6 MAC Pt. 3, R. 4.9
Guaranteed Savings
Cite as 6 Miss. Admin. Code Pt. 3, R. 4.9
Guaranteed Savings. The energy savings plus related cost savings are guaranteed by
the ESCO and must be used to repay the cost of the project. The guaranteed savings must be
more than sufficient to pay the total costs of the project over the guarantee period. The terms of
any shared savings or energy saving performance contract entered into must contain a guarantee
of savings clause from the performance contractor.