural
requirements for qualified Distributed Generator Facilities (DGFs). These DGFs are also
subject to the requirements of the Mississippi Distributed Generator Interconnection Rule
(MDGIR).
Chapter 02: DEFINITIONS
The following capitalized terms, when used in this Rule, shall have the following meanings
unless the context clearly indicates otherwise. These definitions are in addition to those found in
the MGDIR, which also apply to the MDGR.
100 âBilling Periodâ means the monthly billing period used by an Electric Utility (EU) to
measure usage and any excess energy exported by a DGF to the EU, and to bill
customers.
101 âAvoided Cost of Wholesale Powerâ means the cost to an EU1 of electric energy that
the EU would generate itself or purchase from another source, such as from an
organized wholesale power market, but for the purchase from a Distributed Generation
Interconnection Customer (DGIC). In essence, the avoided cost is the marginal cost to
produce or purchase one more unit of electrical energy. When a DGIC delivers
electricity to an EU, the EU will reduce the equivalent amount of electricity that either
is generated at its most expensive operating plant that is not running for reliability
purposes or is purchased from an organized wholesale power market. For power
generated by an EU, the cost avoided consists of the cost of fuel needed to produce that
electricity and the corresponding portion of the plantâs operation and maintenance costs
and shall include an appropriate average line loss adjustment. For DGICs with solar PV
systems, the Avoided Cost of Wholesale Power and the corresponding average line loss
adjustment shall reflect the daytime energy production of a solar PV system. No
capacity credit is given as part of the calculation of Avoided Cost of Wholesale Power.
For an EU that is a member of a regional transmission organization (RTO), the Avoided
Cost of Wholesale Power shall be the average real-time locational marginal price
(LMP) calculated by the RTO for the EUâs load zone(s). Such LMP shall include an
appropriate average line loss adjustment. For DGICs with solar PV systems, such LMP
and the corresponding average line loss adjustment shall reflect the daytime energy
production of a solar PV system.
1 An EU is an electric utility within the meaning of Miss. Code Ann. section 77-3-3(d)(i) (Supp 2014).
102 âDistributed Generation Valueâ means an adjustment to be included in the Total
Value of Distributed Generation for benefits of distributed generation that, while
expected to occur, are currently non-quantifiable or difficult to quantify. The
Distributed Generation Value shall be equal to 2.5 cents per kilowatt hour, unless and
until modified upward or downward based on Mississippi-specific data, by separate
Order of the Commission, and after full notice and hearing. To provide sufficient
financial certainty to qualifying customers that install DGFs, this Distributed
Generation Value shall remain in place for a period of twenty-five (25) years from the
date the customer begins taking net generation service under the EUâs net generation
tariff.
103 âLow-to-Moderate Income Benefits Adderâ means an additional amount to be
included in the Total Value of Distributed Generation that shall flow to qualifying
customers whose household income is at or below 225% of the federal poverty level (or
similar requirement proposed by the EU to be approved by the Commission) who is
approved to take service under the EUâs net generation tariff. Beginning with the
effective date of this rule, the Low-to-Moderate Income Benefits Adder shall be equal
to 2 cents per kilowatt hour. To provide sufficient financial certainty to qualifying low-
to-moderate income customers that install DGFs, this Low-to-Moderate Income
Benefits Adder shall remain in place for a period of twenty-five (25) years from the date
a qualified DGIC customer begins taking service under the EUâs net generation tariff.
104 âTotal Value of Distributed Generationâ means the total amount â expressed in cents
per kilowatt hour - that shall be credited to EU customers as a result of excess energy
exported by a DGF to the EU, which shall include the Avoided Cost of Wholesale
Power plus the Distributed Generation Value plus, if applicable, the Low-to-Moderate
Income Benefits Adder, as further outlined in this rule.
105 âExit Feeâ means a fee that is paid by a customer that reduces load by using a DGF and
is intended to compensate the EU in whole or part for the loss of fixed cost contribution
from that customer. Exit fees are not allowed under this rule, unless otherwise
approved by the Commission.
106 âDistributed Generation Interconnection Customerâ or âDGICâ is any electricity
customer, such as an industrial, large commercial, residential or small commercial
customer, that generates electricity on the customerâs side of the meter using a
Renewable Energy source. The electricity customer must own or lease the DGF
producing the Renewable Energy on the electricity customerâs side of the meter in order
to qualify as a DGIC under this MDGR, unless otherwise approved by the Commission.
107 âNet Generationâ means measuring the real-time kilowatt-hours supplied by the EU to
the DGIC and the kilowatt-hours produced by the DGICâs DGF and exported to the EU
over the applicable Billing Period. Net Generation includes the real-time displacement
of kilowatt-hours that otherwise would be provided by the EU by kilowatt-hours that
were generated by the DGICâs DGF. An EU may employ a multi-channel meter for
separately measuring the DGICâs electric usage and excess energy exported to the EU.
Special metering requirements are obviated with the use of advanced metering
infrastructure or âsmart meters.â
108 âRenewable Energyâ means electric energy produced from solar technologies, wind
energy, geothermal technologies, wave or tidal action, hydro-power facilities, hydrogen,
and biomass. Any energy derived from fossil fuels is not considered renewable and
does not qualify under the MDGR.
109 âBiomassâ means a power source that is comprised of combustible solids or gases from
forest products, manufacturing waste, or byproducts; products from agricultural and
orchard crops; waste or co-products from livestock and poultry operations; waste or
byproducts from food processing; urban wood waste; municipal liquid waste treatment
operations; and landfill gas.
Chapter 03: NET GENERATION REQUIREMENTS
100 This MDGR sets forth the Net Generation requirements that apply to EUs that have
customers who self-generate electricity with Renewable Energy on the customerâs side
of the EUâs meter that wish to Net Generate, as indicated by the customer on the
Standard Application. These customers are referred to as DGICs in this rule.
101 All EUs shall offer Net Generation to any customer that seeks to generate electricity on
the customerâs side of the EUâs meter using Renewable Energy sources, provided:
1. For residential customers, Net Generation nameplate direct current capacity of the
aggregated DGFs at the customerâs premises shall be limited to the lesser of
110% of the customerâs annual peak demand or 20 kW and shall meet the
requirements of the MDGIR;
2. For non-residential customers, Net Generation nameplate direct current capacity
for the aggregate DGFs at the customerâs premises shall be limited to the lesser of
110% of the customerâs annual peak demand or 2 MW and shall meet the
requirements of the MDGIR.
3. In cases where Battery Energy Storage Systems (âBESSâ) are paired with a DGF,
the capacity of the BESS will not affect the total nameplate capacity limits of a
customerâs DGF under this MDGR.
102 EUs may refuse additional net generation requests if the total net generation direct
current capacity in kW, as reported through these requirements, exceeds at any time 3
percent of the EUâs total system peak demand expressed in kW recorded during the
prior calendar year.
103 Each EU shall develop a tariff for Net Generation and interconnection policies in
concordance with this MDGR and the MDGIR. Each EU shall make Net Generation
available to eligible DGICs on a first-come, first-served basis until such time as the
aforementioned cap has been reached.
104 An EU shall provide Net Generation at non-discriminatory rates that are identical, with
respect to rate structure and level, retail rate components, and any monthly fixed
charges, to the rates that a DGIC would be charged if not a DGIC, unless otherwise
approved by the Commission.
105 In each Billing Period, energy supplied to the DGIC from the EU as recorded on the
EUâs bi-directional meter or smart meter will be billed using appropriate commission-
approved rate and rider schedules. This provision means that energy self-supplied by
the DGIC, up to the amount supplied from the EU to the DGIC (e.g., through the
recording of meter Channel 1) will be credited to the DGIC at the full retail rate (i.e.,
effectively displacing energy supplied from the EU). During that same Billing Period,
any excess energy supplied from the DGIC to the EU and recorded on the EUâs bi-
directional net meter in kWh (e.g., through meter Channel 2) will be credited on the
DGICâs bill at the applicable Total Value of Distributed Generation expressed in cents
per kWh and shall be accounted for through the EUâs fuel adjustment clause. The
customerâs monthly bill will be the total of billing for any usage (i.e., as recorded on
meter Channel 1) subject to any customer charge and/or minimum bill provisions in the
EUâs rate and rider schedules less any credit due to the customer from excess energy
exported to the EU (i.e., as recorded on meter Channel 2). If the sum total of the
monthly bill is negative, any such amount will be carried over to the next Billing Period
and applied to any charges arising during the subsequent Billing Period.
106 Beginning with the effective date of this rule, Total Value of Distributed Generation
shall be equal to the Avoided Cost of Wholesale Power plus the Distributed Generation
Value. Further, the Distributed Generation Value shall be equal to 2.5 cents/kWh,
unless and until modified upward or downward based on Mississippi-specific data, by
separate Order of the Commission, and after full notice and hearing. Within sixty (60)
days of the effective date of this rule, each EU shall file with the Commission revised
net generation tariffs consistent with the provisions of this revised rule for consideration
and approval by the Commission.
107 Each new Billing Period shall begin with zero kWh credits to the DGIC; however,
subject to the provisions above, the customer may carry over any value of energy credit
arising from the prior Billing Period(s). When a customer closes his or her account with
the EU, if the DGIC has accumulated a dollar balance as a result of excess energy
delivered to the EU, any such balance, net of costs owed to the EU, shall be paid to the
DGIC.
108 Credit for any excess energy exported to the EU shall not be applied to reduce any fixed
monthly customer charges or minimum bill provisions imposed by the EU under
Commission-approved rate and rider schedules.
109 An EU shall offer a DGIC the choice of a time differentiated energy tariff rate or a
non-time-differentiated energy tariff rate, if the EU offers the choice to customers in the
same rate class as the DGIC. If a DGIC uses a retail billing arrangement that has time-
differentiated rates, the EU shall net any production from the DGFs against the
customerâs consumption within the same time-of-use period in the Billing Period and
any excess energy exported to the EU will be credited as described above.
110 Any renewable energy credits (RECs) created by the DGIC are and shall remain the
property of the DGIC, unless otherwise approved by the Commission. The EU shall not
charge any back-up, standby, or Exit Fees to a DGIC, unless otherwise approved by the
Commission.
111 An EU shall not charge a DGIC any fee or charge, or require additional equipment,
insurance or any other requirement, unless the fee, charge, or other requirement is
specifically authorized in this MDGR or the MDGIR, or the fee would apply to other
customers in the same rate class that are not DGICs, or unless otherwise approved by
the Commission.
112 All DGICs must be electrically interconnected with their EU pursuant to the provisions
of the MDGIR. All rules and regulations for interconnected DGFs within the MDGIR
apply to DGICs. Any Distribution System Upgrades, including additional equipment
needed that is associated with the export of electricity, shall be at the DGICâs expense,
per the MDGIR.
113 Each EU shall file with the Commission within three months of the effective date of this
revised rule the EUâs plan to inform its customers of the opportunities available under
the MDGR.
114 Nothing in this document shall abrogate any person's obligation to comply with all
applicable Federal or State laws, rules or regulations, including the MDGIR.
Chapter 04: METERS AND METERING
100 A DGIC shall be equipped with metering equipment that can measure the flow of
electricity in each direction at the same time. This may be accomplished through the
use of advanced metering infrastructure, or a single bi-directional meter that records
customer usage as well as excess energy exported to the EU (e.g., energy supplied to
the customer net of the output of the DGIC is measured on Channel 1 and excess
energy supplied by the DGIC to the EU in excess of the customerâs requirements is
measured on Channel 2).
101 An EU may choose to use an existing electric revenue meter if the following criteria are
met:
1. The meter is capable of measuring the flow of electricity both into and out of the
DGIC at the same time; and
2. The meter is accurate to within plus or minus five percent when measuring excess
energy flowing from the DGIC to the EU.
102 If the DGICâs existing electric revenue meter does not meet the requirements above, the
EU shall install a new revenue meter for the DGIC, at the DGICâs expense, within 10
business days after the interconnection agreement is executed and approved. If the EU
offers a time-differentiated rate chosen by the DGIC, the meter shall have the capability
to appropriately record energy flows in each direction during any time-differentiated
period.
103 Any subsequent revenue meter change will be at the EUâs expense, meaning such meter
expense will not be charged to an individual DGIC but shall become part of the EUâs
overall cost of service and subsequent revenue requirement.
Chapter 05: REPORTING REQUIREMENTS
100 Each EU with one or more DGICs connected to its grid shall submit to the Mississippi
Public Service Commission a Net Generation report on or before March 1st of each
calendar year. The report shall include the following information regarding DGICs
during the reporting period:
1. The total energy expressed in kilowatt-hours supplied to the EUâs grid by DGICs
and a description of any estimation methodology used;
2. The total number of DGICs that were paid for excess energy exported to the EU
at the end of any Billing Period(s) during the prior calendar year;
3. The total dollar amount by month that the EU paid to REDGICs for excess energy
exported to the EU during the prior calendar year;
4. The total number of net generation DGFs by resource type that were
interconnected at the end of the prior calendar year;
5. The total rated nameplate direct current generating capacity of net generation
DGFs installed during the prior calendar year broken out by resource type; and
6. The percentage of the EUâs total system peak demand from the prior calendar
year represented by the total rated nameplate direct current generating capacity of
net generation DGFs.
7. The total number of REDGICs who received the Low-to-Moderate Income
Benefits Adder that calendar year.
101 For purposes of these reporting requirements, any estimates shall be made using
Commission-approved protocols unless no such protocols are available, in which case
the estimates shall be accompanied by detailed calculations demonstrating how the
estimates were made.
Chapter 06: CUSTOMER PROGRAMS
100 While the Commission recognizes that it cannot order an EU to construct or acquire
specific resources, the Commission finds that economic benefits warrant reasonably
incentivizing energy independence through cost reductions for renewable energy for K-
12 public schools through power purchase agreements, renewable energy for low-to-
moderate income residential customers and residential battery storage systems that can
accommodate and are compatible with any existing or future EU demand side
management or demand response programs. Any renewable energy for public school
programs or low-to-moderate income residential renewable energy programs will be
subject to the three percent (3%) participation cap described, previously, herein; however,
nothing herein prevents an EU from extending these programs if it chooses. These
programs should begin on January 1, 2023, and should continue for no more than five (5)
years.
101 Compliance with tariffs implementing a renewable energy program described above and
the execution and filing of a power purchase agreement shall be deemed sufficient to
satisfy any certificate requirements subject to Commission jurisdiction and authority.
102 Public Schools participating in any solar for public schools program are admonished to
treat any savings or revenues as supplementing, not supplanting, school budgets related to
educational expenses and investments focused on the classroom, such as classroom
supplies.
103 EUs should be allowed to recover all reasonable and prudent costs incurred by them and
resulting rates shall reflect on a prospective basis the reduction in energy sales volume
that will result from all distributed generation. EUs all shall be allowed to recover all
investments relating to this rule and any programs discussed above, including an
opportunity to earn a reasonable return thereon. Such investments shall include, but not
be limited to, equipment, incentives, marketing and delivery, direct installation costs, and
any administration costs.
Chapter 07: CONSUMER PROTECTIONS
100 In an effort to foster continued monitoring and consideration of the fairness and efficacy
of this rule, representatives of the Commission, the Mississippi Public Utilities Staff,
the Office of the Mississippi Attorney General, and other qualified stakeholders shall
meet annually to identify and discuss issues related to net generation that may warrant
further Commission attention and/or review. Members of the Commission Staff and
Public Utilities Staff who participated in the working group shall present any joint
recommendations on such issues to the Commission by January 30th each year.
101 In order to offer all customers some level of consumer protection, any entity interacting
with customers in any transaction or proposed transaction related to this rule or any
program or implementing tariff associated herewith, including but not limited to solar
developers and solar installers, shall take the following actions, as applicable:
1. Must file with the Commission a point of contact to whom the Commission may
direct customer complaints for resolution;
2. Must register with the Secretary of State to do business in Mississippi and list a
registered agent for service of process; and
3. Must file annually with the Commission, and provide a copy to the consumer
protection division of the Office of the Mississippi Attorney General, any
marketing material with attestation to its accuracy.
Chapter 08: REOPENER
100 The Commission may revisit this rule five years from its effective date.
TITLE 39: UTILITIES
PART IV: Mississippi Distributed Generator Interconnection and Net Metering
Distributed Generation
Subpart I: Mississippi Distributed Generator Interconnection Rule
Chapter 01: Introduction
The Mississippi Distributed Generation Interconnection Rule (MDGIR) sets forth standards to
establish the technical and procedural requirements for Distributed Generator Facilities (DGFs) to
be interconnected and operated in Parallel with the Electric Distribution System (EDS) owned or
operated by Electric Utilities (EUs) in Mississippi under the jurisdiction of the Mississippi Public
Service Commission (Commission). Capitalized terms used in this rule have the meaning
specified in the section titled DEFINITIONS.
Chapter 02: Definitions
When used in this chapter, the following terms and phrases shall have the following meaning:
100 âAdverse System Impactâ means a negative effect, due to technical or operational limits
on conductors or equipment being exceeded, that compromises the safety and reliability
of the EDS.
101 âApplicable Laws and Regulationsâ means all duly promulgated and applicable
federal, state and local laws, regulations, rules, ordinances, codes, decrees, judgments,
directives, or judicial or administrative orders, permits and other duly authorized actions
of any Governmental Authority.
102 âCertificate of Completionâ means a certificate in a completed form approved by the
Commission containing information about the Interconnection Equipment to be used, its
installation and local inspections.
103 âCertified Interconnection Equipmentâ or âCertified Equipmentâ or âCertifiedâ
means a designation that the Interconnection Equipment meets the following
requirements:
1. The Interconnection Equipment has been tested by a Nationally Recognized Testing
Laboratory (NRTL) recognized by the United States Occupational Safety and Health
Administration (OSHA) in accordance with the following relevant codes and standards:
a. IEEE 1547.1 Standard for Conformance Tests Procedures for Equipment
Interconnecting Distributed Resources with Electric Power Systems; and
b. Underwriters Laboratories (âULâ), UL 1741 Inverters, Converters, and Controllers
for Use in Independent Power Systems;
2. The Interconnection Equipment shall meet the requirements of the most current
approved version of each code and standard listed above, as amended and
supplemented at the time the Interconnection Request is submitted to be deemed
Certified;
3. The Interconnection Equipment has been labeled and is publicly listed by such NRTL
at the time of the interconnection application;
4. The Interconnection Customer verifies that the intended use of the Interconnection
Equipment falls within the use or uses for which the Interconnection Equipment is
labeled and is listed by the NRTL;
5. If the Interconnection Equipment is an integrated equipment package such as an
inverter, then the Interconnection Customer shall show that the generator or other
electric source being utilized is compatible with the Interconnection Equipment and is
consistent with the testing and listing specified for this type of Interconnection
Equipment;
6. If the Interconnection Equipment includes only interface components (switchgear,
multi-function relays, or other interface devices), an Interconnection Customer shall
demonstrate that the generator or other electric source being utilized is compatible with
the Interconnection Equipment and is consistent with the testing and listing specified
for this type of Interconnection Equipment; and
7. Certified Interconnection Equipment shall not require further design testing or
Production Testing, as specified by IEEE Standard 1547 Sections 5.1 and 5.2, or
additional Interconnection Equipment modification to meet the requirements.
However, nothing herein shall preclude the need for an on-site Witness Test or
operational test by the Interconnection Customer.
104 âCommissionâ means the Mississippi Public Service Commission.
105 âCommissioning Testsâ means the tests applied to a DGF by an Interconnection
Customer after construction is completed to verify that the DGF does not create Adverse
System Impacts. At a minimum, the scope of the Commissioning Tests performed shall
include the commissioning test specified by IEEE Standard 1547 section 5.4
âCommissioning Tests.â
106 âDistributed Generator Facilityâ or âDGFâ means the equipment used by an
Interconnection Customer to generate or store electricity that operates in Parallel with the
EDS. A DGF typically includes an electric generator, prime mover, and the
Interconnection Equipment required to safely interconnect with the EDS or local electric
power system.
107 âDistribution System Upgradeâ means a required addition or modification to the EU's
EDS at or beyond the Point of Common Coupling (PCC) to accommodate the
interconnection of a DGF. Distribution System Upgrades do not include Interconnection
Facilities.
108 âElectric Utilityâ or âEUâ means an electric public utility that distributes electricity to
customers and is subject to the jurisdiction of the Commission pursuant to the provisions
of Mississippi Code Annotated §§ 77-3-1, et seq.
109 âElectric Distribution Systemâ or âEDSâ means the facilities and equipment used to
transmit electricity to ultimate usage points such as homes and industries from
interchanges with higher voltage transmission networks that transport bulk power over
longer distances. The voltage levels at which EDSs operate differ among areas but
generally carry less than 69 kilovolts of electricity. EDS has the same meaning as the
term Area EPS, as defined in 3.1.6.1 of IEEE Standard 1547.
110 âFacilities Studyâ means an engineering study conducted by the EU to determine the
required modifications to the EUâs EDS, including the cost and the time required to build
and install such modifications as necessary to accommodate an Interconnection Request.
111 âFault Currentâ means the electrical current that flows through a circuit during an
electrical fault condition. A fault condition occurs when one or more electrical conductors
contact ground or each other. Types of faults include phase to ground, double-phase to
ground, three-phase to ground, phase-to-phase, and three-phase.
112 âFeasibility Studyâ means a study performed to identify the existence of obvious
adverse impacts before additional studies are undertaken for the proposed project to
continue in the process.
113 âGovernmental Authorityâ mean any federal, state, local or other governmental
regulatory or administrative agency, court, commission, department, board, or other
governmental subdivision, legislature, rulemaking board, tribunal, or other governmental
authority having jurisdiction over the Parties, their respective facilities, or the respective
services they provide, and exercising or entitled to exercise any administrative, executive,
police, or taxing authority or power; provided, however, that such term does not include
the Interconnection Customer, EU or any affiliate thereof.
114 âIEEE Standard 1547â means the Institute of Electrical and Electronics Engineers, Inc.
(IEEE) Standard 1547 (2003) ''Standard for Interconnecting Distributed Resources with
Electric Power Systems,'' as amended and supplemented at the time the Interconnection
Request is submitted.
115 âIEEE Standard 1547.1â means the IEEE Standard 1547.1 (2005) ''Conformance Test
Procedures for Equipment Interconnecting Distributed Resources with Electric Power
Systems,'' as amended and supplemented at the time the Interconnection Request is
submitted.
116 âInterconnection Agreementâ or âAgreementâ means a form of interconnection
agreement approved by the Commission which is applicable to Interconnection Requests
pertaining to DGFs. The agreement between the Interconnection Customer and the EU
governs the connection of the DGF to the EUâs EDS, as well as the ongoing operation of
the DGF after it is connected to the EUâs EDS.
117 âInterconnection Applicationâ or âApplicationâ means a form of interconnection
application approved by the Commission which is applicable to Interconnection Requests
pertaining to DGFs. This application provides the information needed by the EU to
review the request for interconnection. For the Level 1 review process, the Application
and Agreement are part of the same document.
118 âInterconnection Customerâ means an entity that submits an Interconnection Request
for a DGF to an EU's EDS.
119 âInterconnection Equipmentâ means a group of equipment, components, or an
integrated system connecting an electric generator with a local electric power system or
an EDS that includes all interface equipment including switchgear, protective devices,
inverters or other interface devices. Interconnection equipment may be installed as part
of an integrated equipment package that includes a generator or other electric source.
120 âInterconnection Facilitiesâ means facilities and equipment required by the EU to
accommodate the interconnection of a DGF. Collectively, Interconnection Facilities
include all facilities and equipment between the DGF and the PCC, including
modification, additions, or upgrades that are necessary to physically and electrically
interconnect the DGF to the EDS. Interconnection facilities are sole use facilities and do
not include Distribution System Upgrades.
121 âInterconnection Requestâ means an Interconnection Customer's request, in the form
of an Application approved by the Commission, requesting the interconnection of a new
DGF, or to increase the capacity or modify operating characteristics of an existing
approved DGF that is interconnected with the EU's EDS.
122 âLine Sectionâ means that portion of an EU's distribution system connected to an
Interconnection Customer, bounded by automatic sectionalizing devices or the end of the
distribution line.
123 âLocal Electric Power Systemâ or âLocal EPSâ means facilities that deliver electric
power to a load that are contained entirely within a single premises or group of premises.
Local electric power system has the same meaning as the term local electric power system
defined in 3.1.6.2 of IEEE Standard 1547.
124 âMinor Equipment Modificationâ means changes to the DGF that do not have a
material impact on safety or reliability of the EDS.
125 âMississippi Distributed Generation Interconnection Rule (MDGIR)â means the
most current version of the procedures for interconnecting Distributed Generator
Facilities adopted by the Mississippi Public Service Commission.
126 âNameplate Capacityâ means the maximum rated output of a generator, prime mover,
or other electric power production equipment under specific conditions designated by the
manufacturer and is usually indicated on a nameplate physically attached to the power
production equipment.
127 âNationally Recognized Testing Laboratoryâ or âNRTLâ means a qualified private
organization that meets the requirements of the Occupational Safety and Health
Administration's (OSHA) regulations. NRTLs perform independent safety testing and
product certification. Each NRTL shall meet the requirements as set forth by OSHA in
the NRTL program.
128 âParallel Operationâ or âParallelâ means the sustained state of operation over 100
milliseconds, which occurs when a DGF is connected electrically to the EDS and thus
has the ability for electricity to flow from the DGF to the EDS.
129 âPoint of Common Couplingâ or âPCCâ means the point where the DGF is electrically
connected to the EDS. Point of common coupling has the same meaning as defined in
3.1.13 of IEEE Standard 1547.
130 âPrimary Lineâ means a distribution line rated at greater than 600 volts.
131 âProduction Testâ means production test as defined in IEEE Standard 1547.
132 âQueue Positionâ means the order of a valid Interconnection Request, relative to all
other pending valid Interconnection Requests, that is established based upon the date and
time of receipt of the valid Interconnection Request by the EU.
133 âRadial Distribution Circuitâ means a circuit configuration where independent feeders
branch out radially from a common source of supply. From the standpoint of a utility
system, the area described is between the generating source or intervening substations
and the customerâs entrance equipment. A radial distribution system is the most common
type of connection between a utility and load in which power flows in one direction from
the utility to the load.
134 âScoping Meetingâ means a meeting between representatives of the Interconnection
Customer and EU conducted for the purpose of discussing alternative interconnection
options, exchanging information including any EDS data and earlier study evaluations
that would be reasonably expected to impact interconnection options, analyzing
information, and determining the potential feasible points of interconnection.
135 âSecondary Lineâ means a service line subsequent to the Primary Line that is rated for
600 volts or less, also referred to as the customerâs service line.
136 âSystem Impact Studyâ means a study that identifies the electric system impacts that
would result if the proposed DGF were interconnected without DGF modifications or
EDS modifications, focusing on the Adverse System Impacts identified in the Feasibility
Study.
137 âUL Standard 1741â means Underwriters Laboratories' standard titled ''Inverters
Converters, and Controllers for Use in Independent Power Systems,â as amended and
supplemented at the time the Interconnection Request is submitted.
138 âWitness Testâ means verification (through on-site observation) by the EU that the
installation evaluation required by IEEE Standard 1547 Section 5.3 and the
Commissioning Test required by IEEE Standard 1547 Section 5.4, have been adequately
performed. For Interconnection Equipment that has not been Certified, the Witness Test
shall also include the verification by the EU of the on-site design tests as required by
IEEE Standard 1547 Section 5.1 and verification by the EU of Production Tests required
by IEEE Standard 1547 Section 5.2. All tests verified by the EU are to be performed in
accordance with the applicable test procedures specified by IEEE Standard 1547.1.
Chapter 03: INTERCONNECTION REQUESTS, FEES, AND FORMS
100 Interconnection Customers seeking to interconnect a DGF shall submit an
Interconnection Request to the EU that owns the EDS to which interconnection is sought,
using an application approved by the Commission. Electronic versions of such
Commission-approved Application forms shall be posted on the EUâs website. The EU
shall establish processes for accepting Interconnection Requests electronically,
specifically through online submission. Such online submission portal should include, at
a minimum, information on interconnection times and procedures, a repository of relevant
forms that allow for electronic entry of text, an application status tracker, and a searchable
interconnection queue that is updated on a regular basis.
101 When an Interconnection Customer is not currently a customer of the EU at the proposed
PCC, upon request from the EU, the Interconnection Customer shall provide proof of site
control evidenced by a property tax bill, deed, lease agreement, or other legally binding
contract.
102 Interconnection fees shall be governed as follows for all Interconnection Requests and
shall be published on each EUâs website:
1. An EU may not charge an application, or other fee, to an applicant that requests
Level 1 interconnection review. However, if an application for Level 1
interconnection review is denied because it does not meet the requirements for
Level 1 interconnection review and the applicant resubmits the application under
another review procedure in accordance with the MDGIR, the EU may impose a
fee for the resubmitted application, consistent with this section.
2. For a Level 2 interconnection review, the EU may charge fees of up to $50.00 plus
$1.00 per kilowatt of the customer-generator facility's capacity, plus the reasonable
cost of any required minor modifications to the electric distribution system or
additional review. Costs for such minor modifications or additional review will be
based on the EU's non-binding, good faith estimates and the ultimate actual
installed costs. Costs for engineering work done as part of any additional review
will not exceed $100.00 per hour.
3. For a Level 3 interconnection review, the EU may charge fees of up to $100.00 plus
$2.00 per kilowatt of the customer-generator facility's capacity, as well as charges
for actual time spent on any required impact or facilities studies. Costs for
engineering work done as part of an impact study or interconnection facilities study
will not exceed $100.00 per hour. If the EU must install facilities in order to
accommodate the interconnection of the customer generating facility, the cost of
such facilities will be the responsibility of the applicant.
103 When the EU determines that an Interconnection Request is complete, a modification of
DGF design by the Interconnection Customer other than a Minor Equipment Modification
that is not agreed to in writing by the EU shall require submission of a new
Interconnection Request.
Chapter 04: INTERCONNECTION REVIEW LEVELS
100 The EU shall review Interconnection Requests using one of the three levels of review
procedures established below. The EU shall first use the level of DGF Agreement
specified by the Interconnection Customer in the Application. The EU may not impose
additional requirements not specifically authorized unless the EU and the Interconnection
Customer mutually agree to do so in writing.
101 When an Interconnection Request is for an increase in capacity for an existing DGF, the
Interconnection Request shall be evaluated on the basis of the new total Nameplate
Capacity of the DGF.
102 When an Interconnection Request is for a DGF that includes multiple energy production
devices at a site for which the Interconnection Customer seeks a single PCC, the
Interconnection Request shall be evaluated on the basis of the aggregate Nameplate
Capacity of the multiple devices.
Chapter 05: LEVEL 1 INTERCONNECTION REVIEWS
100 The EU shall use Level 1 review procedures to evaluate Interconnection Requests when:
1. The DGF is inverter-based;
2. The DGF has a Nameplate Capacity of 20 kW or less; and
3. The Interconnection Equipment proposed for the DGF is Certified.
101 For Level 1 Interconnection Review, the EU shall first evaluate the potential for Adverse
System Impacts using the following screens, which must be satisfied:
1. For interconnection of a proposed DGF to a Line Section on a Radial Distribution
Circuit, the aggregated generation on the Line Section, including the proposed
DGF, shall not exceed 15% of the Line Section annual peak load.
2. When a proposed DGF is to be interconnected to a single-phase shared Secondary
Line, the aggregate generation capacity on the shared Secondary Line, including
the proposed DGF, may not exceed 20 kW.
3. When a proposed DGF is single-phase and is to be interconnected to a center tap
neutral of a 240 volt service, its addition may not create an imbalance between the
two sides of the 240 volt service of more than 20% of the nameplate rating of the
service transformer.
4. Construction of facilities by the EU on its own system is not required to
accommodate the DGF.
102 The Level 1 Interconnection Review shall then be conducted in accordance with the
following procedures:
1. An EU shall, within 10 business days after receipt of the Interconnection Request,
inform the Interconnection Customer in writing or by electronic mail that the
Interconnection Request is complete or incomplete and indicate what, if any,
materials are missing.
2. When an Interconnection Request is complete, the EU shall assign a Queue
Position.
3. The EU shall, within 15 business days after notifying a Level 1 applicant that the
application is complete, indicate that the DGF equipment meets all Level 1 criteria,
verify the DG can be interconnected safely and reliably using Level 1 screens, and
provide a conditionally approved Level 1 Interconnection Application Form and
Agreement to the Interconnection Customer.
103 Unless the EU determines and demonstrates to the Interconnection Customer that a DGF
cannot be interconnected safely or reliably to its system and provides a letter to the
Interconnection Customer explaining its reasons for denying an Interconnection Request,
the EUâs final approval of the Interconnection Agreement is subject to the following
conditions:
1. âThe DGF has been approved by local or municipal electric code officials with
jurisdiction over the interconnection;
2. The EU has received the required information on the Certificate of Completion
from the Interconnection Customer. Completion of local inspections may be
designated on inspection forms used by local inspecting authorities; and
3. The EU has completed its Witness Test in accordance with the MDGIR.
104 Within 10 business days of the estimated commissioning date indicated on the
Interconnection Request, the EU shall, upon reasonable notice and at a mutually
convenient time, conduct a Witness Test of the DGF to ensure that all equipment has been
appropriately installed and that all electrical connections have been made in accordance
with applicable codes.
105 When a DGF is not approved under a Level 1 review, the Interconnection Customer may
submit a new Interconnection Request for consideration under Level 2 or Level 3
procedures.
Chapter 06: LEVEL 2 INTERCONNECTION REVIEWS
100 The EU shall use the Level 2 Interconnection Review procedure to evaluate an
Interconnection Request when:
1. The DGF has a Nameplate Capacity rating of 2 MW or less;
2. The Interconnection Equipment proposed for the DGF is Certified; and
3. The aggregated total of the Nameplate Capacity of all of the generators on the
circuit, including the proposed DGF, is 2 MW or less.
101 No construction of facilities by an EU shall be required to accommodate the DGF, except
as permitted by an additional review for minimal modifications of the EDS, as described
in these Level 2 procedures.
102 For Level 2 Interconnection Review, the EU first shall evaluate the potential for Adverse
System Impacts using the following screens, which must be satisfied:
1. For interconnection of a proposed DGF to a radial distribution circuit, the
aggregated generation on the Line Section, including the proposed DGF, may not
exceed 15% of the Line Section annual peak load.
2. The proposed DGF, in aggregation with other generation on the distribution circuit,
may not contribute more than 10% to the distribution circuit's maximum Fault
Current at the point on the Primary Line nearest the Point of Common Coupling
(PCC).
3. The proposed DGF, in aggregate with other generation on the distribution circuit,
may not cause any distribution protective devices and equipment (including
substation breakers, fuse cutouts, and line reclosers), or other customer equipment
on the EDS to be exposed to Fault Currents exceeding 87.5% of the short circuit
interrupting capability. The Interconnection Request may not receive approval for
interconnection on a circuit that already exceeds 87.5% of the short circuit
interrupting capability.
4. When a DGF is to be connected to three-phase, three-wire primary EU distribution
lines, a three-phase or single-phase generator shall be connected phase-to-phase.
5. When a DGF is to be connected to three-phase, four-wire primary EU distribution
lines, a three-phase or single-phase generator shall be connected line-to-neutral and
shall be effectively grounded.
6. When the proposed DGF is to be interconnected on a single-phase shared
Secondary Line, the aggregate generation capacity on the shared Secondary Line,
including the proposed DGF, shall not exceed 20 kW.
7. When a proposed DGF is single-phase and is to be interconnected on a center tap
neutral of a 240 volt service, its addition may not create an imbalance between the
two sides of the 240 volt service of more than 20% of the nameplate rating of the
service transformer.
8. A DGF, in aggregate with other generation interconnected to the distribution side
of a substation transformer feeding the circuit where the DGF proposes to
interconnect, may not exceed 10 MW in an area where there are known or posted
transient stability limitations to generating units located in the general electrical
vicinity.
9. No construction of facilities by an EU on its own system shall be required to
accommodate the DGF.
103 The Level 2 Interconnection Review shall then be conducted in accordance with the
following procedures:
1. An EU shall, within 10 business days after receipt of the Interconnection Request,
inform the Interconnection Customer in writing or by electronic mail that the
Interconnection Request is complete or incomplete and indicate what, if any,
materials are missing. As part of this process, the EU shall assign a Queue Position.
The Queue Position of the Interconnection Request shall be used to determine the
potential Adverse System Impact of the DGF based on the relevant screening
criteria. If there are higher queued Interconnection Requests on the same radial line
circuit, the EU shall evaluate the Interconnection Requests by performing any Level
2 screens requiring aggregate capacity calculations and determine if the DGF in
combination with the higher queued Interconnection Requests exceeds any of the
aggregate capacity requirements. If an aggregate capacity requirement is exceeded,
the EU shall notify the Interconnection Customer and shall not be obligated to meet
the timeline for reviewing the Interconnection Request until such time as the EU
has completed the review of all other Interconnection Requests that have a higher
Queue Position and impact the aggregate capacity calculation that has been
exceeded.
2. At the time an EU determines additional information is required to complete an
evaluation, the EU shall request the information. The time necessary to complete
the evaluation may be extended by mutual agreement of the parties, but only to the
extent of the time required for receipt of the additional information. During an
extension of time to submit additional information, the EU may not alter the
Interconnection Customer's Queue Position.
3. Within 20 business days after the EU notifies the Interconnection Customer that it
has received a completed Interconnection Request, the EU shall:
a. Evaluate the Interconnection Request using the Level 2 screening
criteria;
b. Review any analysis provided by the Interconnection Customer, using the
same criteria used by the customer; and
c. Provide the Interconnection Customer with the EU's evaluation,
including a comparison of the results of its own analyses with those of
Interconnection Customer, if applicable. When an EU does not have a
record of receipt of the Interconnection Request and the Interconnection
Customer can demonstrate that the original Interconnection Request was
delivered, the EU shall expedite its review to complete the evaluation of
the Interconnection Request within 20 business days of the
Interconnection Customer's re-submittal.
104 The EU shall provide the Interconnection Customer a DGF Interconnection Agreement
within 5 business days of its determination that the Interconnection Request passes the
Level 2 screening criteria.
105 When a DGF has failed to meet one or more of the Level 2 screens, the EU shall offer to
perform additional review for minimal modifications of the EDS to determine whether
minimal modifications to the EDS would enable the interconnection to be made
consistent with safety, reliability and power quality criteria. The EU shall provide the
Interconnection Customer with a nonbinding, good faith estimate of the costs of
additional review for minimal modifications of the EDS. The EU shall undertake the
additional review for minimal modifications of the EDS or the modifications only after
the Interconnection Customer consents to pay for the review and modifications.
106 If the DGF fails one or more of the Level 2 screening criteria but the EU determines that
minimal modifications to the EDS would enable the DGF to interconnect safely and
reliably, the EU shall provide the Interconnection Customer a DGF Interconnection
Agreement within 5 business days of making that determination.
107 If the EU finds that the DGF cannot be interconnected with minimal modifications to the
EDS, the EU shall provide the Interconnection Customer a letter explaining its reasons
for denying the Interconnection Request. The Interconnection Customer may submit a
new Interconnection Request for consideration under a Level 3 interconnection review.
108 An Interconnection Customer shall have 30 business days to sign and return the
Agreement. When an Interconnection Customer does not sign the DGF Interconnection
Agreement within 30 business days, the Interconnection Request shall be deemed
withdrawn unless the Interconnection Customer requests in writing prior to the expiration
of the 30 business day period to extend the deadline. The EU may not unreasonably deny
the request for extension.
109 The DGF Interconnection Agreement shall not become final until:
5. The milestones agreed to in the DGF Interconnection Agreement are satisfied;
6. The DGF is approved by electric code officials with jurisdiction over the
interconnection;
7. The Interconnection Customer provides a Certificate of Completion to the EU.
Completion of local inspections may be designated on inspection forms used by
local inspecting authorities; and
8. The Witness Test was successfully completed per the terms and conditions found
in the Agreement.
110 If the DGF is not approved under a Level 2 review, the EU shall provide the
Interconnection Customer a letter explaining its reasons for denying the Interconnection
Request. The Interconnection Customer may submit a new Interconnection Request for
consideration under a Level 3 interconnection review. The Queue Position assigned to
the Level 2 Interconnection Request shall be retained provided the request is made within
15 business days of notification that the current Interconnection Request is denied.
Chapter 07: LEVEL 3 INTERCONNECTION REVIEWS
100 The EU shall use the Level 3 review procedure to evaluate an Interconnection Request
when the Interconnection Customer requests Level 3 review.
101 The Level 3 review shall be conducted in accordance with the following process:
1. An EU shall, within 10 business days of receipt of an Interconnection Request,
inform the Interconnection Customer in writing or by electronic means that the
Interconnection Request is complete or incomplete and indicate what, if any,
materials are missing.
2. When the Interconnection Request is deemed not complete, the EU shall provide
the Interconnection Customer with a written list detailing information required to
complete the Interconnection Request. The Interconnection Customer shall have
10 business days to provide appropriate data in order to complete the
Interconnection Request, or the Interconnection Request shall be considered
withdrawn. The parties may agree to extend the time for receipt of the additional
information. The Interconnection Request shall be deemed complete when the
required information has been provided by the Interconnection Customer, or the
parties have agreed that the Interconnection Customer may provide additional
information at a later time.
3. When an Interconnection Request is complete, the EU shall assign a Queue
Position. The Queue Position of an Interconnection Request shall be used to
determine the cost responsibility necessary for the facilities to accommodate the
interconnection. The EU shall notify the Interconnection Customer about other
higher-queued Interconnection Customers that have the potential to impact the cost
responsibility.
4. Level 3 Scoping Meetings shall be conducted as follows:
a. By mutual agreement of the parties, the Scoping Meeting,
interconnection Feasibility Study, interconnection System Impact Study,
or interconnection Facilities Study provided for in a Level 3 review may
be waived;
b. If agreed to by the parties, a Scoping Meeting shall be held within 10
business days, or other mutually agreed to time, after the EU has notified
the Interconnection Customer that the Interconnection Request is deemed
complete, The purpose of the meeting shall be to review the
Interconnection Request, existing studies relevant to the Interconnection
Request, and the results of the Level 1 or Level 2 screening criteria;
c. When the parties agree at a Scoping Meeting that an interconnection
Feasibility Study shall be performed, the EU shall provide to the
Interconnection Customer, no later than 5 business days after the Scoping
Meeting, an interconnection Feasibility Study agreement, including an
outline of the scope of the study and a nonbinding good faith estimate of
the cost to perform the study;
d. When the parties agree at a Scoping Meeting that an interconnection
Feasibility Study is not required, the EU shall provide to the
Interconnection Customer, no later than 5 business days after the Scoping
Meeting, an interconnection System Impact Study agreement, including
an outline of the scope of the study and a nonbinding good faith estimate
of the cost to perform the study; and
e. When the parties agree at the Scoping Meeting that an interconnection
Feasibility Study and System Impact Study are not required, the EU shall
provide to the Interconnection Customer, no later than 5 business days
after the Scoping Meeting, an interconnection Facilities Study agreement
including an outline of the scope of the study and a nonbinding good faith
estimate of the cost to perform the study.
5. Any required interconnection studies shall be carried out using the following
guidelines:
a. An interconnection Feasibility Study shall include the following
analyses and conditions for the purpose of identifying and addressing
potential Adverse System Impacts to the EU's EDS that would result from
the interconnection:
b. Initial identification of any circuit breaker short circuit capability limits
exceeded as a result of the interconnection;
c. Initial identification of any thermal overload or voltage limit violations
resulting from the interconnection;
d. Initial review of grounding requirements and system protection;
e. Description and nonbinding estimated cost of facilities required to
interconnect the DGF to the EU's EDS in a safe and reliable manner; and
f. Additional evaluations at the expense of the Interconnection Customer,
when an Interconnection Customer requests that the interconnection
Feasibility Study evaluate multiple potential points of interconnection.
6. An interconnection System Impact Study shall evaluate the impact of the proposed
interconnection on both the safety and reliability of the EU's EDS. The study shall
identify and detail the system impacts that result when the proposed DGF is
interconnected without project or system modifications, focusing on the Adverse
System Impacts identified in the interconnection Feasibility Study and potential
impacts including those identified in the Scoping Meeting. The study shall consider
all generating facilities that, on the date the interconnection System Impact Study
is commenced, are directly interconnected with the EU's system, have a pending
higher Queue Position to interconnect to the system, and have a signed a DGF
Interconnection Agreement.
a. An interconnection System Impact Study shall be performed when the
interconnection Feasibility Study identifies a potential distribution system
Adverse System Impact. The EU shall send the Interconnection Customer
an interconnection System Impact Study agreement within 5 business
days of transmittal of the interconnection Feasibility Study report. The
agreement shall include an outline of the scope of the study and a good
faith estimate of the cost to perform the study. The System Impact Study
shall include:
i.
A load flow study;
ii.
Identification of affected systems;
iii.
An analysis of equipment interrupting ratings;
iv.
A protection coordination study;
v.
Voltage drop and flicker studies;
vi.
Protection and set point coordination studies;
vii.
Grounding reviews; and
viii.
Impact on system operation.
b.An interconnection System Impact Study shall consider the following
criteria:
i.
A short circuit analysis;
ii.
A stability analysis;
iii.
Alternatives for mitigating Adverse System Impacts on
affected systems;
iv.
Voltage drop and flicker studies;
v.
Protection and set point coordination studies; and
vi.
Grounding reviews.
c. The interconnection System Impact Study shall provide the following:
i.
The underlying assumptions of the study;
ii.
The results of the analyses;
iii.
A list of any potential impediments to providing the
requested interconnection service;
iv.
Required Distribution System Upgrades; and
v.
A nonbinding good faith estimate of cost and time to
construct any required Distribution System Upgrades.
d.The parties shall use an interconnection System Impact Study agreement
approved by the Commission.
7. The interconnection Facilities Study shall be conducted as follows:
a. Within 5 business days of completion of the interconnection System
Impact Study, the EU shall send a report to the Interconnection Customer
with an interconnection Facilities Study agreement, which includes an
outline of the scope of the study and a nonbinding good faith estimate of
the cost to perform the study;
b.The interconnection Facilities Study shall estimate the cost of the
equipment, engineering, procurement and construction work including
overheads needed to implement the conclusions of the interconnection
Feasibility Study and the interconnection System Impact Study to
interconnect the DGF. The interconnection Facilities Study shall
identify:
i.
The electrical switching configuration of the equipment,
including transformer, switchgear, meters and other station
equipment;
ii.
The nature and estimated cost of the EU's Interconnection
Facilities and Distribution System Upgrades necessary to
accomplish the interconnection; and
iii.
An estimate of the time required to complete the
construction and installation of the facilities;
c. The parties may agree to permit an Interconnection Customer to
separately arrange for a third party to design and construct the required
Interconnection Facilities. The EU may review the design of the facilities
under the interconnection Facilities Study agreement. When the parties
agree to separately arrange for design and construction and to comply with
security and confidentiality requirements, the EU shall make all relevant
information and required specifications available to the Interconnection
Customer to permit the Interconnection Customer to obtain an
independent design and cost estimate for the facilities, which shall be built
in accordance with the specifications;
d. Upon completion of the interconnection Facilities Study, and with the
agreement of the Interconnection Customer to pay for the
Interconnection Facilities and Distribution System Upgrades identified
in the interconnection Facilities Study, the EU shall provide the
Interconnection Customer with a DGF Interconnection Agreement
within 5 business days; and
8. When an EU determines, as a result of the interconnection studies conducted under
a Level 3 review, that it is appropriate to interconnect the DGF, the EU shall provide
the Interconnection Customer with a DGF Interconnection Agreement. If the
Interconnection Request is denied, the EU shall provide a written explanation
setting forth the reasons for denial;
9. An Interconnection Customer shall have 30 business days from receipt of the DGF
Interconnection Agreement, unless another mutually agreeable time frame is
reached, to sign and return the DGF Interconnection Agreement to the EU. If an
Interconnection Customer does not sign the DGF Interconnection Agreement
within 30 business days, the Interconnection Request shall be deemed withdrawn
unless the Interconnection Customer requests in writing, prior to the expiration of
the 30 business-day period, to extend the deadline. The EU may not unreasonably
deny the request for extension. When construction is required, the interconnection
of the DGF shall proceed according to milestones agreed to by the parties in the
DGF Interconnection Agreement. The DGF Interconnection Agreement may not
be final until:
a. The milestones agreed to in the DGF Interconnection Agreement are
satisfied;
b. The DGF is approved by electric code officials with jurisdiction
over the interconnection;
c. The Interconnection Customer provides a Certificate of Completion to the
EU. Completion of local inspections may be designated on inspection
forms used by local inspecting authorities; and
d. The Witness Test was successfully completed per the terms and
conditions found in the Agreement.
102 An interconnection System Impact Study is not required when the interconnection
Feasibility Study concludes there is no Adverse System Impact, or when the study
identifies an Adverse System Impact, but the EU is able to identify a remedy without the
need for an interconnection System Impact Study.
103 The parties shall use a form of interconnection Feasibility Study agreement approved by
the Commission.
Chapter 08: TECHNICAL STANDARDS
100 The technical standard to be used in evaluating all Interconnection Requests under
Level 1, Level 2, and Level 3 reviews, unless otherwise provided for in these
procedures, is IEEE Standard 1547. IEEE 1547.2, âApplication Guide for IEEE 1547
Standard for Interconnecting Distributed Resources with Electric Power Systems,â shall
be used as a guide (but not a requirement) to detail and illustrate the interconnection
protection requirements that are provided in IEEE 1547.
Chapter 09: POINT OF COMMON COUPLING
100 To minimize the cost of interconnecting multiple DGFs, the EU or the Interconnection
Customer may propose a single PCC for multiple DGFs located at a single site. If the
Interconnection Customer rejects the EUâs proposal for a single PCC, the Interconnection
Customer shall pay the additional cost, if any, of providing a separate PCC for each DGF.
If the EU rejects the customerâs proposal for a single PCC without providing a written
technical explanation, the EU shall pay the additional cost, if any, of providing a separate
PCC for each DGF.
Chapter 10: RECORDS AND REPORTS
100 An EU shall maintain records of the following for a minimum of 3 years:
1. The total number of and the Nameplate Capacity of the Interconnection Requests
received, approved and denied under Level 1, Level 2, and Level 3 reviews;
2. The number of Interconnection Requests that were not processed within the
timelines established in this rule;
3. The number of Scoping Meetings held and the number of feasibility studies, impact
studies, and facility studies performed and the fees charged for these studies;
4. The justifications for the actions taken to deny Interconnection Requests; and
101 An EU shall provide a report to the Commission containing the information required in
paragraphs (a)-(d) above, on or before February 1st within 90 calendar days of the close
of each year.
Chapter 11: INFORMATION FOR PROSPECTIVE
INTERCONNECTIONCUSTOMERS
100 An EU shall designate a contact person and contact information on its website and for the
Commissionâs website for submission of all Interconnection Requests and from whom
information on the Interconnection Request process and the EU's EDS can be obtained
regarding a proposed DGF. The information shall include studies and other materials
useful to an understanding of the feasibility of interconnecting a DGF at a particular point
on the EU's EDS, except to the extent that providing the materials would violate security
requirements or confidentiality agreements, or otherwise would be contrary to Mississippi
or federal law and regulations. In appropriate circumstances, the EU may require
execution of a confidentiality agreement prior to release of information about the EUâs
EDS.
101 When the EU determines that an Interconnection Request is complete, a modification of
DGF design by the Interconnection Customer other than a Minor Equipment Modification
that is not agreed to in writing by the EU shall require submission of a new
Interconnection Request.
Chapter 12: ADDITIONAL TECHNICAL REQUIREMENTS
100 DGFs shall be capable of being isolated from the EU. For Level 2 and Level 3
interconnection, the isolation shall be by means of a lockable, visible-break isolation
device whose status is clearly indicated and is accessible by the EU. The isolation device
shall be installed, owned and maintained by the owner of the DGF and located between
the DGF and the PCC. A draw-out type circuit breaker with a provision for padlocking at
the draw-out position can be considered an isolation device for purposes of this
requirement. A draw-out type circuit breaker has a switching device capable of making,
carrying and breaking currents under normal and abnormal circuit conditions such as
those of a short circuit. A draw-out circuit breaker can be physically removed from its
enclosure creating a visible break in the circuit. For the purposes of these regulations, the
draw-out circuit breaker shall be capable of being locked in the open, draw-out position.
Level 1 interconnections do not require an external isolation device.
101 A Level 2 or Level 3 Interconnection Customer may elect to provide the EU access to an
isolation device that is contained in a building or area that may be unoccupied and locked
or not otherwise readily accessible to the EU, by installing a lockbox provided by the EU
that shall provide ready access to the isolation device. The Interconnection Customer shall
install the lockbox in a location that is readily accessible by the EU, and the
Interconnection Customer shall permit the EU to affix a placard in a location of its
choosing that provides clear instructions to EU operating personnel on access to the
isolation device. In the event that the Interconnection Customer fails to comply with the
terms of this subsection and the EU needs to gain access to the isolation device, the EU
shall not be held liable for any damages resulting from any necessary EU action to isolate
the Interconnection Customer.
102 Any metering necessitated by a DGF shall be installed, operated and maintained in
accordance with applicable tariffs. Any such metering requirements shall be clearly
identified as part of the DGF Interconnection Agreement executed by the Interconnection
Customer and the EU.
103 The EU shall design, procure, construct, install, and own any Distribution System
Upgrades. The actual cost of the Distribution System Upgrades, including overheads,
shall be directly assigned to the Interconnection Customer. The Interconnection
Customer may be entitled to financial contribution from any other EU customers who
may in the future utilize the upgrades paid for by the Interconnection Customer. Such
contributions shall be governed by the rules, regulations, and decisions of the
Commission.
104 The Interconnection Customer shall design its DGF to maintain a composite power
delivery at continuous rated power output at the Point of Common Coupling at a power
factor within the power factor range required by the EUâs applicable tariff for a
comparable load customer. EU may also require the Interconnection Customer to follow
a voltage or VAR schedule if such schedules are applicable to similarly situated
generators in the control area on a comparable basis and have been approved by the
Commission. The specific requirements for meeting a voltage or VAR schedule shall be
clearly specified in Attachment 3 of the âMississippi Distributed Generator
Interconnection Rule Level 2 and Level 3 Agreement for Interconnection of Distributed
Generator Facilities.â Under no circumstance shall these additional requirements for
voltage support or reactive power exceed the normal operating capabilities of the DGF.
The requirements in this paragraph may be additional to requirements in IEEE 1547.
Chapter 13: DISPUTES
100 A party shall attempt to resolve all disputes regarding interconnection as provided in the
MDGIR promptly, equitably, and in a good faith manner.
101 When a dispute arises, a party may seek immediate resolution through complaint
procedures available through the Commission by providing written notice to the
Commission and the other party stating the issues in dispute.
102 When disputes relate to the technical application of the MDGIR, the Commission may
designate a technical consultant to resolve the dispute. Upon Commission designation,
the parties shall use the technical consultant to resolve disputes related to interconnection.
Costs for dispute resolution conducted by the technical consultant shall be established by
the technical consultant and subject to review by the Commission. The EU and the
Interconnection Customer shall share equally the costs of an outside arbitrator unless they
mutually agree to a different payment arrangement.
103 Pursuit of dispute resolution shall not affect an Interconnection Customer with regard to
consideration of an Interconnection Request or an Interconnection Customer's Queue
Position.
TITLE 39: UTILITIES
PART IV: Mississippi Distributed Generator Interconnection and Net Metering
Distributed Generation
Subpart II: Mississippi Renewable Energy Net Metering Distributed Generation Rule
Chapter 01: Introduction
101 The Mississippi Renewable Energy Net Metering Distributed Generation Rule
(MDGRMDGR) sets forth technical and procedural requirements for Net Metering on
qualified Distributed Generator Facilities (DGFs). These DGFs are also subject to the
requirements of the Mississippi Distributed Generator Interconnection Rule (MDGIR).
Chapter 02: DEFINITIONS
The following capitalized terms, when used in this Rule, shall have the following meanings
unless the context clearly indicates otherwise. These definitions are in addition to those found in
the MGDIR, which also apply to the MDGR.
100 âBilling Periodâ means the monthly billing period used by an Electric Utility (EU) to
measure usage and any excess energy exported by a DGF to the EU, and to bill
customers.
101 âAvoided Cost of Wholesale Powerâ means the cost to an EU2 of electric energy that
the EU would generate itself or purchase from another source, such as from an
organized wholesale power market, but for the purchase from a Renewable Energy Net
Metered Distributed Generation Interconnection Customer (RENMIC DGIC). In
essence, the avoided cost is the marginal cost to produce or purchase one more unit of
electrical energy. When a RENMICDGIC delivers electricity to an EU, the EU will
reduce the equivalent amount of electricity that either is generated at its most expensive
operating plant that is not running for reliability purposes or is purchased from an
organized wholesale power market. For power generated by an EU, the cost avoided
consists of the cost of fuel needed to produce that electricity and the corresponding
portion of the plantâs operation and maintenance costs and shall include an appropriate
average line loss adjustment. For DGICs with solar PV systems, the Avoided Cost of
Wholesale Power and the corresponding average line loss adjustment shall reflect the
daytime energy production of a solar PV system. No capacity credit is given as part of
the calculation of Avoided Cost of Wholesale Power. For an EU that is a member of a
regional transmission organization (RTO), the Avoided Cost of Wholesale Power shall
be the average real-time locational marginal price (LMP) calculated by the RTO for the
EUâs load zone(s). Such LMP may be adjusted to reflect the daytime energy production
of a solar PV system and shall include an appropriate average line loss adjustment. For
DGICs with solar PV systems, such LMP and the corresponding average line loss
adjustment shall reflect the daytime energy production of a solar PV system.
2 An EU is an electric utility within the meaning of Miss. Code Ann. section 77-3-3(d)(i) (Supp 2014).
102 âNon-Quantifiable Expected Benefits Distributed Generation Valueâ means an
temporary adjustment to be included in the Total Benefits Value of Distributed
Generation for benefits of distributed generation that, while expected to occur, are
currently non-quantifiable or difficult to quantify. The Non-Quantifiable Expected
Benefits Distributed Generation Value shall be equal to no more than 2.5 cents per
kilowatt hour, unless and until modified upward or downward based on Mississippi-
specific data, by separate Order of the Commission, and after full notice and hearing.
for no longer than three (3) years after the effective date of this rule, which shall serve
as a proxy for the Actual Benefits of Distributed Generation further defined below. To
provide sufficient financial certainty to qualifying customers that install DGFs, this
Distributed Generation Value shall remain in place for a period of twenty-five (25)
years from the date the customer begins taking net generation service under the EUâs
net generation tariff.
103 âActual Benefits of Distributed Generationâ means actual, quantifiable benefits
realized by installed distributed generation over and above the Avoided Cost of
Wholesale Power, which shall be calculated based upon information derived from the
report of a third party consultant chosen by the Commission (further described below)
and the experience of the utilities since implementation of this rule, as well as any
additional information that may be available in the industry at that time. The
calculation of the Actual Benefits of Distributed Generation shall replace the temporary
Non-Quantifiable Expected Benefits no later than three (3) years following the effective
date of this rule.
103 âLow-to-Moderate Income Benefits Adderâ means an additional amount to be
included in the Total Value Benefits of Distributed Generation that shall flow to the first
1,000 qualifying customers whose household income is at or below 200225% of the
federal poverty level (or similar requirement proposed by the EU to be approved by the
Commission) who is approved to take service under the EUâs net metering generation
tariff. Beginning with the effective date of this rule, the Low-to-Moderate Income
Benefits Adder shall be equal to 2 cents per kilowatt hour. To provide sufficient
financial certainty to qualifying low-to-moderate income customers that install DGFs,
this Low-to-Moderate Income Benefits Adder shall remain in place for a period of
twenty-five (25) fifteen (15) years from the date the a qualified DGIC customer begins
taking net metering service under the EUâs net generation metering tariff.
104 âTotal Benefits Value of Distributed Generationâ means the total amount â
expressed in cents per kilowatt hour - that shall be credited to EU customers as a result
of excess energy exported by a DGF to the EU, which shall include the Avoided Cost of
Wholesale Power plus the Distributed Generation Value Non-Quantifiable Expected
Benefits Adder or the Actual Benefits of Distributed Generation, plus, if applicable, the
Low-to-Moderate Income Benefits Adder, as further outlined in this rule.
105 âExit Feeâ means a fee that is paid by a customer that reduces load by using a DGF and
is intended to compensate the EU in whole or part for the loss of fixed cost contribution
from that customer. Exit fees are not allowed under this Rule, unless otherwise
approved by the Commission.
106 âRenewable Energy Net Metered Distributed Generation Interconnection
Customerâ or âRENMICDGICâ is any electricity customer, such as an industrial,
large commercial, residential or small commercial customer, that generates electricity
on the customerâs side of the meter using a Renewable Energy source. The electricity
customer must own or lease the DGF producing the Renewable Energy on the
electricity customerâs side of the meter in order to qualify as a RENMICDGIC under
this MDGR, unless otherwise approved by the Commission.
107 âNet Generation Meteringâ means measuring the real-time kilowatt-hours supplied by
the EU to the RENMICDGIC and the kilowatt-hours produced by the RENMICDGICâs
DGF and exported to the EU over the applicable Billing Period. Net generation
metering includes the real-time displacement of kilowatt-hours that otherwise would be
provided by the EU by kilowatt-hours that were generated by the RENMICDGICâs
DGF. An EU may employ a multi-channel meter for separately measuring the
RENMICDGICâs electric usage and excess energy exported to the EU. Special metering
requirements are obviated with the use of advanced metering infrastructure or âsmart
meters.â
108 âRenewable Energyâ means electric energy produced from solar technologies, wind
energy, geothermal technologies, wave or tidal action, hydro-power facilities, hydrogen,
and biomass. Any energy derived from fossil fuels is not considered renewable and
does not qualify under the MDGR.
109 âBiomassâ means a power source that is comprised of combustible solids or gases from
forest products, manufacturing waste, or byproducts; products from agricultural and
orchard crops; waste or co-products from livestock and poultry operations; waste or
byproducts from food processing; urban wood waste; municipal liquid waste treatment
operations; and landfill gas.
Chapter 03: NET METERING GENERATION REQUIREMENTS
100 This MDGR sets forth the Net Metering Generation requirements that apply to EUs that
have customers who self-generate electricity with Renewable Energy on the customerâs
side of the EUâs meter that wish to Net Meter, as indicated by the customer on the
Standard Application. These customers are referred to as RENMICDGIC s in this Rule.
101 All EUs shall offer Net Metering Generation to any customer that seeks to generate
electricity on the customerâs side of the EUâs meter using Renewable Energy sources,
provided:
1. For residential customers, Net Generation Metering nameplate direct current
capacity of the aggregated DGFs at the customerâs premises shall be limited to the
lesser of 110% of the customerâs annual peak demand or 20 kW and shall meet
the requirements of the MDGIR;
2. For non-residential customers, Net Generation Metering nameplate direct current
capacity for the aggregate DGFs at the customerâs premises shall be limited to the
lesser of 110% of the customerâs annual peak demand or 2 MW and shall meet
the requirements of the MDGIR.
3. In cases where Battery Energy Storage Systems (âBESSâ) are paired with a DGF,
the capacity of the BESS will not affect the total nameplate capacity limits of a
customerâs DGF under this MDGR.
102 EUs may refuse additional net generation metering requests if the total net generation
metering direct current capacity in kW, as reported through these requirements, exceeds
at any time 3 percent of the EUâs total system peak demand expressed in kW recorded
during the prior calendar year.
103 Each EU shall develop a tariff for Net Generation Metering and interconnection policies
in concordance with this MDGR and the MDGIR. Each EU shall make Net Generation
Metering available to eligible RENMICDGICs on a first-come, first-served basis until
such time as the aforementioned cap has been reached.
104 An EU shall provide Net Generation Metering at non-discriminatory rates that are
identical, with respect to rate structure and level, retail rate components, and any
monthly fixed charges, to the rates that a RENMICDGIC would be charged if not a
RENMICDGIC, unless otherwise approved by the Commission.
105 In each Billing Period, energy supplied to the RENMICDGIC from the EU as recorded
on the EUâs bi-directional net meter or smart meter will be billed using appropriate
commission-approved rate and rider schedules. This provision means that energy self-
supplied by the RENMICDGIC, up to the amount supplied from the EU to the
RENMICDGIC (e.g., through the recording of meter Channel 1) will be credited to the
RENMICDGIC at the full retail rate (i.e., effectively displacing energy supplied from
the EU). During that same Billing Period, any excess energy supplied from the
RENMICDGIC to the EU and recorded on the EUâs bi-directional net meter in kWh
(e.g., through meter Channel 2) will be credited on the RENMICDGICâs bill at the
applicable Total Benefits Value of Distributed Generation expressed in cents per kWh
and shall be accounted for through the EUâs fuel adjustment clause. The customerâs
monthly bill will be the total of billing for any usage (i.e., as recorded on meter Channel
1) subject to any customer charge and/or minimum bill provisions in the EUâs rate and
rider schedules less any credit due to the customer from excess energy exported to the
EU (i.e., as recorded on meter Channel 2). If the sum total of the monthly bill is
negative, any such amount will be carried over to the next Billing Period and applied to
any charges arising during the subsequent Billing Period.
106 Beginning with the effective date of this rule, Total Benefits Value of Distributed
Generation shall temporarily be equal to the Avoided Cost of Wholesale Power plus the
Distributed Generation Value Non-Quantifiable Expected Benefits. Further, the
Distributed Generation Value Non-Quantifiable Expected Benefits shall be equal to 2.5
cents/kWh, unless and until modified upward or downward based on Mississippi-
specific data, by separate Order of the Commission, and after full notice and hearing.
which may be modified downward at any time by order of this Commission, should the
Commission find it is in the public interest to do so. Within sixty (60) days of the
effective date of this rule, each EU shall file with the Commission revised net
generation metering tariffs consistent with the provisions of this revised rule for
consideration and approval by the Commission.
107 In the calculation of Total Benefits of Distributed Generation, Non-Quantifiable
Expected Benefits shall be replaced and subsumed by Actual Benefits of Distributed
Generation no later than three (3) years following the effective date of this rule. In
order to develop a calculation for Actual Benefits of Distributed Generation within
that three-year timeframe, the Commission shall cause a study to be performed by an
independent consultant beginning no earlier than one year after the effective date of
this rule, the costs of which shall be paid by each EU whose rates are regulated by the
Commission under the Mississippi Public Utilities Act, §§ 73-3-1 et seq., and
recovered through each such EUâs net metering tariff. Said independent consultant
will work collaboratively with the utilities and gather information from other
stakeholders to provide the Commission with guidance in developing a calculation of
benefits that can be demonstrated to have been realized and quantified as a result of
the adoption of distributed generation in Mississippi. No later than three (3) years
from the effective date of this rule, the Commission shall instruct each EU to file
modifications to their net metering tariffs to reflect a calculation of Actual Benefits of
Distributed Generation consistent with conclusions of the study and data provided by
the EUs.
107 Each new Billing Period shall begin with zero kWh credits to the RENMICDGIC;
however, subject to the provisions above, the customer may carry over any value of
energy credit arising from the prior Billing Period(s). When a customer closes his or
her account with the EU, if the RENMICDGIC has accumulated a dollar balance as a
result of excess energy delivered to the EU, any such balance, net of costs owed to the
EU, shall be paid to the RENMICDGIC.
108 Credit for any excess energy exported to the EU shall not be applied to reduce any fixed
monthly customer charges or minimum bill provisions imposed by the EU under
Commission-approved rate and rider schedules.
109 An EU shall offer a RENMICDGIC the choice of a time differentiated energy tariff rate
or a non-time-differentiated energy tariff rate, if the EU offers the choice to customers
in the same rate class as the RENMICDGIC. If a RENMICDGIC uses a retail billing
arrangement that has time- differentiated rates, the EU shall net any production from the
DGFs against the customerâs consumption within the same time-of-use period in the
Billing Period and any excess energy exported to the EU will be credited as described
above.
110 Any renewable energy credits (RECs) created by the RENMICDGIC are and shall
remain the property of the RENMICDGIC, unless otherwise approved by the
Commission. The EU shall not charge any back-up, standby, or Exit Fees to a
RENMICDGIC, unless otherwise approved by the Commission.
111 An EU shall not charge a RENMICDGIC any fee or charge, or require additional
equipment, insurance or any other requirement, unless the fee, charge, or other
requirement is specifically authorized in this MDGR or the MDGIR, or the fee would
apply to other customers in the same rate class that are not RENMICDGICs, or unless
otherwise approved by the Commission.
112 All RENMICDGICs must be electrically interconnected with their EU pursuant to the
provisions of the MDGIR. All rules and regulations for interconnected DGFs within the
MDGIR apply to RENMICDGICs. Any Distribution System Upgrades, including
additional equipment needed that is associated with the export of electricity, shall be at
the RENMICDGICâs expense, per the MDGIR.
113 As a further requirement under this rule, each Each EU shall file with the Commission
within three months of the effective date of this revised rule the EUâs plan inform its
customers, whether through a website, a bill insert, or other form of communication, of
the opportunities available under the MDGR to interconnect DGFs and receive
compensation for excess energy delivered to the grid.
114 Nothing in this document shall abrogate any person's obligation to comply with all
applicable Federal or State laws, rules or regulations, including the MDGIR.
Chapter 04: METERS AND METERING
100 A RENMICDGIC shall be equipped with metering equipment that can measure the
flow of electricity in each direction at the same time. This is typically may be
accomplished through the use of advanced metering infrastructure, or a single bi-
directional meter that records customer usage as well as excess energy exported to the
EU (e.g., energy supplied to the customer net of the output of the RENMICDGIC is
measured on Channel 1 and excess energy supplied by the RENMICDGIC to the EU in
excess of the customerâs requirements is measured on Channel 2).
101 An EU may choose to use an existing electric revenue meter if the following criteria are
met:
1. The meter is capable of measuring the flow of electricity both into and out of the
RENMICDGIC at the same time; and
2. The meter is accurate to within plus or minus five percent when measuring excess
energy flowing from the RENMICDGIC to the EU.
102 If the RENMICDGICâs existing electric revenue meter does not meet the requirements
above, the EU shall install a new revenue meter for the RENMICDGIC, at the
RENMICDGICâs expense, within 10 business days after the interconnection agreement
is executed and approved. If the EU offers a time-differentiated rate chosen by the
RENMICDGIC, the meter shall have the capability to appropriately record energy
flows in each direction during any time-differentiated period.
103 Any subsequent revenue meter change will be at the EUâs expense, meaning such meter
expense will not be charged to an individual RENMICDGIC but shall become part of
the EUâs overall cost of service and subsequent revenue requirement.
Chapter 05: REPORTING REQUIREMENTS
100 Each EU with one or more RENMICDGICs connected to its grid shall submit to the
Mississippi Public Service Commission a Net Generation Metering report within 90
days of the end on or before March 1st of each calendar year. The report shall include
the following information regarding RENMICDGICs during the reporting period:
1. The total energy expressed in kilowatt-hours supplied to the EUâs grid by
RENMICDGICs and a description of any estimation methodology used;
2. The total number of RENMICDGICs that were paid for excess energy exported to
the EU at the end of any Billing Period(s) during the prior calendar year;
3. The total dollar amount by month that the EU paid to RENMICDGICs for excess
energy exported to the EU during the prior calendar year;
4. The total number of net generation metering DGFs by resource type that were
interconnected at the end of the prior calendar year;
5. The total rated nameplate direct current generating capacity of net metering
generation DGFs installed during the prior calendar year broken out by resource
type; and
6. The percentage of the EUâs total system peak demand from the prior calendar
year represented by the total rated nameplate direct current generating capacity of
net metering generation DGFs.
7. The total number of DGICs who received the Low-to-Moderate Income Benefits
Adder that calendar year.
101 For purposes of these reporting requirements, any estimates shall be made using
Commission-approved protocols unless no such protocols are available, in which case
the estimates shall be accompanied by detailed calculations demonstrating how the
estimates were made.
Chapter 06: CUSTOMER PROGRAMS
100 While the Commission recognizes that it cannot order an EU to construct or acquire
specific resources, the Commission finds that economic benefits warrant reasonably
incentivizing energy independence through cost reductions for renewable energy for K-
12 public schools through power purchase agreements, renewable energy for low-to-
moderate income residential customers and residential battery storage systems that can
accommodate and are compatible with any existing or future EU demand side
management or demand response programs. Any renewable energy for public school
programs or low-to-moderate income residential renewable energy programs will be
subject to the three percent (3%) participation cap described, previously, herein;
however, nothing herein prevents an EU from extending these programs if it chooses.
These programs should begin on January 1, 2023, and should continue for no more than
five (5) years.
101 Compliance with tariffs implementing a renewable energy program described above
and the execution and filing of a power purchase agreement shall be deemed sufficient
to satisfy any certificate requirements subject to Commission jurisdiction and authority.
102 Public Schools participating in any solar for public schools program are admonished to
treat any savings or revenues as supplementing, not supplanting, school budgets related
to educational expenses and investments focused on the classroom, such as classroom
supplies.
103 EUs should be allowed to recover all reasonable and prudent costs incurred by them
and resulting rates shall reflect on a prospective basis the reduction in energy sales
volume that will result from all distributed generation. EUs all shall be allowed to
recover all investments relating to this rule and any programs discussed above,
including an opportunity to earn a reasonable return thereon. Such investments shall
include, but not be limited to, equipment, incentives, marketing and delivery, direct
installation costs, and any administration costs.
Chapter 076: SAFETY AND CONSUMER PROTECTION WORKING GROUP
CONSUMER PROTECTIONS
100 In an effort to foster continued monitoring and consideration of the fairness and efficacy
of this rule, order to ensure adequate safeguards for safety and consumer protection, a
the joint working group shall be established between representatives of the
Commission, the Mississippi Public Utilities Staff, the Office of the Mississippi
Attorney General, and other qualified stakeholders, as identified and requested by the
working group. Prior to January 1, 2017, the working group shall establish and present
to the Commission an initial set of consumer protection and safety standards and
guidelines related to the installation and use of distributed generation systems.
Thereafter, the working group shall reconvene as necessary to discuss additional issues
related to net metering as they arise, and to present shall meet annually to identify and
discuss issues related to net generation that may warrant further Commission attention
and/or review. Members of the Commission Staff and Public Utilities Staff who
participated in the working group shall present any joint any recommendations on such
issues to the Commission by January 30th each year.
101 In order to offer all customers some level of consumer protection, any entity interacting
with customers in any transaction or proposed transaction related to this rule or any
program or implementing tariff associated herewith, including but not limited to solar
developers and solar installers, shall take the following actions, as applicable:
a. Must file with the Commission a point of contact to whom the Commission may
direct customer complaints for resolution;
b. Must register with the Secretary of State to do business in Mississippi and list a
registered agent for service of process; and
c. Must file annually with the Commission, and provide a copy to the consumer
protection division of the Office of the Mississippi Attorney General, any
marketing material with attestation to its accuracy.
Chapter 087: REOPENER
101 Five years from the effective date of this Rule, the Commission shall open a new docket
to assess the efficacy and functionality of the MDGR, and make any subsequent
revisions or modifications of the Rule that may be deemed necessary at that time. The
Commission may revisit this Rule five years from its effective date.