6 MAC Pt. 4, R. 4.21
Close-Out Process
Cite as 6 Miss. Admin. Code Pt. 4, R. 4.21
Close-Out Process. The close-out process encompasses a series of activities to verify
that DIP Funds have been properly spent and that the applicant has completed the elements of its
program in a timely and acceptable manner.
A. The grantee recipient must submit all financial, performance, and other reports required
as a condition of the grant.
B. Close-Out Packages bearing the original signatures of the designated signatory officials
are due to MDA within 30 days after completion of the project including investment
commitment and job creation. Failure to submit Close-Out Packages in a timely manner
will result in the Community Services Division holding any and all pending Requests for
Cash, Close-Outs and new project approvals for the grant recipient.
C. The grantee recipient must retain all records for a period of five years from the date the
State executes the Certificate of Completion.
D. The tasks involved in closing out a grant include:
(i) Resolution of all monitoring findings;
(ii) Submission of close-out report (one original copy);
(iii) Submission of Certificate of Completion (three originally signed copies);
E. The close-out process should begin when the following criteria have been met or will be
met shortly:
(i) All costs to be paid with program funds have been paid, including any unsettled third-
party claims, with the exception of close-out costs, such as the final administration costs.
(ii) The recipient has fulfilled all of its responsibilities under the Funding Agreement.
This includes injection of all local cash and in-kind services, other State and/or Federal
funding, all private investment, and job creation/retention (where applicable).
F. Delays in completing close-out can result in the denial of future requests with
Community Services.