6 MAC Pt. 11, R. 2.21
Close-Out Process
Cite as 6 Miss. Admin. Code Pt. 11, R. 2.21
Close-Out Process.
A.
The close-out process encompasses a series of activities to verify that GCRF
funds have been properly spent and that all GCRF administrative actions and all
required work on the project has been completed in a timely and acceptable
manner.
B.
The close-out process should begin when the following criteria have been met:
(i.)
All costs to be paid with program funds have been paid, including any
unsettled third- party claims.
(ii.)
The recipient has fulfilled all its responsibilities under the grant
agreement. This includes injection of all matching funds, all private
investment,
achieving
all
performance
metrics
and
all
job
creation/retention commitments (where applicable).
C.
Close-out packages bearing the original signatures of the designated signatory
officials (one original copy) and submission of the Certificate of Completion (two
original copies) are due to MDA within 30 days after completion of the project.