MAC Pt. 18, R. 5.5.15
Expanded Polystyrene (EPS) Aggregate Systems
Cite as Miss. Admin. Code Pt. 18, R. 5.5.15
Expanded Polystyrene (EPS) Aggregate Systems.
1.
General: The EPS Aggregate system utilizes bundles of expanded polystyrene aggregate
to replace rock aggregate in a subsurface disposal system. Effluent is distributed via a 4
inch perforated pipe incorporated into the center of one EPS bundle. System
configurations of multiple bundles will incorporate one bundle run containing the 4 inch
perforated pipe in conjunction with bundles containing only EPS aggregate. This 4 inch
perforated pipe receives the treated effluent for distribution throughout the trench. The
expanded polystyrene aggregate must be contained in a material that is resistant to the
effects of wastewater, will prevent the loss of aggregate from the container and strong
enough to retain the shape of the bundles during system installation and backfilling. All
EPS Aggregate Systems must be installed by a factory-trained installer that is an
authorized representative of the manufacturer.
2.
Sizing: The EPS aggregate replacement systems shall be sized in accordance with Table
6 (Horizontal Configurations) and Table 7 (Triangular Configurations).
3.
Construction:
a.
The EPS Aggregate System absorption trenches shall be a minimum of 24 inches
and a maximum of 36 inches in width.
b.
The bottom of the trenches and the distribution lines shall have a grade from level
to no greater than two inches fall per 100 feet.
c.
The grade shall be measured from the trench bottom and not the effluent
distribution line encased in the EPS bundle.
d.
The EPS Aggregate system shall be covered with an approved cover material
before backfilling. Covering material shall consist of craft paper or other bio-
degradable product approved and/or supplied by the manufacturer.
4.
Distribution of Effluent – EPS Aggregate System:
a.
When a change in elevation of the disposal trench is required, a distribution box,
connecting lateral or crossover must be used. At the point where a crossover line
leaves a lateral, the trench for the crossover line shall be dug no deeper than the
top of the distribution pipe in the preceding trench so that an undisturbed block of
earth will remain in place for the full depth of the system. [See Figure 14.] The
invert of the crossover must be at least four inches lower than the invert of the
septic tank outlet line.
b.
Distribution boxes may be used to connect the effluent line to the effluent
distribution lines. The distribution box shall be level and supply all lines equally.
Field lines must be equal lengths when served by one distribution box. Non-
perforated rigid pipe shall exit the distribution box for a minimum of five feet at
level grade before the effluent distribution line (perforations) begins.
5.
Absorption Beds – EPS Aggregate Systems: Absorption beds may be constructed using
the EPS Aggregate system (Horizontal configuration only):
a.
Absorption beds and trenches should be located a minimum of 10 feet from any
trees.
b.
The amount of linear footage required for EPS horizontal systems shall be the
same as for trench configurations. [See Table 6.] The bottom of the bed should
have a relatively level grade; the grade within the bed shall not exceed the grade
allowed for EPS trench installations. EPS triangular systems shall not be used in
bed configurations.
c.
The EPS bundles shall be placed side by side in the bed. The number of bundles
will depend on the linear footage required and the width of the bed to be
constructed.
d.
Care should be taken to prevent heavy machinery from damaging the bed during
backfilling.
e.
The effluent must be equally distributed to the bed by means of a distribution box
or with a pipe manifold.
6.
Homeowners may install 1-14 configuration EPS, provided that all applicable regulations
of the Department are observed.